|
|
|
|
Opinions Released December 30, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON TUESDAY, DECEMBER 30, 2003
-
Breaux v. Thurston,
No. 1011655 (Ala.
Dec. 30, 2003)
(medical malpractice;
standard of care; jury instruction; retention case/negligent or wanton
failure to remove all foreign objects after surgery; Sheila Bailey Thurston
decided to undergo a bariatric procedure known as gastric bypass.
When she first consulted Dr. Breaux she weighed 283 pounds. When
the bypass surgery was performed at Cooper Green Hospital a little more
than eight months later, on December 21, 1994, she weighed 310 pounds.
In essence, the surgery rerouted portions of Ms. Thurston's intestines
to shorten the length available for digestion and absorption, significantly
reduced the size of her stomach, and reconnected her stomach to the intestine
by a small opening. Dr. Charles W. Breaux was assisted by Dr. Harris,
a third-year resident at Cooper Green Hospital, registered nurse Cynthia
Venton, functioning as the circulating nurse, and Wylie King, functioning
as the scrub nurse or operating-room technician. The hospital's "Operating
Room Policies and Procedures" provided, with respect to "Instrument Count,"
that "[t]he purpose of an instrument count is to prevent the possibility
of any foreign object being left in a body cavity." Venton and King
did not perform the required instrument count immediately before Ms. Thurston's
surgery. When such a preoperative count is performed, Dr. Breaux
often has not yet entered the operating room and is in some other part
of the hospital attending to other duties or patients. At the end
of the operation, but before Dr. Breaux closed the abdominal incision,
Venton and King jointly conducted the required postoperative count and
reported to Dr. Breaux that it was "correct," meaning that the postoperative
count of each category of surgical instruments matched exactly the preoperative
count. Dr. Breaux did not participate in the counts and contended
that "[t]he nurses actually don't want any interference when they are counting,
so that they are not distracted and don't lose count of what they are doing."
Dr. Breaux further explained that a surgeon does not make any attempt to
count the instruments placed in a patient and then removed, because of
the need to concentrate on the performance of the surgical procedure.
Ms. Thurston did well and lost weight. She moved to Nevada.
During the late winter of 1996, she started having pain on her left side.
She consulted Dr. Lynn Greenhouse, a physician in Nevada specializing in
internal medicine. The X-ray films from a barium enema Dr.
Greenhouse ordered revealed "right in the middle of the large intestine
... a Babcock-type surgical clamp." Dr. Greenhouse referred Ms. Thurston
to Dr. Myron J. Gomez, a general surgeon in Nevada, for removal of the
clamp. During that surgery, Dr. Gomez found that the clamp had eroded
into the small bowel; he removed the clamp and repaired the bowel.
Thurston filed a medical-malpractice action against Dr. Charles W. Breaux
and Jefferson Clinic, P.C., a professional corporation through which a
group of doctors, including Dr. Breaux, provided physicians for the staff
of Cooper Green Hospital. The case was originally tried before a
jury in October 1999, against Dr. Breaux, the Jefferson Clinic, P.C., Cooper
Green Hospital, and two surgical nurses, Cynthia Venton and Wylie King.
The jury returned a $78,000 verdict against the defendants, but the trial
judge, realizing he had committed an error, subsequently ordered a new
trial. The defendants appealed. The Supreme Court affirmed the grant
of a new trial. Breaux v. Bailey, 789 So.2d 204 (Ala. 2000).
When the case was retried on February 19, 2002, only Dr. Breaux and the
Jefferson Clinic remained as defendants, Cooper Green Hospital, Venton,
and King having settled the claims against them for a total of $100,000.
The jury returned a verdict against Dr. Breaux and the Jefferson Clinic
in the amount of $300,000. The trial court entered a judgment on
the verdict and later denied the defendants' postjudgment motions for a
judgment as a matter of law, a new trial, or a remittitur. Dr. Breaux
and the Jefferson Clinic again appealed. HOLDING: The
Supreme Court reversed. The Court noted that neither Dr. Greenhouse
nor Dr. Gomez testified during their depositions concerning the medical
standard of care that should apply to abdominal surgery and that the only
testimony presented at trial concerning the applicable medical standard
of care, and whether it had been breached, came from Dr. Breaux and Dr.
Edward Waites, a general surgeon from Atlanta presented by Dr. Breaux.
Dr. Waites testified that, based on Dr. Breaux's description of what he
had done in visually and manually exploring for any retained objects and
then relying on the nurses' count, Dr. Breaux had met the standard of care.
The Court held that while the presence of the retained object is prima
facie evidence of negligence by the surgeon in carrying out that responsibility,
the presence of the retained objected does not, however, establish negligence
per se. The Court wrote: "Rather, it serves to shift the burden to
the defendant surgeon to show that he or she was not negligent because
he or she fully complied with the statutorily defined standard of care.
The fact that the operating-room nurses responsible for counting objects
before and after the surgery report a final "correct" count does not in
itself relieve the surgeon of liability. Rather, for a jury question
to be presented, there must be expert testimony establishing the medical
standard of care for attempting to prevent the retention of foreign objects
in the body after surgery. To the extent that the surgeon relied
on the nurses' counts, there must be expert testimony establishing that
such a practice is within the standard of care. If, after the plaintiff
offers prima facie evidence of negligence by a showing that a foreign object
was retained in the body after surgery and the burden of proof shifts to
the surgeon, the standard of care is clearly established by expert testimony
and there is substantial evidence indicating that the surgeon complied
with all components of that standard of care, a jury question is presented
as to whether the surgeon was in fact negligent." The Court held
that there were numerous errors in the jury instructions that collectively
constituted reversible error. Primarily, the Court found that there
was clearly the "potential for confusing the jury" in the instruction that
the nurses' count amounted "only to an added precaution" by Dr. Breaux
to "ensure that he had properly performed his duty to remove the instruments
from the patient." The Court wrote: "[P]roof of a retained
surgical instrument, in the absence of expert medical testimony presented
by the plaintiff, constitutes only prima facie evidence of negligence on
the part of the surgeon. The effect of such prima facie evidence
is to shift to the surgeon the burden of going forward with the evidence,
to the end that the surgeon has the opportunity to overcome the prima facie
evidence by establishing, through expert medical testimony, the elements
of the applicable medical standard of care, and that he satisfied all of
them. If no contradictory expert medical testimony is introduced,
however, that prima facie evidence is sufficient to sustain a verdict against
the surgeon. The jury instruction in this case, as duly objected
to, and in the face of the expert testimony presented, clearly had the
potential to confuse the jury." The Court remanded the case to the
trial court for further proceedings.)
*Download or view
PDF version of opinion*
-
Ex parte Western
Mental Health Ctr.,
Nos. 1011990 &
1021481 (Ala. Dec. 30, 2003)
(discovery; psychotherapist-patient
privilege; mental anguish; On June 4, 2001, P.H. sued James B. Koikos,
owner of The Bright Star Restaurant, Inc. (hereinafter referred to as "Bright
Star"), where P.H. worked, alleging assault and battery and the tort of
outrage. P.H. maintained that, as a result of Koikos's alleged conduct,
she suffered physical injuries, financial hardship, and mental anguish.
P.H. later amended her complaint to allege negligence and wantonness.
During discovery, Koikos filed a request for the production of information
regarding P.H.'s alleged mental suffering. P.H. objected to the production
of the information on the grounds of the psychotherapist-patient privilege.
Subsequently, P.H. again amended her complaint to add Bright Star as a
defendant, and to demand workers' compensation benefits. In response
to discovery concerning P.H.'s medical treatment, Koikos and Bright Star
served a subpoena upon Western Mental Health Center, a division of the
Jefferson County Board of Health (hereinafter referred to as "Western"),
a nonparty to the litigation, requesting that Western produce all medical
records on the care and treatment of P.H. Western objected; it moved
the trial court to quash the subpoena, or, in the alternative, to issue
a protective order. Koikos and Bright Star responded, arguing that
because P.H. had placed her mental state at issue, they would be prejudiced
if they were unable to obtain the records. The trial court
overruled Western's objections and ordered it to produce the requested
records. It also entered a protective order, stipulating that only
persons and entities having current or prior connections to either the
records or the pending litigation would have access to the records.
The order further stated that all records produced would be placed under
seal and would not become part of the public record of the case.
Western petitioned the Supreme Court for a writ of mandamus directing the
Jefferson Circuit Court, Bessemer Division, to vacate that order.
In a separate case, M.S. sued James Kevin Stewart and others as a result
of injuries she sustained in an automobile accident. M.S. contends
that she sustained property damage, serious physical injuries, emotional
anxiety and distress, other pain and suffering, and ongoing medical costs
as a result of Stewart's negligence or wantonness. M.S. also claimed
that she was rendered permanently disabled as a result of the accident.
In response to discovery concerning M.S.'s injuries, Stewart served a subpoena
upon Western, a nonparty to the litigation, requesting that Western produce
records relative to the care, treatment and confinement of M.S. Western
objected, and it moved for the court to quash the subpoena. Stewart
filed a response to its motion, and the trial court conducted a hearing
on the matter. The trial court overruled Western's objections and
ordered that it produce the requested documents. Specifically, the
circuit court issued an order requiring Western to produce all records
relating to M.S., "[keeping them] confidential between the parties and
their attorneys"; however, this order did not "preclude the utilization
of the information obtained by these records ... as evidence in open court
at hearings in this present action, or at the trial of this case."
As in the other case, Western petitioned the Supreme Court for a writ of
mandamus directing the Jefferson Circuit Court to vacate its order and
to quash the subpoena. HOLDING: The Supreme Court granted
the writs of mandamus. The Court noted that Alabama has not recognized
an exception to the psychotherapist-patient privilege when, in civil actions
such as these, the plaintiff merely alleges mental anguish. The Court
held that by merely alleging mental anguish and emotional distress the
plaintiffs in these cases have not waived the psychotherapist-patient privilege
conferred by Ala. Code §34-26-2. The Court held that Stewart
failed to include any evidence demonstrating that mental-health records
relating to M.S. held by Western are necessary to Stewart's defense in
this action. Therefore, Stewart "failed to show that any constitutional
right has been violated by the retention of the privilege legislatively
extended to the [plaintiff's] medical records." The Court held that the
records the trial courts ordered Western to produce are privileged and
confidential and are not subject to production under the facts of these
cases.)
*Download or view
PDF version of opinion*
-
Shiv-Ram, Inc. v.
McCaleb,
No. 1012112 (Ala.
Dec. 30, 2003)
(punitive damages;
excessive award; clear and convincing evidence; Plaintiff was injured when
she hit her foot on a sharp piece of metal protruding from the bed in a
motel room. The plaintiff and her husband sued, alleging negligence,
wantonness, breach of contract, and loss of consortium. The case
was tried before a jury in the Calhoun Circuit Court. The jury returned
a verdict in favor of the plaintiff, awarding compensatory damages of $176,572.82
and punitive damages of $500,000.00. The jury returned a verdict
in favor of the defendant as to the plaintiff's husband's loss-of-consortium
claim. The defendant filed postjudgment motions pursuant to Rules
50 and 59, Ala.R.Civ.P., seeking a judgment as a matter of law, a new trial,
or a remittitur of the damages. The trial court denied those motions.
HOLDING:
The Supreme Court affirmed. The Court held that even if it were to
overrule Henderson v. Alabama Power it would not resurrect
the "old" statutory punitive-damages cap of $250,000 set forth in the former
Ala. Code §6-11-21. The Court concluded that there was substantial
evidence of wantonness and clear and convincing evidence that the defendant
acted with a reckless or conscious disregard of the rights or safety of
others in its conscious omission of its duty to furnish safe premises to
the plaintiff. The Court stated that had the defendant pursued any
of the opportunities it had to fulfill its duty to furnish safe premises
that its guests might use in the ordinary and reasonable way without danger,
it would have protected guests such as the plaintiff from what was in fact
a prevalent, dangerous defect in the king-sized beds in the motel.
Instead, the Court concluded, the defendant chose to turn a blind eye and
a deaf ear to the situation and to forgo making even the most cursory inspections
or inquiries concerning the safety of the guest rooms. The Court
stated that had the defendant made a reasonable inspection, or had it made
any inquiry of either of the previous owners, it would have readily learned
of the dangers inherent in the structures of the king-sized bed it was
offering its guests. The Court concluded that the defendant was sufficiently
alerted during the three and one-half months preceding the purchase of
the motel of the possibility, if not probability, of potential safety hazards
in the guest rooms. The Court reviewed the various BMW and
Green
Oil factors and concluded that the punitive damages were not excessive,
finding, among other things, the ratio of punitive damages to compensatory
damages to be reasonable.)
*Download or view
PDF version of opinion*
--(A clarification of this decision
was released on application for rehearing on April 2, 2004. That
clarification is also available on the Wallace, Jordan, Ratliff & Brandt,
L.L.C. web site.)--
-
Kinney v. Williams,
No. 1020412 (Ala.
Dec. 30, 2003)
(fraud; negligent
or mistaken misrepresentation; The Adairs are a married couple. So
are the Kinneys. Mr. Adair and Mrs. Kinney are brother and sister.
The two couples agreed to cooperate in the purchase of a certain parcel
of land about five acres in size so that one couple could build and live
on one half and the other couple could build and live on the other half.
A paved road bordered the north end of the property. The couples'
inquiries led them to believe the road was private, not public. The
private character of the road was important to both couples because they
wanted privacy and quiet. After some preliminary negotiations, the
Kinneys contracted in writing to buy the property from its owner, one Marcinowski,
and the Adairs orally agreed with the Kinneys to buy one-half of the property
from the Kinneys. The Kinneys and Marcinowski employed defendant
Williams to prepare the deed from Marcinowski to the Kinneys and to obtain
the title insurance. The Kinneys and the Adairs disclosed their mutual
interest in and plans for the property to Williams. The couples also
told Williams the importance of the private character of the road along
the north end of the property. Williams also served as the closing
agent for the sale by Marcinowski to the Kinneys. The Adairs as well
as the Kinneys attended the closing of that sale. There Williams
assured both couples that the road was private, not public; and Marcinowski
and the Kinneys closed the sale to the Kinneys. Several weeks later,
in accordance with the couples' oral agreement, the Adairs bought half
of the property from the Kinneys. Months thereafter, when the Adairs
tried to stop neighbors from using the road, the Adairs learned that it
was public, not private. Among the claims the Adairs asserted in
their action against Williams were fraud theories of negligent misrepresentation
and innocent misrepresentation. In support of these theories and
in opposition to Williams's motion for a summary judgment, Mr. Adair testified
that, but for Williams's assurances that the road was private, not public,
the Adairs would not have bought their half of the property. He testified
that they would not have bought the property had they known that the road
was public or that its private status was uncertain. The sole ground
of Williams's motion for a summary judgment on the Adairs' claims was that
the absence of an attorney-client relationship between Williams and the
Adairs deprived them of standing to sue. The trial court granted
the motion for summary judgment. HOLDING: The Supreme
Court reversed. The Court held that although Williams was not the
Adairs' attorney, he knew their interest in the property and in the private
status of the road, and he directed his misrepresentations to the
Adairs as well as to his clients the Kinneys. Therefore, the Court
held that the trial court erred in entering a summary judgment in favor
of Williams on the Adairs' fraud claims.)
*Download or view
PDF version of opinion*
-
Ex parte Sharp,
Nos. 1020781 &
1020852 (Ala. Dec. 30, 2003)
(criminal; appellate
procedure; Jason Michael Sharp was indicted for capital murder.
Before trial, he moved to suppress statements he had made to the police.
Judge Laura W. Hamilton granted Sharp's pretrial suppression motion.
Sharp then moved the court to dismiss the indictment, arguing that the
indictment was based on the suppressed statements. On May 9, 2002,
the district attorney volunteered to reindict Sharp without the use of
the statements and agreed to have the grand jury proceedings resulting
in the indictment recorded and transcribed, and the trial court directed
that the grand jury proceedings be transcribed. In May 2002, Sharp
was reindicted for capital murder; however, the grand jury proceedings
were not recorded and transcribed. Sharp filed an amended motion
to dismiss the second indictment because the proceedings were not recorded
and transcribed. On September 20, 2002, Judge Hamilton issued a written
order directing the district attorney to reindict Sharp yet again
and to record and transcribe the proceedings. Judge Hamilton also
stated that if the district attorney failed to comply he was to appear
before the court on November 20, 2002, and show cause why he should not
be held in contempt. On October 25, 2002, the State sought
to have Judge Hamilton recuse herself from the case. On November
18, 2002, Judge Hamilton issued an order declining to recuse herself.
On the same day, the State petitioned the Court of Criminal Appeals for
a writ of mandamus directing Judge Hamilton to recuse herself and for a
writ of prohibition directing Judge Hamilton to vacate her September 20,
2002, order requiring the district attorney to have the grand jury proceedings
recorded and transcribed. On January 31, 2003, the Court of Criminal
Appeals granted the State's petition for the writ of prohibition and, without
opinion, denied the State's petition for a writ of mandamus. Sharp
and Judge Hamilton filed separate petitions for writ of mandamus to the
Supreme Court seeking a writ of mandamus instructing the Court of Criminal
Appeals to vacate its order granting the State of Alabama's petition for
a writ of prohibition. HOLDING: The Supreme Court granted
the petitions. The Court held that the Court of Criminal Appeals
erred in accepting the State's petition for the writ of prohibition as
timely. The Court concluded that the petition should have been filed
within the seven-day period set forth in Rule 15.7, Ala.R.Crim.P.)
*Download or view
PDF version of opinion*
-
Ex parte State of
Alabama (In re: Girard v. State),
No. 1020889 (Ala.
Dec. 30, 2003)
(criminal; multiple
counts of possessing obscene matter; unit of prosecution; David A. Girard
was indicted on May 23, 2001, for 26 counts of possessing obscene matter,
violations of Ala. Code §13A-12-192(b). The counts were based
on the number of alleged obscene images on the defendant's computer.
The images had been saved or downloaded on different dates and times.
Girard's trial began on October 10, 2001. After the State had presented
its case-in-chief, the trial court granted Girard's motion for a judgment
of acquittal on counts 2 through 6, 14, and 17 through 26, leaving pending
10 counts of possession of obscene matter. On October 11, 2001, the
jury found Girard guilty of all 10 counts. On November 14, 2001,
the trial court sentenced Girard to 10 years in prison on each count, but
"split" the sentence and ordered Girard to serve 3 years in prison followed
by 5 years on probation. The trial court ordered that Girard's sentences
were to run concurrently. Girard appealed to the Court of Criminal
Appeals. That court reversed the judgment of the trial court and
remanded the cause for the trial court to vacate all but one of the convictions
and sentences. HOLDING: The Supreme Court affirmed
the Court of Criminal Appeals. The Court concluded that the proper
unit of prosecution for the offense of possession of obscene matter under
Ala. Code §13A-12-192(b) is the possession of the obscene matter,
regardless of how many items are actually possessed.)
*Download or view
PDF version of opinion*
-
Turenne v. Turenne,
No. 1021056 (Ala.
Dec. 30, 2003)
(domestic relations;
subject-matter jurisdiction; dispute over a marital settlement agreement
that was incorporated in the judgment of divorce; Roger W. Turenne, the
Roger W. Turenne 2001 Revocable Trust, and Turenne PharMedCo, Inc. (hereinafter
referred to collectively as "the plaintiffs"), sued Patti W. Turenne, individually
and as trustee of the Patti W. Turenne Revocable Trust; Christopher R.
Schmidt, Patti's son, as trustee of the Patti W. Turenne Revocable Trust;
Timothy W. Schmidt, Patti's son, as trustee of the Patti W. Turenne Revocable
Trust; Talladega Healthcare Center, Inc.; Albertville Healthcare Center,
Inc.; Hillview Properties, LLC; as well as other fictitiously named defendants,
on claims alleging in count I, fraudulent inducement; in count II, suppression
of material facts; in count III, breach of contract against Patti Turenne;
in count IV, breach of contract against Talladega Healthcare Center, Inc.,
Albertville Healthcare Center, Inc., and Hillview Properties, LLC; in count
V, anticipatory breach of contract against Talladega Healthcare Center,
Inc., Albertville Healthcare Center, Inc., and Hillview Properties, LLC;
and in count VI and count VII, money due and owing. on December 12,
2001, Roger Turenne and Patti Turenne entered into a marital settlement
agreement. On December 13, 2001, a final judgment of divorce was
entered, divorcing Roger Turenne and Patti Turenne. The judgment
stated, in pertinent part, that "the 'Marital Settlement Agreement' entered
into between the parties on the 12 day of December, 2001, is hereby incorporated
and merged into this Order, the same to be legally binding on both parties
and enforceable by either." The marital settlement agreement provided
for a property division between Roger Turenne and Patti Turenne.
Before their divorce, the couple jointly owned several businesses, including
a medical-supply company and two nursing homes. Under the agreement,
Roger received, among other things, PharMedCo, a pharmaceutical and medical-supply
company, and Patti received the two nursing homes -- Albertville Healthcare
Center, Inc., and Talladega Healthcare Center, Inc. Hillview Properties,
LLC, operates a nursing home under the name Hillview Terrace. According
to the plaintiffs' complaint, "Patti Turenne is a 60% member of Hillview
Properties, and ... Chris Schmidt is a 40% member of Hillview Properties."
The marital settlement agreement did not purport to change the ownership
of Hillview Properties. Patti Turenne, Christopher Schmidt, Timothy
Schmidt, Talladega Healthcare Center, Inc., Albertville Healthcare Center,
Inc., and Hillview Properties, LLC, moved to dismiss counts I (fraudulent
inducement), II (suppression of material facts), III (breach of contract
as to Patti Turenne), and V (anticipatory breach of contract as to Talladega
Healthcare Center, Inc., Albertville Healthcare Center, Inc., and Hillview
Properties, LLC) because, they stated in their motion, "as a matter of
law, these claims fail to state claims upon which relief can be granted."
The motion to dismiss also stated that those four claims "all stem[med]
from a Marital Settlement Agreement entered between [Roger Turenne] and
Plaintiff's former wife, Defendant Patti Turenne." The circuit court
granted the motion to dismiss. HOLDING: The Supreme
Court affirmed. The Court held that the Turennes' marital settlement
agreement is no longer an enforceable contract; it was subsumed by the
divorce judgment. The Court held that jurisdiction of all matters
arising from the divorce judgment, including the provisions of the marital
settlement agreement, remained with the domestic relations division of
the Montgomery Circuit Court, which, in a proper exercise of its jurisdiction,
had entered a judgment divorcing Roger Turenne and Patti Turenne.
The Court noted that the fraud actions, i.e., count I (fraudulent inducement)
and count II (suppression of material facts), are within the ancillary
jurisdiction of the domestic relations division of the Montgomery Circuit
Court. The Court noted that the dismissal was without prejudice and
that nothing prevents Roger Turenne from refiling this action in the domestic
relations court, and nothing prevents the domestic relations court from
enforcing the divorce judgment it entered.)
*Download or view
PDF version of opinion*
-
Ex parte Liberty
Nat'l Life Ins. Co.,
No. 1021173 (Ala.
Dec. 30, 2003)
(Barbara Roberts,
Duane Johnson, and Mary Nalley sued Liberty National Life Insurance Company
and Torchmark Corporation (hereinafter collectively referred to as "Liberty
National") in the Choctaw Circuit Court, alleging breach of contract, unjust
enrichment, misrepresentation, and suppression. The action was brought
on behalf of them and a class of persons who were the insureds under certain
types of cancer-insurance policies sold by Liberty National (hereinafter
"the plaintiffs"). The plaintiffs alleged that Liberty National failed
to inform them that it had closed their block of insurance policies and
that Liberty National had actively misrepresented the reasons for the increase
in the amount of their premiums. The plaintiffs were all members
of the class certified in Adams v. Robertson, 676 So. 2d 1265 (Ala.
1995). Robertson, a class action filed in the Barbour
Circuit Court, involved over 400,000 policyholders of Liberty National
Life Insurance Company cancer insurance (hereinafter the "Robertson
class"). The Robertson class alleged that Liberty National
Life Insurance Company had fraudulently encouraged them to switch their
insurance policies ("the old policies") for new policies that provided
less coverage ("the new policies"). The Robertson class included
both persons who had switched to the new policies and those who had retained
their old policies. The action was settled, and the settlement, as
modified, was approved by the trial court; its order was affirmed by the
Supreme Court. The settlement required Liberty National Life Insurance
Company to offer to the members of the Robertson class insurance
policies with substantially all of the benefits of the old and new policies;
it also prevented Liberty National Life Insurance Company from increasing
premiums on the policies for three years and from ever increasing premiums
by an amount that would result in a loss ratio of less than 55%.
These "special policies" were never offered to persons outside the Robertson
class. After three years, the premiums for the Robertson class
increased substantially, but never exceeded the limit set forth in the
Robertson
settlement. After Liberty National Life Insurance Company increased
the premiums, the plaintiffs filed this action in the Choctaw Circuit Court
against Liberty National, seeking another class certification. In
response, Liberty National filed a motion to dismiss or, in the alternative,
for a summary judgment. The basis of its motion was 1) that the Robertson
settlement gave the Barbour Circuit Court continuing jurisdiction over
matters related to the Robertson settlement and its enforcement
and that, therefore, the Choctaw Circuit Court lacked subject-matter jurisdiction,
2) that the current action was barred by the res judicata effect of Robertson,
and 3) that the claims now being asserted by the plaintiffs had been released
as a part of the Robertson settlement. The court denied the
motion. Liberty National then filed a motion to alter, amend, or
vacate the order denying its motion or, in the alternative, to certify
the order for an interlocutory appeal, pursuant to Rule 5, Ala. R. App.
P. The court denied that motion as well. Liberty National now
seeks a writ of mandamus ordering the trial judge either to dismiss the
action or to certify for an interlocutory appeal his denial of its motion
to dismiss. HOLDING: The Supreme Court granted the petition.
The Court held that the question of subject-matter jurisdiction is reviewable
by a petition for a writ of mandamus. The Court held that the current
action essentially attempts to improperly attack collaterally in another
circuit court portions of the Robertson settlement. The Court
held that the Barbour Circuit Court expressly retained continuing jurisdiction
over matters relating to the Robertson settlement and the enforcement
of that settlement and that, therefore, the Choctaw Circuit Court does
not have jurisdiction to hear this action. The Court ordered the
Choctaw Circuit Court to dismiss this action.)
*Download or view
PDF version of opinion*
-
Veteto v. Swanson
Servs. Corp.,
No. 1021278 (Ala.
Dec. 30, 2003)
(appellate procedure;
failure to prosecute; Ronald D. Veteto ("Veteto") sued Swanson Services
Corporation ("Swanson") and, "in both their individual and official capacities,"
Michael Haley, commissioner of the Alabama Department of Corrections ("DOC");
Billie Mitchem, warden of the William E. Donaldson Correctional Facility,
a prison operated under the auspices of DOC and located in Bessemer, Alabama;
Hurbert Etheridge, a captain at Donaldson; and Officer Marion C. Espy,
a correctional officer supervisor II at Donaldson (Haley, Mitchem, Etheridge,
and Espy are hereinafter referred to collectively as the DOC defendants).
Veteto, an inmate at Donaldson, alleged in his complaint that he had completed
Swanson order forms distributed to inmates by Donaldson employees for the
purpose of selecting items, to be paid for by his parents, available to
inmates under Swanson's "Holiday Package Program." The order forms
represented that orders received by November 13, 2000, would be delivered
between December 11 and December 22, 2000. Veteto's parents subsequently
completed their portion of the forms and mailed them to Swanson along with
an "official" bank check made out to the order of Swanson in the amount
of $158.68. Veteto did not receive his holiday packages during the
promised time frame; they were finally delivered on January 5, 2001.
Donaldson employees checked the contents of the packages, but, according
to Veteto, they "rushed the process," comingling the contents, thereby
failing to detect "some of the shortages and overages" that Veteto subsequently
determined to exist in the packages. Veteto determined that a number
of items were missing, that some items were included that he had not ordered,
and that various items of candy and snack foods were damaged or degraded.
Veteto concluded that the total value of the shortages was $40.09.
In addition to making numerous factual assertions against Swanson and asserting
a variety of theories of legal liability against it, Veteto asserted that
the DOC defendants "conspired with and/or aided and abetted" Swanson in
its breach of contract and tortious wrongdoings. Veteto sought actual
damages for breach of contract in the amount of $40.09; $20,000 in compensatory
damages against Swanson "for hungry, sickness, mental pain and anguish,
and emotional distress"; $10,000 in compensatory damages against the DOC
defendants "for conspiring with and aiding and abetting Swanson"; and $50,000
in punitive damages against Swanson and the DOC defendants. The DOC
defendants filed a motion to dismiss, or, alternatively, for a summary
judgment. The DOC defendants argued various legal points in
a supporting brief, including their immunity from suit and that there had
been no "material breach of contract." The trial court entered a
summary judgment in favor of the DOC defendants and dismissed for want
of prosecution the claims against Swanson. Veteto filed a notice
of appeal stating that he "appeals to the Supreme Court of Alabama from
the dismissal of this civil action with prejudice for want of prosecution"
There was no indication that he was appealing as to the DOC defendants.
HOLDING:
The Supreme Court affirmed. The Court held that the propriety of
the judgment in favor of the DOC was not before the Court because of the
failure of Veteto to indicate he was appealing as to that judgment.
As to Swanson, the Court held that Veteto's failure to seek a deposition
either under Rule 30 or 31, there was nothing before the trial court that
could have constituted Veteto's "prosecution" of the civil case.
Veteto, as an incarcerated civil plaintiff, is not entitled to be brought
from the penitentiary to testify in his own behalf. The Court concluded
that the trial judge did not exceed his discretion in dismissing Veteto's
claims against Swanson for want of prosecution at the scheduled trial date,
given the state of the record at that time.)
*Download or view
PDF version of opinion*
-
Blount Recycling,
LLC v. City of Cullman,
Nos. 1021683 &
1021766 (Ala. Dec. 30, 2003)
(preliminary injunction;
The City of Cullman ("City") and the Cullman County Commission ("Commission")
established the Cullman County Solid Waste Authority to provide for the
disposal of solid waste generated within the geographical limits of Cullman
County, which includes the City. In 1992, the City, the Commission,
and the Cullman County Solid Waste Authority entered into the Waste Disposal
Services Agreement. The agreement provided for the disposal of waste
generated in Cullman County in a landfill built by the Authority.
The Commission enacted a resolution and the City enacted an ordinance to
govern the collection of nonhazardous solid waste within the geographical
limits of Cullman County. The provisions authorize the City and the
Commission to provide for the collection and the disposal of nonhazardous
solid waste, with a few exceptions noted for sharing services and for the
issuance of certificates of exception to persons or entities who did not
want the service. Blount Recycling is a waste-collection and recycling
company authorized by the Alabama Department of Environmental Management
to do business in every county in Alabama. Blount Recycling operates
a construction and demolition landfill in Blount County. In 2002,
Blount Recycling was issued a business license to conduct its business
in Cullman County. Shortly after it was issued a license to operate
in Cullman County, Blount Recycling began advertising its services and
picking up construction and demolition debris from around the City and
in other parts of Cullman County. The City notified Blount Recycling
by letter that Blount Recycling's collection of the construction and demolition
debris violated the City ordinance and the Commission's resolution.
The City requested that Blount Recycling discontinue its collection services.
Blount Recycling refused. The City filed an action seeking a declaration
of the parties' rights as to the collection of the debris and a petition
seeking a preliminary injunction preventing Blount Recycling from collecting
waste in the City. The ordinance was the only evidence submitted
by the City to establish the prerequisites for the issuance of the preliminary
injunction. The circuit court issued a preliminary injunction prohibiting
Blount Recycling from collecting waste in the City until a final hearing
was held in the case. The Commission similarly began its action against
Blount Recycling by filing in the circuit court a declaratory-judgment
action and a petition seeking an injunction. Without conducting a
hearing, the circuit court enjoined Blount Recycling from picking up or
hauling solid waste in Cullman County. HOLDING: The
Supreme Court reversed. The Court found that the ordinance does not
establish that the City will suffer immediate and irreparable injury without
the injunction; or that the City is likely to succeed on the merits of
the case; or that the hardship imposed upon Blount Recycling by the injunction
would not unreasonably outweigh the benefit to the City. As to the
Commission, the Court noted that the Commission did not present any evidence
and Blount Recycling was not given an opportunity to be heard. It
therefore ordered that its injunction be dissolved. The Court held,
however, that the City and the Commission were not precluded from requesting
the circuit court to again issue an injunction, if they deem one necessary.)
*Download or view
PDF version of opinion*
-
Ex parte Murphy,
No. 1021703 (Ala.
Dec. 30, 2003)
(domestic relations;
periodic alimony; agreement to pay periodic alimony after remarriage; merger
with divorce judgment; Ala. Code §30-2-55; James R. Murphy and
Mary J. Murphy Benvenuto divorced. Incorporated into the parties'
final judgment of divorce was a settlement agreement that awarded $1,500
per month as periodic alimony to Benvenuto. It further provided that
"[t]he award of periodic alimony shall not be taxable to the payee spouse
nor deductible to the payor spouse." About 19 months later, the parties
executed an agreement purporting to modify the amount of alimony.
It provided that the agreement to pay periodic alimony will terminate in
the event that Benvenuto marries someone other than Murphy, but that it
would not take effect until January 1, 2000. It further provided
that Murphy would pay Benvenuto $300 per month for life upon the marriage
of Benvenuto. The agreement also provided that the $300 per month was to
be used for the support, maintenance, and general maintenance and for the
health of Benvenuto during her lifetime, but Benvenuto agreed to deposit
in an account separate from her estate which upon her death any monies
therein would be paid to Murphy any money not so used. The agreement
also provided that either party could petition the court to incorporate
the agreement into the divorce judgment. Benvenuto remarried on December
1, 1999. Murphy paid Benvenuto $300.00 per month from January 2000
until June 2001. On September 20, 2001, Benvenuto petitioned the
Russell Circuit Court to modify the final judgment of divorce to reflect
the incorporation into the judgment of the agreement to modify alimony
in the event of remarriage. The court ordered "That permanent
periodic alimony to be paid by [Murphy] to [Benvenuto] is set at $300.00
per month as of the date of [Benvenuto's] remarriage." Murphy appealed
the circuit court's order to the Court of Civil Appeals; that court affirmed,
without an opinion. HOLDING: The Supreme Court reversed
the Court of Civil Appeals. The Court held that when Murphy and Benvenuto
executed the agreement to reduce Murphy's periodic-alimony payments after
her remarriage, the agreement was contractual in nature and could be enforced
like any other contract. However, the Court held that when Benvenuto
petitioned the Russell Circuit Court to incorporate the agreement into
the divorce judgment, the agreement lost its contractual nature and became
subject to the equity power of the court. The Court held that when
the agreement became subject to the equity power of the court, it became
incumbent upon the court to follow the mandates of Ala. Code §30-2-55.
Thus, the Court held that the circuit court exceeded the scope of its authority
in ordering Murphy to pay alimony after Benvenuto had remarried.)
*Download or view
PDF version of opinion*
-
Ex parte Bracknell,
No. 1021724 (Ala.
Dec. 30, 2003)
(criminal; sufficiency
of pleading of Rule 32 petition for post-conviction relief; ineffective
assistance of counsel; The Supreme Court denied the petition for writ of
certiorari without opinion. Justice Johnstone wrote a dissenting
opinion.)
*Download or view
PDF version of opinion*
-
Ex parte Procom
Servs., Inc.,
No. 1021851 (Ala.
Dec. 30, 2003)
(outbound forum-selection
clause; venue; nonsignatories; Hank Smith, Jr., sued Procom Services, Inc.
("Procom"), a Texas corporation, and Russell Leitch and Hal Crews, both
residents of Dallas, Texas, in the Jefferson Circuit Court alleging breach
of an employment contract. Procom, Leitch, and Crews filed a motion to
dismiss alleging, among other grounds, that venue in Jefferson County was
improper and asking the trial court to enforce the outbound forum-selection
clause contained in Smith's employment contract with Procom. The
motion to dismiss was supported by Leitch's and Crews's affidavits.
Smith amended his complaint to add a fraud claim based upon allegedly false
representations made to him by Leitch and Crews. Smith also filed
a response to the defendants' motion to dismiss, along with his supporting
affidavit. The trial court overruled the motion to dismiss without
a written explanation. Procom, Leitch, and Crews petition this Court
for a writ of mandamus "directing the trial court to dismiss the claims
of Smith against petitioners" based on the outbound forum-selection clause.
HOLDING:
The Supreme Court granted the writ of mandamus. The Court held that
Smith failed to meet his burden of "clearly establish[ing]" that enforcement
of the forum-selection clause was unfair because the clause was "affected
by fraud." The Court held that Smith failed to establish that the
employment contract was affected by overweening bargaining power.
The Court held that a trial in Dallas, Texas, would not be so difficult
and inconvenient that it would effectively deprive Smith of his day in
court. The Court held that because Smith's claims against nonsignatories
Leitch and Crews arise out of statements Leitch and Crews allegedly made
while negotiating Smith's employment contract with Procom, Leitch and Crews
are entitled to enforce the outbound forum-selection clause contained in
the employment contract.)
*Download or view
PDF version of opinion*
-
Ex parte Romines,
No. 1022065 (Ala.
Dec. 30, 2003)
(workers' compensation;
hypertension; definition of "injury" in the Workers' Compensation Act;
The Supreme Court denied the petition for writ of certiorari without opinion.
Justice Johnstone wrote a dissenting opinion.)
*Download or view
PDF version of opinion*
-
Ex parte Pierce,
No. 1030054 (Ala.
Dec. 30, 2003)
(domestic relations;
child custody; evidence that may be considered on a Ala.R.Civ.P. 59 motion;
The Supreme Court denied the petition for writ of certiorari without opinion.
Justice Johnstone wrote a dissenting opinion.)
*Download or view
PDF version of opinion*
Opinions Released December 19, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON FRIDAY, DECEMBER 19, 2003
-
Dolgencorp, Inc.
v. Hall,
No. 1012000 (Ala.
Dec. 19, 2003)
(premises liability;
negligence; Faye Hall went to a Dollar General Store to find a household
item. As she was looking for the item, she noticed a musical instrument
on a top shelf. Someone said, "Excuse me" and stepped in front of
Hall. Hall stepped back. When she stepped forward and looked
up toward the instrument on the top shelf, a liquid substance fell in her
face, getting in her nose, mouth, and eyes. She called for help because
her face was burning. Ruth Johnson, a Dollar General Store assistant manager,
helped get Hall to the bathroom so Hall could wash her face. Johnson noticed
that Hall's lips, face, and arm were burned. After the paramedics
arrived and treated Hall, Johnson went to the area where the incident occurred
and found a bottle of liquid drain cleaner lying on a shelf; the top to
the bottle was on the shelf beside the bottle. She also saw that
there was liquid from the bottle on the shelf and running down the side
of the shelf. Johnson had not seen the bottle of liquid drain cleaner
on the shelf when she inspected the store the night before and again at
8:30 that morning. The shelf where the bottle was was not the shelf where
the liquid drain cleaners were ordinarily kept. On the day of the
incident, the Dollar General Store employees had conducted "recovery,"
which included checking the shelves for bottles with loose caps, at 8:30
a.m. The incident involving Hall occurred at 11:30 a.m. Dollar
General Store employees had noticed that bottles sometimes arrived at the
store with loose caps. In addition, the employees speculated that
vandals or careless customers left the caps loose on some bottles already
on the shelves. Sandra Ingram, the store manager, testified that
the store had only two employees working at any one time because it did
not have the money to hire more employees. She testified that if she had
more employees, she would have had them doing "recovery" more often.
Hall sued Dolgencorp, Inc. ("Dolgencorp"), which owns and operates Dollar
General Store discount stores, alleging negligence and wantonness after
the contents of a bottle of liquid drain cleaner spilled onto her face
from a shelf in the Dollar General Store in Marion. At trial, at
the close of Hall's case-in-chief, Dolgencorp filed a motion for a judgment
as a matter of law ("JML") as to Hall's negligence and wantonness claims.
The trial court granted Dolgencorp's motion as to the wantonness claim,
but it denied the motion as to the negligence claim. At the close
of all of the evidence, Dolgencorp renewed its motion for a JML as to Hall's
negligence claim, and the trial court again denied the motion. The
jury returned a $100,000 general verdict for Hall, and Dolgencorp appealed.
HOLDING:
The Supreme Court reversed. The Court noted that no evidence indicating
that a store employee put the bottle on a high shelf next to the musical
instruments or that any employees knew that the liquid drain cleaner was
misshelved and that the cap to the bottle was loose or had been removed,
and it held that such a conclusion would be mere speculation and therefore
insufficient to show negligence on the part of Dolgencorp. The Court
stated that the fact that Dolgencorp did not have an employee policing
every aisle at more frequent intervals does not mean that it was on constructive
notice of the hazardous condition that resulted in Hall's injury.
The Court held that, therefore, the trial court erred by not granting Dolgencorp's
motion for a JML.)
*Download or view
PDF version of opinion*
-
Ex parte Heard,
No. 1020241 (Ala.
Dec. 19, 2003)
(criminal; appellate
procedure; Ala.R.Crim.P. 24.4; time for appeal; On January 12, 2002, Rodericus
Heard was convicted of one count of murder and one count of capital murder.
He was sentenced to life imprisonment for the murder conviction and to
life imprisonment without the possibility of parole for the capital-murder
conviction. After his trial and sentencing, Heard filed a motion
for a new trial on February 11, 2002. On the same day, Heard also
filed a "Motion to Set Hearing and Extend Time for Decision on Motion for
New Trial and Motion in Arrest of Judgment." Heard's motion stated
two grounds for extending the time. The first ground was that the
time needed to prepare the trial transcript, combined with the time needed
to adequately review the transcript, would likely be longer than 60 days.
Heard's counsel explained that pursuant to Rule 24.4, Ala. R. Crim. P.,
the motion for a new trial would be denied by operation of law 60 days
after the pronouncement of sentence. The second ground for the motion
was that Heard's counsel was pregnant, and she anticipated being on maternity
leave during a portion of the 60-day period. Heard's counsel asserted
in the motion that "the undersigned has contacted counsel for the state
who consents to such an extension [of time] for the stated grounds."
In response to the motion, the trial court filed an order on March 13,
2002, setting Heard's motion for a new trial for a hearing on April 11,
2002. Subsequently, Heard's counsel, for reasons unclear from the
record, filed a notice of appeal on May 22, 2002, 41 days after the April
11, 2002, scheduled hearing date. Upon receiving the notice of appeal,
the Court of Criminal Appeals issued an order on June 20, 2002, stating
that it appeared that Heard's motion for a new trial had been denied by
operation of law on March 13, 2002, unless the motion had been continued.
The Court of Criminal Appeals ordered Heard to provide that court with
"a certified copy of the entry of record made on or before March 13, 2002,
continuing his motion for new trial beyond that date in compliance with
the procedure prescribed in Rule 24.4 of the Alabama Rules of Criminal
Procedure." The court further stated that if Heard failed to provide
the requested material within 14 days, his appeal would be dismissed.
Heard responded to the order by filing in the trial court a motion requesting
that court to clarify its March 13, 2002, order. The trial court
held a hearing on the motion and afterwards, on July 3, 2002, issued a
corrected order. The court's order stated that its understanding
at the time of the March 13, 2002, order was that the prosecutor and Heard
had consented to extend the time for a ruling on Heard's motion for a new
trial. Furthermore, the trial court stated that its failure to include
a reference in the text of its March 13, 2002, order to the parties' consent
to extend the time was a clerical error. Consequently, pursuant to
Rule 29, Ala. R. Crim. P., the trial court corrected its March 13, 2002,
order to include a recitation that the parties had in fact consented on
record to the continuance. Heard filed this clarification order with
the Court of Criminal Appeals on July 8, 2002. The record of
the case was certified as complete by the circuit clerk on July 24, 2002,
and was filed with the Court of Criminal Appeals on July 29, 2002.
The Court of Criminal Appeals dismissed Heard's appeal. In its opinion
dismissing Heard's appeal, the Court of Criminal Appeals noted that, under
Rule 59.1, Ala. R. Civ. P., which provides that in civil cases a postjudgment
motion is deemed denied by operation of law after it has been pending for
90 days, a trial court loses jurisdiction over any postjudgment motions
not ruled upon within 90 days, unless there is a continuance that is of
record before the expiration of the 90-day period. The Court of Criminal
Appeals analogized Rule 59.1 to Rule 24.4, Ala. R. Crim. P., which provides
that a motion for a new trial is deemed denied after it has been pending
for 60 days, and held that the trial court in this case was without jurisdiction
to enter its clarification order because it lost jurisdiction of the case
after 60 days. Therefore, the Court of Criminal Appeals dismissed
Heard's appeal as untimely. HOLDING: The Supreme Court
reversed the dismissal by the Court of Criminal Appeals. The Court
held that the express consent of both parties to the continuance of the
motion for a new trial was clearly expressed in the record before March
13, 2002, as required by Rule 24.4, Ala. R. Crim. P., by Heard's
uncontested February 11, 2002, motion, contained in the record, which stated
that Heard's counsel had "contacted counsel for the state who consents
to such an extension for the stated grounds.")
*Download or view
PDF version of opinion*
-
Callaway v. Whittenton,
No. 1020660 (Ala.
Dec. 19, 2003)
(wrongful repossession
and trespass; On May 10, 2000, Christopher Callaway purchased a 1993 Geo
Tracker sport utility vehicle from Summerdale Budget Auto & Truck,
Inc.("Budget"). Baldwin Finance, Inc., which financed the Callaways'
purchase of the Tracker, held a lien on the Tracker; the sales agreement
entered into by the Callaways and Budget gave Budget and Baldwin Finance
the right to repossess the vehicle in the event of a default. The
Callaways did not make the payment due in August. On August 31, 2000,
Michael Whittenton, who repossessed cars as an unincorporated independent
contractor, repossessed the Tracker without incident. Christopher
paid the past-due amount and the repossession fee and retook possession
of the Tracker. The Callaways allege that Budget orally agreed to
extend the date the October payment was due to November 24, 2000.
The only evidence of this oral agreement is the Callaways' testimony; the
record contains no evidence presented by Budget regarding the alleged extension,
and there is no evidence of consideration for the alleged agreement to
defer the October payment. The Callaways did not make the October
payment when it was due, and Whittenton repossessed the Tracker again on
November 6, 2000, at approximately 11:00 a.m. The second repossession
is the subject of this action. The parties disagree as to what happened
on November 6, 2000. The Callaways sued Whittenton, Budget, and Baldwin
Finance, alleging assault and battery, negligence, wantonness, trespass,
civil conspiracy, and wrongful repossession (a violation of § 7-9-503,
Ala. Code 1975 (secured party's right to take possession after default;
replaced by §7-9A-609)); Joy Callaway alleged loss of consortium.
Budget and Baldwin Finance separately moved to compel arbitration, and
on October 30, 2001, the trial court granted their motions. The Callaways'
claims against Whittenton were tried. On December 12, 2002, at the
close of the Callaways' case, the trial court granted Whittenton's motion
for a judgment as a matter of law as to the wrongful-repossession, trespass,
and civil-conspiracy claims. The remaining claims -- negligence,
wantonness, assault and battery, and loss of consortium -- were submitted
to the jury. The jury found in favor of Whittenton on all claims.
The Callaways appealed the trial court's judgment as a matter of law as
to their claims of wrongful repossession and trespass. HOLDING:
The Supreme Court affirmed as to the trespass claim and reversed as to
the wrongful repossession claim. The Court concluded that the Callaways
were in default under the purchase agreement, and Budget was entitled to
take possession of the car. However, the Court noted that Budget
was required to take possession without causing a breach of the peace.
The Court held that the testimony of the Callaways, though somewhat contradictory,
is substantial evidence that the repossession was not accomplished "peacefully
(i.e., without risk of injury to the secured party, the debtor, or any
innocent bystanders)." Because Whittenton entered onto the Callaways'
property for the purpose of repossessing the Tracker, the Court held that
Whittenton had a legal right to be on the premises, and it affirmed the
trial court's judgment as a matter of law on this issue. However,
viewing the evidence in the light most favorable to the nonmovant Callaways,
the Court concluded that they presented sufficient evidence from which
a jury could conclude that in repossessing the Tracker Whittenton breached
the peace; therefore, the Court held that the claim alleging wrongful repossession
should have been submitted to a jury.)
*Download or view
PDF version of opinion*
-
Gore v. Alabama
Dep't of Public Safety,
No. 1020722 (Ala.
Dec. 19, 2003)
(sovereign immunity;
conversion; declaratory judgment; seizure of cash and other personal property;
On November 2, 2001, Ray Gore was stopped by an Alabama State Trooper for
speeding on I-65 near Bay Minette. During that traffic stop, the
trooper discovered approximately $115,000 in United States currency in
Gore's possession. Suspecting that the currency may have been the
product of criminal activity, the trooper confiscated it, along with Gore's
cellular telephone and various personal documents. Gore was neither
arrested nor taken into custody as a result of the traffic stop.
The cash was subsequently transferred to the Federal Drug Enforcement Administration
("DEA"), which instituted forfeiture proceedings. Gore has not been
charged with any crime, offense, or violation, other than a warning citation
he received for speeding. He has since sought the return of the currency
and personal items from the Department of Public Safety; however, the Department
has refused to return them, stating that an investigation is ongoing and
that the return of potential evidence could jeopardize that investigation.
On March 21, 2002, Gore sued the Department in the Baldwin Circuit Court
alleging conversion and seeking a judgment declaring that the seizure of
the money and personal items was wrongful. The Department moved to
dismiss the complaint, alleging that Gore failed to state a claim upon
which relief could be granted and that the trial court lacked subject-matter
jurisdiction over the matter. The trial court granted the motion
as to the currency, which was in the possession of the DEA, but denied
the motion as to the personal property, over which the Department maintained
control. The Department moved for a summary judgment on Gore's remaining
claims relating to the cellular telephone and the personal documents.
The trial court granted that motion. HOLDING: The Supreme
Court held that the trial court properly dismissed Gore's claim for a judgment
declaring that the seizure of the currency was wrongful and his claim for
conversion seeking damages because they are barred under the doctrine of
sovereign immunity. However, the Court held that the doctrine of
sovereign immunity is not applicable to Gore's claim for the physical return
of the seized items, because the return of that property could be compelled
as a ministerial act and there is an exception to sovereign immunity for
actions brought to compel State officials to perform ministerial acts.
The Court held that the retention of a citizen's property for 15-24 months
may not be justified solely by the law-enforcement agency's assurance that
an investigation is ongoing. The Court held that Gore has, therefore,
established a genuine issue of material fact as to whether the Department
has wrongfully withheld his cellular telephone and personal documents.
As such, the Court reversed the summary judgment entered in favor of the
Department regarding the cellular telephone and personal documents.)
*Download or view
PDF version of opinion*
-
AmSouth Bank v.
Looney,
No. 1020839 (Ala.
Dec. 19, 2003)
(arbitration; discovery;
Beulah H. Looney, a customer of AmSouth Bank, sued AmSouth and its employee
Helen Kendrick for invasion of privacy and intentional infliction of emotional
distress for disclosing information about Looney's AmSouth bank accounts
to certain persons. Relying on arbitration agreements contained in
the "Customer Agreements" between Looney and AmSouth, AmSouth moved to
compel arbitration. Responding to the arbitration motion, Looney
did not attack the grounds asserted by AmSouth to invoke arbitration but,
instead, requested production of a number of specified documents.
Looney moved to defer a ruling on the motion to compel arbitration long
enough for Looney to obtain the requested documents to prepare defenses
to the arbitration motion. Looney supported this motion with an affidavit.
AmSouth filed an objection to the request for discovery and a motion to
strike the affidavit by Looney. AmSouth argued that, because Looney
had not stated any facts to demonstrate any defense to the arbitration
agreement, her request for discovery should be denied and her affidavit
should be stricken. The trial court granted the request by Looney
for discovery of the requested documents, denied the motion by AmSouth
to strike the affidavit by Looney, and denied the motion by AmSouth to
compel Looney to arbitrate her claims. HOLDING: The
Supreme Court held that Looney does not state in her affidavit or in any
other materials presented to the trial court why the documents she seeks
would invalidate the documents incorporating by reference or containing
the arbitration agreement invoked by AmSouth. The Court also noted
that AmSouth apparently has already supplied most of the discovery sought
by Looney. The Court noted that while Looney's affidavit denies that
she has ever signed or even seen an arbitration agreement with AmSouth,
her affidavit does not deny that she has signed documents which incorporated
the arbitration agreement by reference and that acknowledged her receipt
of the arbitration agreement. The Court held that these signed documents
are sufficient to bind her to the terms of the arbitration agreement.
The Court concluded its opinion by stating that "if, as in this case, the
party opposing arbitration has not made a record before the trial court
sufficient to support the discovery order accompanying the premature denial
of the motion to compel arbitration, then our reversal of the denial must
be accompanied, as this one hereby is, with an instruction that the trial
court not only vacate the denial but also enter an order granting the motion
to compel.")
*Download or view
PDF version of opinion*
-
DCH Healthcare Auth.
v. Duckworth,
No. 1020913 (Ala.
Dec. 19, 2003)
(medical malpractice;
dilatory-diagnosis-and-treatment case; 83-year-old Dee Duckworth went to
the DCH Regional Medical Center ("the Center") on October 9, 1999, to pick
up Mary Duckworth, a patient at the Center, who was being discharged
that day. After arriving at the Center, however, Mr. Duckworth fell
on an escalator and struck his head. He was taken to the emergency
department at 10:24 a.m. Mrs. Duckworth was notified of the accident
and joined him at the emergency department. At 10:59 a.m., Dr. Malcolm
Nelson, the emergency-department physician, examined Mr. Duckworth and
ordered an X-ray examination, which began at 12:36 p.m. For approximately
45 minutes preceding the X-ray examination, Mr. Duckworth waited in the
hallway of the radiology department. While he was waiting, he developed
a headache and nausea. He vomited during and after the X-ray examination.
At 1:17 p.m., Dr. Nelson ordered a computerized tomography scan ("CT scan"),
which was performed at 1:54 p.m. At 2:00 p.m., the radiology department
notified emergency-department personnel that Mr. Duckworth had a subdural
hematoma. At approximately 2:15 p.m., Mr. Duckworth was relocated
to the critical-care unit, and neurosurgeon Dr. Moses Jones was called
to relieve the hemorrhage. Dr. Jones arrived at the Center at approximately
3:15 p.m. Surgery began at 4:40 p.m. and was completed at 6:00
p.m. Mr. Duckworth remained hospitalized until October 22, 1999,
when he died as a result of the injuries he sustained in the fall on October
9. Subsequently, Mrs. Duckworth sued the Center, alleging that Dr.
Nelson and the other emergency-department personnel "caused or negligently
allowed [Mr. Duckworth] to go without proper and timely evaluation, monitoring,
care, and treatment for a potential closed-head injury, and failed to timely
and properly address, observe and report changes in his condition."
The complaint further alleged that as a consequence of the alleged negligence,
Mr. Duckworth "was caused to worsen with a cerebral bleed and he was so
injured that he died." During the trial of the case, the Center moved
for a judgment as a matter of law ("JML") at the close of Mrs. Duckworth's
evidence, and, again, at the close of all the evidence. As a ground
for the motions, the Center asserted that Mrs. Duckworth failed to present
substantial evidence of causation by expert testimony. The trial
court denied the motions, and a jury awarded Mrs. Duckworth $350,000.
The Center filed a postverdict motion for a JML. That motion was
overruled by operation of law. HOLDING: The Supreme
Court reversed and rendered a judgment for the Center. The Court
concluded that Mrs. Duckworth failed to present substantial evidence of
medical causation. The Court noted that the plaintiff's only medical
expert testimony is functionally identical to the testimony held to be
insufficient in McAfee v. Baptist Medical Center, 641 So.2d 265
(Ala. 1994).)
*Download or view
PDF version of opinion*
-
Delta Health Group,
Inc. v. Stafford,
No. 1021675 (Ala.
Dec. 19, 2003)
(defamation; fraud;
loss of consortium; Delta Health Group, Inc. operates approximately 45
nursing homes in the Southeastern states; Willow Trace Nursing Home, located
in Butler, Alabama, is one of those nursing homes. Beginning in 1994
until August 1997, Tim Stafford worked as the maintenance supervisor for
Willow Trace. He resigned in August 1997 to take a higher paying
position with another employer. During an internal study conducted
in 1999, Delta Health could not account for certain building materials
purchased on Willow Trace's account during the period from December 1996
through August 1997. Anthony Perotta, director of maintenance for
Delta Health, reviewed a number of the purchase invoices for the materials
in question and determined that Tim Stafford had signed the invoices.
Perotta also indicated that some of the wiring purchased during that period,
"Romex" brand wire, was a residential-grade wire inappropriate for use
at the nursing home and that the amount of materials purchased during that
period was greater than the amount of materials normally used at Willow
Trace during that time frame. Perotta requested that James Dew, the
director of maintenance at Willow Trace, inspect the nursing home to determine
if the building materials purchased on Willow Trace's account had been
used at Willow Trace. Dew reported that the materials purchased included
a residential-grade wire that was inappropriate for use as a permanent
fixture in a commercial building such as a nursing home. He indicated
that he had inspected Willow Trace but had not found any evidence indicating
that the wire in question had been used there. Based on this information,
Delta Health concluded that someone had stolen the building materials –-
i.e., had purchased the materials on Willow Trace's account and not used
the materials at Willow Trace. Susan Fox, the administrator for Willow
Trace, requested that the Choctaw County sheriff's office pursue a criminal
investigation. However, the sheriff told Fox that the evidence Delta
Health had compiled was insufficient to support a criminal charge because
no one had been seen taking the materials and no one had been seen with
the materials off the premises of Willow Trace. In July 1999, Tod
Ioakim, the director of risk management for Delta Health, notified Lumbermens
Mutual Casualty Company, the fidelity insurer for Delta Health, that it
had suffered a loss of approximately $10,600 in building materials.
Ioakim telephoned the Lumbermens' agent who worked with Delta Health and,
based on their conversation, the agent completed a property-loss notice.
That loss notice described the loss as follows: "Employee, over a period
of several months, purchased building supplies from Ace Hardware, Surplus
& Salvage & Southern Electric (total of $10,600) to be used in
the construction of his home and charged them to the insured." Under
the section entitled "kind of loss" the insurance agent wrote "crime."
Ioakim named Tim Stafford as the employee responsible for the loss.
Lumbermens compiled and maintained a file on the claim filed by Delta Health.
Lumbermens determined the loss suffered by Delta Health was $8,418.26.
After subtracting the $1,000 deductible, Lumbermens paid Delta Health $7,418.26
on its claim. In exchange, Delta Health signed a release and assigned
its rights to Lumbermens. In October 2000, Kemper Insurance Companies,
on behalf of Lumbermens, notified Stafford that he owed Lumbermens and
Delta Health a total of $8,418.26 because, it alleged, he had converted
the building materials from Willow Trace to his own use. Lana Stafford
began communicating with Kemper; she denied that her husband had stolen
any building materials from Willow Trace. She indicated that their
house was completed before the time period in question. Kemper asked
Tim Stafford to provide proof that he was not responsible for Delta Health's
loss, but Stafford refused. On December 3, 2000, Stafford sent a
letter to Willow Trace asserting that he had taken nothing from Willow
Trace, that he owed no money to Willow Trace, and that Delta Health's claim
that he had stolen building materials was completely false. Delta
Health, Lumbermens, and Kemper conducted no further investigation to determine
the validity of the claim asserted against Stafford. In May 2001,
Lumbermens sued Stafford in the Choctaw District Court alleging conversion.
The complaint was filed in the name of Delta Health Group, Inc., d/b/a
Willow Trace Nursing Home, and Lumbermens Mutual Casualty Co., as subrogee.
Lumbermens sought to recover from Stafford $8,447.44, plus interest and
costs. In June 2001, Tim Stafford and Lana Stafford sued Delta Health,
Lumbermens, and various fictitiously named parties. In the complaint,
Tim Stafford alleged slander, slander per se, libel, the tort of outrage,
malicious prosecution and/or abuse of process, and fraud. Lana Stafford
asserted a claim alleging loss of consortium. Delta Health and Lumbermens
filed separate motions seeking summary judgments. Tim Stafford's
tort-of-outrage claim was dismissed by agreement of the parties, and the
trial court dismissed without prejudice his claim of malicious prosecution
and/or abuse of process on the ground that it was prematurely asserted.
Because the only claims asserted against Lumbermens by Tim Stafford were
the tort-of-outrage and the malicious-prosecution and/or abuse-of-prosecution
claims, and because the only claim asserted by Lana Stafford against Lumbermens
was a derivative one –- loss of consortium –- the trial court granted Lumbermens'
motion for a summary judgment. Lumbermens was dismissed as a party
from the action. The claim of malicious prosecution and/or abuse
of process against Delta Health was dismissed without prejudice as premature;
the tort-of-outrage claim against Delta Health was dismissed by agreement
of the parties. The trial court denied Delta Health's motion for
a summary judgment on the remaining claims of slander, slander per se,
libel, fraud, and loss of consortium. The Staffords' claims alleging
slander, slander per se, libel (those claims are hereinafter referred to
collectively as "defamation claims"), fraud, and loss of consortium against
Delta Health went to trial. At trial, Stafford presented evidence
indicating that the construction of the Staffords' house was completed
in August 1996 and that he and Lana were living in the house on August
30, 1996. Stafford also testified that he had used Romex wiring extensively
at Willow Trace, particularly in the 200 Hall and 700 Hall residences.
Stafford also presented the testimony of Timothy Glosson, the former director
of maintenance for Willow Trace, who testified that, immediately after
Stafford resigned, Glosson saw new Romex wiring "all over" the Willow Trace
facility. At trial, Stafford read excerpts from the deposition of
Anthony Perotta. Perotta testified that he was told that excessive
amounts of building materials had been purchased under Tim Stafford's signature.
He stated that he prepared a list of excessive building materials by simply
going through the invoices presented to him and picking out, to the
best of his ability, what he thought would be used and what he thought
would not be used at Willow Trace. Perotta admitted that the invoices
were not specific and that he made assumptions and guesses in this process
as to the specific materials purchased and the exact amounts purchased.
Perotta also admitted that he had heard "through the [rumor] mill" that
Tim Stafford was building a house; however, Perotta denied ever hearing
that Stafford was using or had used the building materials purchased by
Willow Trace to build his house. He also did not personally investigate
to determine if all of the materials represented on the invoices were actually
used at Willow Trace; he was primarily concerned with the use of Romex
wiring because, Perotta testified, its use in a commercial setting
would have created a safety hazard. To determine whether Romex
wire had been used at Willow Trace, Perotta said he personally lifted up
ceiling tiles to look for Romex wire. Perotta acknowledged that any
wiring at Willow Trace would have to be run through conduit, but he stated
that he did not cut any conduit when he was looking for the Romex wire.
At the close of the evidence, Delta Health requested a judgment as a matter
of law on Stafford's claims of defamation and fraud, asserting that Stafford
had failed to establish sufficient evidence to justify submitting either
claim to the jury. Delta Health also argued that, if the defamation
and fraud claims were dismissed, it was entitled to a judgment as a matter
of law on Lana Stafford's derivative loss-of-consortium claim. The
trial court denied this motion and submitted the Staffords' claims to the
jury. The jury returned a general verdict in favor of Tim Stafford,
awarding him $200,000 in compensatory damages and $200,000 in punitive
damages. The jury awarded Lana Stafford $100,000 on her loss-of-consortium
claim. The trial court entered a judgment on this verdict.
Delta Health filed a postjudgment motion seeking a judgment as a matter
of law and a motion for a remittitur or, in the alternative, for a new
trial. On June 12, 2003, the trial court issued an order denying
Delta Health's postjudgment motions. On June 26, 2003, the trial
court issued a separate order withdrawing that portion of its June 12,
2003, order that addressed punitive damages and analyzing the jury's $200,000
punitive-damages award for excessiveness. The trial court found the
punitive-damages award not to be excessive and again denied Delta Health's
motion for a remittitur of the punitive damages. HOLDING:
The Supreme Court reversed and remanded for a new trial. The Court
concluded that Stafford presented sufficient evidence to justify submitting
his defamation claims to the jury. The Court held that Delta Health's
communications to Lumbermens –- its insurer -- were protected by a qualified
privilege. The Court concluded that Stafford presented sufficient
evidence to create a conflict for the jury on whether Delta Health made
the communications with actual malice. However, the Court concluded
that the record is devoid of any evidence tending to establish that Stafford
relied to his detriment on any of the alleged misrepresentations made by
Delta Health to Lumbermens. As such, the Court concluded that Stafford
failed to produce sufficient evidence to create a jury question on each
of the elements necessary for his fraud claim. Therefore, the Court
held that the trial court erred in denying Delta Health's motion for a
judgment as a matter of law regarding Stafford's fraud claim. The
Court held that the fraud claim should not have been submitted to the jury.
Because a good claim (defamation) and a bad claim (fraud) were submitted,
the Court was required to reverse the judgment, including the loss-of-consortium
claim, and remand the case for a new trial.)
*Download or view
PDF version of opinion*
-
Scott Bridge Co.
v. Wright,
No. 1021705 (Ala.
Dec. 19, 2003)
(worker's compensation;
retaliatory discharge; Scott Bridge Company hired Michael Wright on June
26, 1997, as a carpenter on a bridge-construction project in Georgia.
When he was hired, Wright was a resident of Georgia. Wright claims
that he suffered an on-the-job injury on March 18, 1998, while working
on a bridge project in Augusta, Georgia. On or about September 28,
1998, Wright filed a claim for benefits with the Georgia State Board of
Workers' Compensation. Wright never sought benefits under the Alabama
Workers' Compensation Act. In October 1998, Scott Bridge assigned
Wright to work at its office in Opelika, where he remained employed until
he was discharged on April 21, 2000. Wright sued Scott Bridge
in the Chambers Circuit Court on April 19, 2002, alleging that he was discharged
in retaliation for having filed a claim for workers' compensation benefits.
The action was transferred to the Lee Circuit Court. Scott Bridge
filed a motion for a summary judgment on the ground that the prohibition
set forth in Ala. Code §25-5-11.1 against terminating an employee
solely because the employee has filed a workers' compensation claim does
not apply to employees asserting claims under the workers' compensation
laws of any other state. The trial court denied the motion.
Scott Bridge then filed a motion asking the trial court to alter or amend
the order, or, in the alternative, to certify the order for permissive
appeal pursuant to Rule 5, Ala.R.App.P. The trial court entered
an order stating that the case involved "a controlling question of law
as to which there is a substantial ground for difference of opinion, specifically
whether Ala. Code §25-5-11.1 recognizes a claim for retaliatory discharge
where the plaintiff never sought workers' compensation benefits in Alabama,
but rather sought workers' compensation benefits in Georgia pursuant to
an injury occurring when the plaintiff worked and lived in Georgia."
The trial court then amended that order, finding expressly that "Plaintiff
never sought workers' compensation benefits in Alabama, but claims only
that he sought workers' compensation benefits in Georgia." Continuing,
the trial court observed that "Alabama law may recognize a claim for retaliatory
discharge, pursuant to Ala. Code §25-5-11.1, based on the facts alleged
by Plaintiff." Scott Bridge then filed with the Supreme Court a petition
for permission to appeal pursuant to Rule 5, Ala.R.App.P. The Supreme
Court granted the petition.
HOLDING: The Supreme Court
reversed the trial court's denial of the motion for summary judgment and
rendered a judgment for Scott Bridge Company. The Court held that
§25-5-11.1 quite plainly creates a remedy where an employee has been
discharged solely for instituting or maintaining an action for workers'
compensation benefits "under this chapter." The Court stated that
the case for modifying §25-5-11.1 to embrace claims arising from an
employee's discharge in Alabama as a result of the employee's asserting
rights conferred by the workers' compensation laws of another state should
be made in the Legislature.)
*Download or view
PDF version of opinion*
-
Moore v. State Farm
Auto. Ins. Co.,
No. 1021725 (Ala.
Dec. 19, 2003)
(insurance; breach
of contract; bad faith; fraud; outrage; The Supreme Court affirmed without
opinion. Justice Johnstone wrote an opinion concurring in part and
dissenting in part.)
*Download or view
PDF version of opinion*
-
Williams v. State
Farm Mut. Auto. Ins. Co.,
No. 1021758 (Ala.
Dec. 19, 2003)
(bad-faith failure
to pay; claim insurer by third party injured by insured; Danny Williams
was involved in an automobile accident; Frank Shaw was driving the other
vehicle involved in the accident. Shaw, who was killed in the accident,
was insured by State Farm. While Williams suffered no personal injuries,
his tractor-trailer was damaged. State Farm opened a claim, and the
matter was assigned to Derek Kidd, a State Farm claim representative, for
handling. Kidd received a demand from Williams's insurance carrier,
Western World Insurance Group, seeking reimbursement of $12,000 Western
World had paid Williams on the claim relating to his damaged tractor-trailer,
as well as reimbursement of Williams's $1,000 deductible. Attached
to that demand was a copy of an appraiser's report obtained by Western
World; the appraiser had inspected the tractor-trailer on June 24, 2002.
The report contained three independent quotes valuing the tractor-trailer
at $15,000, $13,000, and $13,000. The average of the three values
was $13,667. The maximum payable under Williams's policy with Western
World was $12,000, plus Williams's deductible, for a total of $13,000.
Western World was entitled to the salvage. Therefore, if the tractor-trailer
was declared a total loss and was not repaired, Williams would lose between
$667 and $2,000, depending on which value figure was used. After
unsuccessful efforts were made to secure an axle that could be used to
repair the tractor-trailer, on August 5, 2002, State Farm reimbursed Western
World the $12,000 it had paid to Williams. State Farm paid Williams
directly $1,000, as reimbursement for his deductible. On September
17, 2002, State Farm received a letter from Williams's attorney, who presented
an "offer to settle the balance of Mr. Williams'[s] claim against your
insured." The settlement demand included $965 in towing fees plus
$5,890 in lost profits, which Williams computed by taking his daily net
profit and multiplying it by the 29 "working days" he claims he was without
the tractor-trailer (June 18 to July 26). On September 12, 2002,
Kidd wrote Williams's attorney, stating that State Farm would agree to
reimburse Williams for the towing charges, but claimed that Williams's
demand for 29 days of lost profits was excessive. Specifically,
Kidd noted that Williams's tractor-trailer was inspected on June 24 and
determined to be a total loss. Kidd stated the claim should have
been settled six days after the inspection and offered Williams 11 days
of lost profits for a total of $3,420.78. Coupled with the
towing charges, State Farm proposed to pay Williams $4,385.78, contingent
upon Williams's execution of a full release in favor of Shaw's estate.
The parties could not agree as to the amount of lost profits, and Williams
sued State Farm in the Jefferson Circuit Court, alleging bad-faith failure
to pay. State Farm filed a motion for a summary judgment, which the
trial court granted. HOLDING: The Supreme Court affirmed.
The Court noted that it is well established that a party cannot bring an
action against an insurance company for bad-faith failure to pay an insurance
claim if the party does not have a direct contractual relationship with
the insurance company. The Court held that this rule accords with
the language of Ala. Code §27-12-24, which is clearly directed at
regulating insurers' contractual relationships with their insureds for
the protection of the insureds, not third parties. The Court held
that since it is undisputed that Williams has no contract of insurance
with State Farm and that Williams procured no judgment against Shaw's estate
before bringing his action against State Farm, State Farm was entitled
to a judgment as a matter of law.)
*Download or view
PDF version of opinion*
Opinions Released December 12, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON FRIDAY, DECEMBER 12, 2003
-
General Motors Corp.
v. Jernigan,
No. 1020069 (Ala.
Dec. 12, 2003)
(product liability;
the Alabama Extended Manufacturer's Liability Doctrine ("the AEMLD"); recusal;
venue; jury selection; challenges for cause of prospective jurors related
to an attorney in the case; expert testimony; On December 10, 1999, Jeffrey
Jernigan and his older brother Nickolas Jernigan were involved in an automobile
accident. Nickolas, who was 17 years old, was driving a 1993 Oldsmobile
Delta 88 automobile ("the Oldsmobile") owned by Wilbert Jernigan ("Jernigan"),
the father of the Jeffrey and Nickolas. Jeffrey, who was 12 years
old, was a passenger in the front seat of the Oldsmobile. Both boys
were wearing their seat belts. The Oldsmobile, traveling at a speed
of 50 to 55 miles per hour, crashed into an oncoming 2000 Pontiac Grand
Prix automobile ("the Pontiac") traveling at approximately the same speed.
The right front corners of both automobiles took the brunt of the impact.
In this offset frontal (almost head-on) collision, the Oldsmobile's right
front structures crushed toward Jeffrey, striking his head and pinning
his feet in the wreckage. He was thrown forward and sustained grave
injuries, primarily a skull fracture that required surgical removal of
a portion of the left frontal lobe of his brain, resulting in permanent
and severe brain damage, personality changes, and learning deficits; he
also sustained a second-degree burn to his left foot. Neither Nickolas
nor the driver of the Pontiac sustained serious injuries. Jernigan,
individually and as father and next friend of Jeffrey Jernigan, a minor,
sued General Motors Corp. ("GM") and other defendants in Bullock County
Circuit Court, seeking compensatory and punitive damages individually and
on behalf of Jeffrey based upon the AEMLD. Jernigan is also the circuit
clerk of Bullock County. The jury returned a verdict in favor of
Jernigan, awarding $20 million in compensatory damages to Jernigan on behalf
of Jeffrey, $2 million in compensatory damages to Jernigan, individually,
and $100 million in punitive damages. The trial court entered a judgment
on the verdict. GM filed a postjudgment motion renewing previously
filed motions for a judgment as a matter of law ("JML"), requesting a new
trial, or, alternatively, requesting a remittitur of the damages awards.
The trial court remitted the punitive-damages award to $60 million (three
times the compensatory damages awarded on Jeffrey's behalf as required
by § 6-11-21(a), Ala. Code 1975), but otherwise denied the postjudgment
motion. GM appealed. HOLDING: The Supreme Court
reversed the portion of the postjudgment order denying GM's motion for
a new trial and remanded the case for a new trial. The Court declined
to change the standard for admitting expert testimony from the Frye
v. United States standard to the Daubert v. Merrell Dow Pharmaceuticals
standard. The Court held that the plaintiff's expert's testimony
was admissible and offered substantial evidence of alternative designs.
The Court held that the plaintiff introduced sufficient evidence
of the availability of a safer, practical, alternative design. Therefore,
the Court held that the trial court properly denied GM's motions for a
JML. The Court held that because Myron Penn was an "attorney in the
case to be tried" within the meaning of Ala. Code §12-16-150(11),
GM was entitled to have its challenges for cause as to Penn's five
relatives granted. The Court distinguished several cases each involving
one erroneous ruling on a challenge for cause considered to be harmless
errors from the present case because they involved only one challenge for
cause whereas the present case involved five. As such, the Court
held that the trial court, by denying five of GM's challenges for cause
that should have been granted, substantially impaired GM's right to the
use of its peremptory challenges in selecting a jury. Therefore,
the Court held that the trial court erred in denying GM's motion for a
new trial. The Court further ruled that a motion for a change of
venue for cause, made pursuant to Ala. Code §6-3-20, will not be reviewed
on an appeal from a final judgment, but instead, review of such a ruling
in a civil action is by a petition for a writ of mandamus. The Court
also held that Jernigan offered substantial evidence indicating that GM
waived any objection it may have had to Judge Smithart's vacation trip
with several lawyers, one of whom represents Jernigan in this case.
The Court concluded that Judge Smithart's recusal is not required.)
*Download or view
PDF version of opinion*
-
SCI Ala. Funeral
Servs., Inc. v. Corley,
No. 1020450 (Ala.
Dec. 12, 2003)
(arbitration; interstate
commerce; On the authority of Service Corp. International v. Fulmer,
No. 1021503 (Ala. Dec. 5, 2003), the Supreme Court affirmed the order of
the trial court denying the motion of the defendants-appellants to compel
arbitration insofar as it applies to the plaintiffs' claims against
Service Corporation International but reversed the order insofar as it
applies to the plaintiffs' claims against SCI Alabama Funeral Services,
Inc. ("SCI- Alabama"). The Court further rejected the argument of
the nonsignatory plaintiffs that their nonsignatory status spares them
the burden of the arbitration agreements between the signatory plaintiffs
and SCI-Alabama, because the nonsignatory plaintiffs' claims, which are
identical to the signatory plaintiffs' claims, depend on the obligations
undertaken by SCI-Alabama pursuant to the contracts containing the arbitration
agreements.)
*Download or view
PDF version of opinion*
-
Howard v. City of
Atmore,
No. 1021312 (Ala.
Dec. 12, 2003)
(immunity; wrongful-death
action arising out of a suicide in jail; On May 24, 1999, following convictions
for third-degree theft of property, third-degree assault, resisting arrest,
and destroying city property, Marilyn Faye Bowens began serving a 120-day
sentence in the City of Atmore jail. The jail was equipped
with a video camera that allowed continuous monitoring of Bowens's cell
from a remote location. At 3:00 p.m. the next day, May 25, Betty
Cox completed her eight-hour shift as the jailer/dispatcher. Before
leaving for the day, Cox conducted a cell check of the inmates. At
that time, Officer Frank Bryars began his shift as the jailer/dispatcher,
replacing Cox. At 4:08 p.m., Sgt. Carey Flavors went to Bowens's
cell to speak with her. He found Bowens hanging by the neck from
bars in the ceiling, to which she had attached herself with her shoe laces.
Flavors "yelled for help," and he and Officer Bryars removed Bowens from
the makeshift noose. Bowens died without regaining consciousness.
Subsequently, Gladys Bowens Howard, as administratrix of the estate
of her sister, filed this wrongful-death action against the City and against
Chief McKinley and Officer Bryars, in their individual and official capacities.
The defendants moved for a summary judgment, contending that they are entitled
either to "peace-officer" immunity, pursuant to Ala. Code §6-5-338,
or to "State-agent" immunity under the analysis set forth in Ex parte
Cranman, 792 So.2d 392 (Ala. 2000), and adopted in Ex parte Butts,
775 So.2d 173 (Ala. 2000). The trial court entered a summary judgment
for all the defendants, relying expressly on the ground of immunity. HOLDING:
The Supreme Court affirmed the judgment as to Chief McKinley and reversed
as to Officer Bryars and the City. The Court held that Officer
Bryars was a sworn law-enforcement officer at the time of Bowens's suicide,
that the guarding of a city jail by a regular police officer is one of
the "law enforcement duties" contemplated by Ala. Code §6-5-338, and
that the categories in Cranman are broad enough to contemplate the
confinement of prisoners. However, the Court held that the summary
judgment in favor of Officer Bryars was erroneous because the plaintiff
presented substantial evidence that Officer Bryars failed to follow mandatory
rules and procedures prescribed by the City police department for
observing inmates. As to Chief McKinley, the Court held that Chief
McKinley is responsible for the day-to-day operations of the police department
and the city jail, that those activities fall squarely within Cranman
categories, and that there is a conspicuous absence of binding authority
as to how to identify and handle a potential suicide risk and what precautions
to take in any particular case. Thus, the Court held that Howard
has not met her burden to show that Chief McKinley's conduct falls within
an exception to State-agent immunity and that the trial court did not err
in entering a summary judgment in favor of Chief McKinley. As to
the City, the Court held that the trial court correctly entered a summary
judgment for the City with respect to the claims against Chief McKinley
but that the trial court erred insofar as the summary judgment for the
City was entered with respect to the alleged "neglect, carelessness and
unskillfulness" of Officer Bryars.)
*Download or view
PDF version of opinion*
-
Cook's Pest Control,
Inc. v. Hastings,
No. 1021795 (Ala.
Dec. 12, 2003)
(arbitration; interstate
commerce; The Marshall Circuit Court denied the motion to compel arbitration
filed by Cook's Pest Control, Inc. ("Cook's"), finding that the transaction
did not involve interstate commerce; the court's ruling was based on the
now abrogated decision in Sisters of the Visitation v. Cochran Plastering
Co., 775 So.2d 759 (Ala. 2000). The Supreme Court reversed the
order denying the motion and remanded the cause for consideration in light
of Service Corp. Int'l v. Fulmer, No. 1021503 (Ala. Dec. 5, 2003),
and Bowen v. Security Pest Control, Inc., No. 1010783 (Ala. Oct.
3, 2003).)
*Download or view
PDF version of opinion*
-
Hammonds v. Town
of Priceville,
No. 1021637 (Ala.
Dec. 12, 2003)
(municipal government;
Doyle Hammonds became Priceville's chief of police in 1980. In May
2000, two former girlfriends brought harassment charges against Hammonds.
On October 15, 2001, he pleaded guilty to two counts of "harassing communications."
On November 15, 2001, Priceville's town council convened a hearing to discuss
Hammonds's situation. At the conclusion of that hearing, the council
voted 4-2 to remove Hammonds as chief of police. The mayor's vote
was one of the four votes in favor of Hammonds's removal. Hammonds
was subsequently removed as chief of police. Hammonds petitioned
the trial court for a common-law writ of certiorari to review his removal.
The trial court granted the petition and subsequently entered a summary
judgment for the Town of Priceville. It is undisputed that Priceville
has less than 12,000 inhabitants and that it thus falls within Ala. Code
§11-43-2 HOLDING: The Supreme Court noted that
§11-43-2 states the broad principle that the mayor "may vote as a
member of the council on any question coming to a vote." However,
the Court held that §11-43-160, when read in pari materia with §11-43-2,
provides an exception to this broad principle. The exception concerns
not who may vote, but whose vote will actually count in removing a person
appointed to office in the municipality. The Court noted that §11-43-160
allows removal "by a two-thirds vote of all those elected to the council"
and that mayors are "elected to" the office of mayor, not "to the council."
Therefore, the Court held that the mayor is fully entitled to vote
to remove a municipal official, but the mayor's vote does not count in
determining if there was the requisite "two-thirds vote of all those elected
to the council" to remove the official. Thus, the Court held that
the town council did not have the requisite two-thirds vote needed to remove
Hammonds from the office of chief of police, and it reversed the judgment
in favor of the town.)
*Download or view
PDF version of opinion*
Opinions Released December 5, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON FRIDAY, DECEMBER 5, 2003
-
Alabama Ins. Guar.
Ass'n v. Air Tuskegee, LTD.,
No. 1021087 (Ala.
Dec. 5, 2003)
(residency for purposes
of the Alabama Insurance Guaranty Association Act (Ala. Code 1975,
§§ 27-42-1 through 27-42-20) ("the Guaranty Act"); The purpose
of the Guaranty Act is to provide a mechanism for the payment of statutorily
defined claims made under certain types of insurance policies issued by
insurance companies licensed to transact insurance in the State of Alabama
that are declared insolvent and against whom an order of liquidation has
been entered. On December 6, 1995, the Troup County (Georgia) Airport
Authority was the owner, maintainer and lessor of a Piper PA-28-180 aircraft.
On December 6, 1995, David R. Dobbins rented the Piper aircraft from the
Troup County Airport Authority. Wilford Senn was a passenger in the
Piper aircraft that was piloted by David R. Dobbins. The engine in
the Piper aircraft piloted by David R. Dobbins failed, resulting in a crash
landing near Athens, Georgia. As a result of the crash, David R.
Dobbins and Wilford Senn sustained severe, permanent injuries to their
bodies. Prior to the December 6, 1995 crash of the Piper aircraft,
Air Tuskegee, Ltd., and/or Gerald Waller had been hired by the Troup County
Airport Authority to perform maintenance on and/or to examine the engine
of the Piper aircraft. The subject maintenance and inspection to
the subject Piper aircraft took place in Alabama. At all times relevant
to his performance of maintenance on and/or examination of the engine of
the Piper aircraft, Gerald Waller was either an independent contractor,
agent or employee of Air Tuskegee, Ltd. Wilford Senn, Joan Senn,
David R. Dobbins and Robin Dobbins filed a lawsuit in the Superior Court
of Troup County, Georgia against Air Tuskegee, Ltd. and Gerald Waller,
among others. At the time of the December 6, 1995, crash made the
basis of the Underlying Action, Air Tuskegee, Ltd. was a corporation existing
under the laws of the State of Delaware having its principal place of business
in Tuskegee, Macon County, Alabama. At the time of the December 6,
1995 crash made the basis of the Underlying Action and effective April
18, 1995 through April 18, 1996, American Eagle Insurance Company (hereinafter
'American Eagle') provided a General Liability Airport Policy to its named
insured, Air Tuskegee, Ltd. to its named insured, Air Tuskegee, Ltd.
American Eagle is an 'insolvent insurer,' as defined by Ala. Code §27-42-5(5).
The Alabama Insurance Guaranty Association ("AIGA") filed this action to
determine the residency of Air Tuskegee, LTD. The trial court ruled
that Air Tuskegee is a resident of the State of Alabama within the meaning
of the Guaranty Act. HOLDING; The Supreme Court affirmed.
The Court held that a corporation can be a resident of only one state for
purposes of entitlement to recovery under the Guaranty Act, and the Court
adopted the principal-place-of-business rule in the AIGA context.)
*Download or view
PDF version of opinion*
-
Pearson v. Brooks,
No. 1021494 (Ala.
Dec. 5, 2003)
(fictitious parties;
relation back; statute of limitations; Annie Pearson was employed at Perdue
Farms, Inc., a company operating a chicken-processing plant in Dothan.
Pearson was responsible for cleaning the "kill floor," where many of the
machines used to prepare the chickens for sale and distribution were located.
Pearson's cleaning routine required her to spray the machines with a high-pressure
hose to remove the chicken remains. On November 17, 1999, while Pearson
was cleaning the kill floor, she slipped in the chicken remains.
In an attempt to break her fall, Pearson held her hands in front of her.
Pearson fell into a "neck-skinning" machine, a machine that removed the
skin from the chickens' necks. Pearson's right index finger was amputated
when it became entangled in the machine. Apparently, the guard mechanism
that would have prevented the blade of the machine from cutting was not
in place at the time of Pearson's accident. On October 17, 2001,
one month before the statutory limitations period would have run on her
claims, Pearson sued Perdue Farms, Inc. and several of her co-employees
who were involved in the direct maintenance and supervision of the neck-skinning
machine. Pearson did not name as defendants Glenn Brooks and Michael
Black, although she did assert claims against fictitiously named defendants
who were either "that person, corporation or other legal entity who or
which designed the machine, which is the subject matter of this lawsuit";
"that person, corporation, or other legal entity who had responsibility
for maintenance or repair of the machine which is the subject matter of
this lawsuit"; or "that person, corporation, or other legal entity whose
negligence, wantonness, recklessness, willfulness or other wrongful conduct
caused the injury to Plaintiffs [sic]." Pearson claims that at the
August 20, 2002, deposition of Hughes she became privy to an accident investigation
report related to her injury, which Hughes had prepared. Hughes stated
in the report that Pearson's accident was caused by the "lack of control
and supervision by the Sanitation Hourly Supervisor[] [Black] and Sanitation
Superintendent [Brooks]." On August 30, 2002, Pearson amended her
complaint to substitute Brooks and Black for two of the fictitiously named
parties. Brooks and Black moved to dismiss Pearson's complaint, arguing
that Pearson's claims against them were barred by the statute of limitations.
The trial court granted the motion and dismissed Brooks and Black from
the action. HOLDING:
The Supreme Court affirmed. The
Court concluded that Pearson could not have reasonably been ignorant of
the identities of Brooks and Black. The Court referred to Pearson's deposition
in which she testified that she had known for over three or four years
that Brooks was the superintendent of the sanitation department, that Brooks
had personally trained her to clean the machines, that Black was her immediate
supervisor in the sanitation department, and that Black instructed the
employees regarding the safety procedures in the plant. Thus, the
Court held that when she filed her complaint, Pearson knew Brooks's
and Black's identities as well as their duties regarding plant safety and
the safe operation and cleaning of the plant's machinery. The Court
overruled Roberts v. Cochran, 656 So.2d 353 (Ala. 1995), to the
extent that it conflicts with the rule established in Columbia Engineering
International, Ltd. v. Espey, 429 So.2d 955 (Ala. 1983), and followed
in Marsh v. Wenzel, 732 So.2d 985 (Ala. 1998), regarding the substitution
of fictitiously named parties and the doctrine of relation back.)
*Download or view
PDF version of opinion*
-
Service Corp. Int'l
v. Fulmer,
No. 1021503 (Ala.
Dec. 5, 2003)
(arbitration; interstate
commerce; unconscionability; Following the death of his mother, Blair Fulmer
entered into a contract with SCI-Alabama d/b/a Johns-Ridout's Southside
Chapel pursuant to which Johns-Ridout's Chapel would, among other things,
perform a funeral service and cremate his mother's body. The
contract, entitled "Statement of Funeral Goods and Services Selected/Purchase
Agreement," included an arbitration provision. Fulmer sued SCI-Alabama
and SCI (SCI-Alabama's parent company), asserting various claims.
The appellants filed a motion to compel arbitration, which the trial court
denied on grounds of an insufficient connection to interstate commerce.
HOLDING:
The
Supreme Court reversed as to SCI-Alabama but affirmed as to SCI.
The Court explains in a scholarly discussion the interstate commerce issue
and explains why the U.S. Supreme Court decisions on interstate commerce
apply under the Federal Arbitration Act ("FAA") to require enforcement
of arbitration provisions in virtually any economic or commercial contract,
including those that are purely intrastate commercial transactions, if
the "'general practice' those transactions represent" has, in the aggregate,
a substantial effect on interstate commerce. The Court explained
that "there are few, if any, economic or commercial transactions that are
beyond the reach of Congress's commerce power." The Court further
noted that "while there can be no per se rule that would preclude a trial
court's role in evaluating whether a contract 'evidenc[es] a transaction
involving commerce,' ... a trial court evaluating a contract connected
to some economic or commercial activity would rarely, if ever, refuse to
compel arbitration on the ground that the transactions lacked 'involvement'
in interstate commerce." The Court also rejected Fulmer's contention
that he did not consent to arbitration because, when he entered into the
contract with SCI-Alabama, he was suffering great emotional distress over
the loss of his mother and because the contract is a contract of adhesion.
The Court held that Fulmer could not assert a breach-of-contract claim
based on the contract and also contend that, for arbitration purposes,
it was unconscionable and that he lacked the mental capacity to enter it.
The Court held that Fulmer's alleged lack of mental capacity, even if true,
is a defense directed toward the contract as a whole, not just toward the
arbitration provision. However, the Court held that the language
of the arbitration provision did not allow it to be enforced by SCI, a
non-party to the contract. Thus, as to SCI, the order denying arbitration
was affirmed.)
*Download or view
PDF version of opinion*
-
Ex parte Full Circle
Distribution, L.L.C.,
No. 1021631 (Ala.
Dec. 5, 2003)
(relief from a default
judgment; Ala.R.Civ.P. 60(b)(4); time for filing motion to set aside; in
personam jurisdiction; Full Circle Distribution, L.L.C. and SECO Aviation,
Inc., a corporation organized under the laws of Georgia ("SECO(GA)"), entered
into a consignment agreement pursuant to which SECO(GA) agreed to act as
a distributor for the sale of 14 helicopter-fuel-dump pumps owned by Full
Circle. According to the consignment agreement, Full Circle was to
be paid 30 percent of the revenues from the sale of the pumps.
Approximately two years later, on August 10, 1999, SECO(GA) sold many of
its assets, including the fuel-dump pumps. On February 27, 2002,
Full Circle sued SECO Aviation, Inc., a corporation organized under the
laws of Pennsylvania ("SECO(PA)"), and Anthony Aviation Center, Inc., a
corporation organized under the laws of Florida ("AAC"), in the Etowah
Circuit Court, alleging breach of contract and conversion. Full Circle
contended that AAC purchased the 14 fuel-dump pumps from SECO(GA), but
that SECO(GA) never paid Full Circle a commission on the sale of the fuel-dump
pumps as required under the consignment agreement. Full Circle served
the summons and complaint on SECO(PA) and AAC. However, SECO(PA)
is a different entity from SECO(GA), with which Full Circle had entered
into the consignment agreement. After SECO(PA) and AAC failed to
answer the complaint or to appear within 30 days, Full Circle filed an
application and affidavit for the entry of a default judgment. On
May 10, 2002, the trial court entered a default judgment against SECO(PA)
and AAC; it amended that judgment on June 28, 2002, and July 10, 2002.
On November 19, 2002, the default judgment was filed with the circuit court
in Broward County, Florida, for domestication in accordance with the laws
of the State of Florida. At this time, SECO(PA) and AAC were provided
with notice by certified mail that the default judgment was being domesticated
in Florida. Nevertheless, SECO(PA) and AAC failed to respond or to
challenge the default judgment within 30 days of this notice, and the default
judgment was domesticated in Florida on January 9, 2003. On April
18, 2003, a writ of garnishment was issued by the Broward Circuit Court.
Then, on April 23, 2003, SECO(PA) and AAC filed an emergency motion in
the Broward Circuit Court to dissolve the writ of garnishment; they argued
that the Alabama judgment made the basis of the garnishment action was
void because the Etowah Circuit Court lacked personal jurisdiction over
them and because, they argue, Full Circle had not properly served the summons
and complaint on either of the defendants. Immediately after filing
the emergency motion, SECO(PA) and AAC filed with the Etowah Circuit
Court a motion for relief from the default judgment pursuant to Rule 60(b)(4).
SECO(PA) and AAC argued that the default judgment was void because, they
argued, the trial court lacked personal jurisdiction over them. In
its opposition to the motion for relief from the judgment, Full Circle
asserted that SECO(PA) and AAC's motion failed to satisfy the requirement
of Rule 60(b) that such a motion be filed within "a reasonable time," and
that the actions of SECO(PA) and AAC were sufficient to establish minimum
contacts so as to warrant the trial court's exercise of personal jurisdiction
over them. On June 20, 2003, the trial court granted SECO(PA) and
AAC's motion for relief. Full Circle petitioned for a writ of mandamus
directing the trial court to set aside its order granting relief pursuant
to Rule 60(b)(4). HOLDING: The Supreme Court denied
the petition for writ of mandamu. The Court held that the reasonable-time
limitation is not applicable to actions seeking to set aside a void judgment
pursuant to Rule 60(b)(4). The Court found no evidence indicating
that SECO(PA) or AAC had sufficient connections with Alabama to meet the
requirements for either specific or general in personam jurisdiction.
As such, the Court held that the default judgment was void, and the trial
court did not err in setting it aside.)
*Download or view
PDF version of opinion*
Opinions Released November 26, 2003
-
DECISION ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON WEDNESDAY, NOVEMBER 26, 2003
-
State Farm Mut.
Auto. Ins. Co. v. Harris,
No. 1020609 (Ala.
Nov. 26, 2003)
(uninsured/underinsured
motorist insurance; stacking; definition of "relative"; Bo Harris was driving
a Chevrolet S-10 truck owned by his father. Bo's father had given
Bo permission to operate the truck. On that same date, Fate Foley III was
operating an automobile owned by his wife, Lana Foley. Foley failed to
stop at a stop sign, and the automobile he was driving collided with the
truck being driven by Bo Harris. It is undisputed that Foley's negligence
and/or wantonness caused the accident, and that, as a result of the accident,
Bo Harris suffered serious injuries. It is also undisputed that Fate
Foley and Lana Foley were uninsured motorists, as that term is defined
by Alabama law. At the time of the accident, State Farm insured Hugh
Harris's Chevrolet S-10 truck under policy number D26 9897-F09-01. That
policy was in effect on the date of the accident. In separate policies,
State Farm also insured four other vehicles owned by Hugh Harris; those
policies were also in effect on the date of the accident. In the
policies issued to Hugh Harris, "relative" was originally defined to mean
"a person related to you or your spouse by blood, marriage or adoption
who lives with you. It includes your unmarried and unemancipated child
away at school." In a later endorsement, State Farm amended the definition
of "relative" to read: "a person related to you or your spouse by blood,
marriage or adoption who lives primarily with you. It includes your unmarried
and unemancipated child away at school." Donna Robinson, as mother
and next friend of Bo Harris, sued Fate Foley and Lana Foley. Robinson
alleged that Fate Foley had negligently or wantonly operated the vehicle
he was driving. Robinson also alleged that Lana Foley had negligently or
wantonly entrusted her vehicle to Fate Foley. Robinson sought to
recover compensation for Bo Harris's medical expenses, his permanent injuries,
and his pain and suffering. She also sought punitive damages. State
Farm filed a motion to intervene in the case. The trial court granted the
motion, and State Farm answered Robinson's complaint. State Farm deposited
with the clerk of the circuit court the sum of $25,000, which State Farm
alleged was the maximum Bo Harris was entitled to recover under the uninsured-motorist
coverage available under Hugh Harris's policy with State Farm insuring
the Chevrolet S-10 truck. This amount represented the limits of the uninsured-motorist
coverage provided under State Farm automobile policy D26 9897-F09-01, the
policy issued on the Chevrolet S-10 pick-up truck being operated by Bo
Harris at the time of the accident. State Farm subsequently
sought a partial summary judgment, relying on Bo Harris's deposition testimony
in which he stated that he lived primarily with his mother. State Farm
argued that because Bo Harris did not live primarily with his father, he
did not meet the definition of "relative" contained in the insurance policies
issued to Hugh Harris. State Farm argued that because Bo Harris did not
fall within any definition of "insured," he was not entitled to stack the
uninsured-motorist coverage available under the insurance policies issued
by State Farm on Hugh Harris's four other vehicles. Robinson opposed this
motion and filed her own motion for a partial summary judgment, arguing,
on various grounds, that Bo Harris was entitled to stack the coverage available
under those policies. Bo Harris's father and mother were divorced,
and they had joint custody of Bo. His father lived in Stapleton and his
mother lived in Daphne. In deposition testimony included in the record,
Bo Harris testified that he was living
with his mother at
the time of the accident. The trial court subsequently denied State Farm's
motion for a partial summary judgment and granted Robinson's motion for
partial summary judgment, holding that Bo Harris was entitled to stack
the uninsured-motorist coverage available under his father's five State
Farm insurance policies. On November 6, 2000, Robinson's claims alleging
negligence and wantonness as to Fate Foley were tried before a jury.
The jury returned a verdict in favor of Bo Harris in the amount of
$121,800 in compensatory damages and $7,000 in punitive damages. On November
7, 2002, the trial court entered a judgment on that verdict. On November
15, 2002, State Farm filed its postjudgment motion styled as a "Motion
for Reduction in Judgment Amount." In that motion, State Farm again argued
that, because Bo Harris did not live primarily with Hugh Harris, he could
not meet the definition of an "insured." State Farm argued that Bo Harris
was therefore entitled to recover uninsured-motorist benefits under only
the insurance policy applicable to Hugh Harris's Chevrolet S-10 truck and
that he was not entitled to stack the uninsured-motorist coverage
available under the four other State Farm policies issued to Hugh Harris.
For these reasons, State Farm requested that the trial court reduce the
judgment to $25,000. The trial court denied the motion. HOLDING:
The Supreme Court reversed. The Court concluded that the trial court
erred in finding that Bo Harris was a "relative," as that term is defined
in the State Farm insurance policies. The Court held that because
Bo Harris did not fall within the definition of the term "relative" or
under any other definition of "insured," he was not entitled to stack the
uninsured-motorist coverage available in the insurance policies issued
to Hugh Harris by State Farm.)
*No PDF version of
the opinion is available*
Opinions Released Nov. 21, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON FRIDAY, NOVEMBER 21, 2003
-
Dunning v. New England
Life Ins. Co.,
No. 1011927 (Ala.
Nov. 21, 2003)
(standing; insurance;
fraud and breach-of-contract claims; appellate procedure; notice of appeal;
filing of original; standing to appeal; In 1985 and 1992, Hammer, Inc.,
a construction company located in Monroeville, entered into "supplemental
income agreements" with three key employees, George Dunning, Gerald Salter,
and Dennis Coleman. The agreements provide retirement and/or death
benefits for each of the employees. Hammer was solely responsible
for funding the promised benefits. The employees received the benefits
if they remained employed by the company through the retirement date specified
in the agreements or died while employed by the company. Hammer
purchased a life insurance policy on each of the three employees to fund
its anticipated obligations under the supplemental income agreements.
Hammer purchased the insurance from New England Mutual Life Insurance Company
("New England Mutual") through its agent, Spencer Tatum d/b/a Tatum &
Associates. Hammer--not the employees--was the owner and beneficiary
of the life insurance policies. Article 7 of each of the supplemental
income agreements specifically permitted this type of funding arrangement.
Hammer receives annual statements from New England Mutual showing the value
of each policy. Since 1991, the value of each policy has been lower
than anticipated and the policies would not fund Hammer's obligations to
its employees under the supplemental income agreements. Hammer is
aware of the under-performance of the life insurance policies and acknowledges
that it is still obligated to honor the agreements with its employees.
Hammer, however, has no current obligation under the agreements because
none of the employees' benefits has vested, that is, none of the employees
has retired or died. After learning that the life insurance policies
were not performing at a level that would fully fund their promised benefits,
the employees sued Hammer, Tatum, New England Life Insurance Company, and
Metropolitan Life Insurance Company (hereinafter we refer to New England
Life Insurance Company and Metropolitan Life Insurance Company collectively
as "New England"), alleging fraud, suppression, and breach of contract.
New England and Tatum moved for a summary judgment, arguing that the employees'
claims are not ripe for adjudication, or, alternatively, that their claims
are barred by the statute of limitations or are preempted under ERISA.
On May 6, 2002, the trial court entered a summary judgment in favor of
New England and Tatum, finding that the employees' claims were not ripe
for adjudication. Following the issuance of that order, the employees
dismissed their claims against Hammer without prejudice. On June
17, 2002, Sidney W. Jackson III, counsel for the employees, telephoned
Milton Coxwell, Jr., an attorney practicing in Monroeville, and asked him
to file with the Monroe Circuit Court clerk a copy of the employees’ notice
of appeal from the summary judgment for New England and Tatum because,
Jackson said, he had no way of getting the notice of appeal to Monroeville
that day. Coxwell agreed, and Jackson faxed a copy of the notice
of appeal to Coxwell. Coxwell delivered the faxed copy of the notice
of appeal to the circuit court clerk. Jackson never forwarded the
original notice of appeal to the clerk. The appeal was docketed
in the Supreme Court on July 16, 2002. On July 25, 2002, New England
and Tatum moved to dismiss the appeal, arguing that the employees failed
to file a proper and timely notice of appeal. The Supreme Court granted
the motion to dismiss. The employees moved for reconsideration of
the dismissal, asking the Court to set aside its order of dismissal and
to reinstate their appeal. The Court did so; however, it instructed
the parties to brief the issue of the effectiveness of facsimile filings
together with the substantive issues presented on appeal. HOLDING:
The Supreme Court vacated the trial court's judgment and dismissed the
appeal. The Court held that a copy of an original notice of appeal,
timely filed, is sufficient to invoke the jurisdiction of an appellate
court under Ala.R.App.P. 3. The Court noted that the employees
did not file their notice of appeal by faxing it to an agent of the Monroe
Circuit Court clerk. Instead, a local attorney filed a copy of their
notice of appeal in person. The copy of the notice of appeal had
been produced by a fax machine in the local attorney's office; it had not
been transmitted to the clerk's office by fax machine. Therefore,
the Court noted that the issue presented in this case is not whether the
filing of a notice of appeal by facsimile transmission is permissible;
instead, it is whether a timely filed copy of a notice of appeal is acceptable
under the Alabama Rules of Appellate Procedure if that copy was produced
by a facsimile transmission. The Court held that neither the Alabama
Rules of Appellate Procedure nor the Alabama Rules of Civil Procedure requires
that a notice of appeal bear an original, penned signature. The Court
held that the employees lacked standing to sue on the alleged underperformance
of the life insurance policies because they are strangers to the contract
on which their claims are based. The Court held that, similarly,
the employees have no standing to complain about the alleged fraudulent
behavior in connection with the execution of the contracts on New England
Mutual's part. Because the employees lack standing, the Court held
that the trial court did not have jurisdiction over their claims.
*Download or view
PDF version of opinion*
-
Wal-Mart Stores,
Inc. v. Hepp,
No. 1012237 (Ala.
Nov. 21, 2003)
(workers' compensation;
retaliatory discharge; collateral estoppel; Peter Gregory Hepp was employed
at a Wal-Mart discount department store as a manager in the "tire and lube
express" service center. In November 1996, Hepp injured his back
while on the job. He underwent back surgery and in November 1997
filed an action against Wal-Mart seeking workers' compensation benefits.
On June 8, 1998, the trial court approved a settlement agreement between
Wal-Mart and Hepp. Also on June 8, 1998, Randy Baggett, a district
manager for Wal-Mart, received a report that Hepp had been dispensing freon
without charging a fee for the service. Baggett investigated the
claim, and learned that Hepp had dispensed freon into his personal vehicle
and a vehicle belonging to an acquaintance. Hepp had not charged
for the service and had not prepared service orders for the vehicles; Wal-Mart
required that a service order be prepared for each vehicle brought in for
servicing. On June 10, 1998, Hepp was terminated for violating the
following policies: "(1) performing work (i.e. dispensing freon) at the
Riverchase [tire and lube express service center], which ... was not allowed,
(2) failing to write up a service report on a vehicle for which he provided
service[,] and (3) performing service on a personal vehicle." Hepp
filed for unemployment-compensation benefits with the Department of Industrial
Relations ("DIR") on June 28, 1998. On July 21, 1998, DIR denied
Hepp benefits. Hepp appealed the denial to the appeals tribunal,
as provided by Ala. Code 1975, § 25-4-91 and § 25-4-92, alleging
that he was terminated because he had filed a workers' compensation claim
against Wal-Mart, which had recently been settled. A hearing was
held on Hepp's appeal. Both Hepp and a representative from Wal-Mart
participated in the hearing. On August 14, 1998, the appeals referee
determined that Hepp had been discharged for "misconduct connected with
his work," pursuant to Ala. Code 1975, § 25-4-78(3)(c), because Hepp
had violated Wal-Mart's policy. The referee then held that
Hepp was disqualified from receiving full benefits and was entitled to
only reduced benefits under that Code section. Hepp did not appeal
this decision. After Hepp's hearing before the referee, but before
the referee issued his decision, Hepp filed a complaint in the Shelby Circuit
Court, seeking to reopen his 1997 workers' compensation case to consider
vocational disability. He later amended his complaint to allege that
Wal-Mart had discharged him in retaliation for his filing a workers' compensation
action, in violation of Ala. Code §25-5-11.1. Wal-Mart moved
for a summary judgment on the retaliatory-discharge claim, arguing that
Hepp is barred by the doctrine of collateral estoppel from relitigating
the reason underlying his termination, which, Wal-Mart argued, the appeals
referee had already determined was "misconduct connected with his work."
The trial court denied Wal-Mart's motion, but certified its order for an
interlocutory appeal under Rule 5, Ala.R.App.P. HOLDING: The
Supreme Court reversed. The Court held that the doctrine of
collateral estoppel bars Hepp from arguing in this case that he was terminated
for some reason other than "misconduct connected with his work," which
was the reason the referee had determined Hepp was terminated. Thus, the
Court held that Hepp cannot establish a prima facie case of retaliatory
discharge.)
*Download or view
PDF version of opinion*
-
Kingvision Pay-Per-View,
Ltd. v. Ayers,
No. 1012384 (Ala.
Nov. 21, 2003)
(denial of motion
to vacate a default judgment; the validity of a purported appearance by
an attorney on behalf of a party; Kingvision Pay-Per-View, Ltd. ("Kingvision"),
a Delaware corporation headquartered in Florida and the owner of the exclusive
right to broadcast the June 28, 1997, fight between Evander Holyfield and
Mike Tyson, employed Coral Springs, Florida attorneys Scott Salomon and
Barry Mittelberg (collectively "Salomon & Mittelberg") to pursue claims
against the plaintiff Lester Ayers and others in Alabama for the unlicenced
interception of the broadcast. Salomon & Mittelberg, in turn,
employed Andrew Nelms ("Nelms"), a Montgomery attorney, to act as Alabama
counsel for Kingvision in the pursuit of these claims. Before filing a
lawsuit against the plaintiff, Salomon & Mittelberg attempted to collect
money from the plaintiff by means of telephone calls and letters.
In response to the collection efforts of Salomon & Mittelberg, the
plaintiff sued Kingvision for invasion of privacy and felonious injury,
in the Bessemer Division of the Jefferson County Circuit Court in November
1997. The plaintiff served Kingvision by sending the summons and complaint
by certified mail to Salomon & Mittelberg rather than by serving either
Kingvision itself or CT Corporation, the registered agent of Kingvision
for service of process. Salomon & Mittelberg, on behalf of Kingvision,
moved the circuit court for additional time to respond to the plaintiff's
complaint. The motion stated that "Defendant was served with the instant
action seeking damages on or about December 5, 1997." The motion did not
assert that the service of process on Kingvision was insufficient. After
Salomon & Mittelberg obtained additional time to respond to the complaint,
Nelms, on behalf of Kingvision, simultaneously filed both a Rule 12(b),
Ala. R. Civ. P., motion to dismiss and an answer. The Rule 12(b) motion
sought dismissal of the plaintiff's complaint on the grounds that the "complaint
... fail[ed] to state a claim ... upon which relief [could] be granted"
and that the plaintiff's claims were "barred by personal jurisdiction."
The motion did not assert that the service of process on Kingvision was
insufficient. Similarly, while the answer asserted that the trial court
"lack[ed] ... jurisdiction," it did not assert that the service of process
on Kingvision was insufficient. After the trial court denied the motion
to dismiss, Salomon & Mittelberg and Nelms filed a separate lawsuit
against the plaintiff for recovery of damages for the unauthorized interception
of the broadcast, in the United States District Court for the Northern
District of Alabama. Subsequently, Nelms amended the answer of Kingvision
in the plaintiff's state court lawsuit to assert a statute of limitations
defense that Nelms had omitted from the original answer. This amended answer,
like the previously filed Rule 12(b) motion and the original answer, failed
to assert that the service of process on Kingvision was insufficient.
In the summer of 2000, Nelms withdrew as attorney of record for Kingvision
in the plaintiff's lawsuit. Salomon & Mittelberg then employed Birmingham
attorney James Ward ("Ward") and his law firm, Corley, Moncus & Ward,
P.C. ("Corley"), to defend Kingvision against the plaintiff's claims. Corley,
on behalf of Kingvision, deposed the plaintiff in October 2000. In December
2000, Ward and Corley, withdrawing as attorneys of record for Kingvision,
requested that the trial court send copies of the order granting their
motion to withdraw and send future notices to Kingvision in care of Salomon
& Mittelberg. The trial court called the plaintiff's lawsuit
for trial on September 24, 2001. When Kingvision failed to appear, the
trial court entered a default against Kingvision. In December 2001, after
the plaintiff presented evidence of damages, the trial court entered a
default judgment against Kingvision in the amount of $65,000. In
July 2002, Kingvision moved the trial court under Rule 60(b), Ala. R. Civ.
P., to vacate the default judgment because, Kingvision said, the default
judgment was void and Kingvision had a meritorious defense to the plaintiff's
claims. Kingvision asserted that the default judgment was void because:
(1) the service of process was insufficient and (2) this insufficiency
deprived the trial court of in personam jurisdiction over Kingvision. Kingvision
did not assert that the trial court lacked in personam jurisdiction because
of a lack of contacts between Kingvision and the State of Alabama or because
of any reason other than the insufficiency of the service of process on
Kingvision. In support of the Rule 60(b) motion, Kingvision submitted an
affidavit from Donna K. Westrich. The trial court heard the Rule
60(b) motion of Kingvision without ruling on either the plaintiff's motion
to strike Westrich's affidavit and to compel her deposition. Nelms and
Ward testified at the hearing that they were employed by Salomon &
Mittelberg, that all of their communications were with Salomon & Mittelberg,
and that they had not communicated directly with Kingvision. Nelms opined
that Salomon & Mittelberg had apparent authority to act as a
general agent for Kingvision in the collection of monies owed Kingvision
for the unlicenced interception of the broadcast of the Holyfield-Tyson
fight. The trial court held that Salomon & Mittelberg P.A. had a dual
role, that of attorney for Kingvision and collection agent in the State
of Alabama. The trial court held that their failure to answer the
complaint and the subsequent entry of default against them on September
24, 2001, is not due to be set aside. HOLDING: The Supreme
Court affirmed. The Court noted that Ala. Code §34-3-22 provides
that "the court may at any stage of the proceedings, upon proof [that an
attorney has appeared for a party without authority], relieve the party
for whom the attorney has assumed to appear from the consequences of [the
attorney's] acts," and that "[a]n appearance in a suit by an attorney of
the proper court, is presumed to be authorized," with the burden of proof
on the party denying the authority. The Court noted that the only evidence
Kingvision presented that was relevant to the issue of Nelms's authority
was Westrich's affidavit, which failed to refute effectively Nelms's authority
to file these pleadings.)
*Download or view
PDF version of opinion*
-
Young v. Pimperl,
No. 1020323 (Ala.
Nov. 21, 2003)
(contract for sale
of real estate; Lehman Harvey Young, Mary Rebecca Orton Newcomber, Howard
Franklin Young, Jr., Evelyn Alice Hollar Young, and Virginia Caroline Young
Martin (hereinafter collectively referred to as "the landowners") each
owned an undivided 1/5 interest in a 20-acre parcel of property located
in Baldwin County. John Pimperl and his wife Judy Pimperl discussed
with each of the landowners the possibility of the Pimperls' purchasing
the land. When the Pimperls reached what they believed to be an agreement
with the landowners as to a fair price for the land, the Pimperls mailed
each of the landowners a quitclaim deed, along with a purchase agreement,
to be executed and mailed back to the Pimperls. Lehman, Mary, Evelyn,
and Virginia each executed a copy of the purchase agreement and the quitclaim
deed each had received and mailed the documents back to the Pimperls.
The Pimperls then contacted Howard and inquired as to why he had not executed
his purchase agreement and quitclaim deed. Howard told the Pimperls
that he believed that the property was worth more than the price reflected
in the purchase agreement as the sales price and that, consequently, he
did not intend to execute the purchase agreement and deed. The Pimperls
recorded the deeds they had received from Lehman, Mary, Evelyn, and Virginia,
and sent them each a check in the amount of $2,300, representing 1/5 of
the purchase price of the entire property. The Pimperls also sent
Virginia an additional $1,000 as reimbursement for funds she had expended
to redeem the land from a tax sale. The next month, Lehman, Mary,
and Evelyn returned to the Pimperls the checks they had received for $2,300
with letters stating that they no longer intended to sell their interests
in the land to the Pimperls. The Pimperls filed an action in the
Baldwin Circuit Court, seeking a declaration of ownership of the property
interests of Lehman, Mary, and Evelyn, and seeking a partition of the land
and a sale against Howard. The defendants answered the complaint
and filed a counterclaim, seeking a declaration that the purchase agreements
and quitclaim deeds containing their signatures are a nullity and vaguely
alleging "misrepresentation." After a bench trial, the trial court
entered an order finding that the purchase agreements and quitclaim deeds
executed by Lehman, Mary, and Evelyn were binding contracts for the sale
of their undivided interests in the land. The court then ordered
the Pimperls to pay Lehman, Mary, and Evelyn $2,300 each for their interests
in the land. The court further found "by stipulation of the parties
that the deed [from] Virginia Carolyn Young Martin is a valid conveyance
of her fractional interest in the property subject to the complaint."
The court then determined that the Pimperls were entitled to purchase the
remaining 1/5 undivided interest from Howard. The court appointed
a licensed appraiser to perform a valuation of the remaining 1/5 interest
to serve as the basis for a purchase price. The Pimperls then had
30 days from the date of the valuation in which to pay to Howard the purchase
price as set by the court-appointed appraiser. Lehman, Mary, and
Evelyn (hereinafter collectively referred to as "the appellants") appealed
the trial court's order finding that their execution of the purchase agreements
and deeds constituted binding contracts with the Pimperls for the sale
of their interests in the land. HOLDING: The Supreme
Court reversed. The Court held that when the terms of the purchase
agreement are read as a whole and each word is given its ordinary, plain,
and natural meaning, it is clear that the purchase agreement requires the
participation of all of the landowners for the sale of the land to occur.
The Court held that because fewer than all five of the landowners agreed
to sell their interests and to execute the purchase agreement and quitclaim
deeds, there is no binding contract for the sale of the land.)
*Download or view
PDF version of opinion*
-
Harbor Village Home
Center, Inc. v. Thomas,
No. 1020392 (Ala.
Nov. 21, 2003)
(arbitration; merger
clauses; Curtis Thomas purchased from Harbor Village a new mobile home
manufactured by Buccaneer Homes of Alabama, Inc. In connection with
the purchase, Thomas and Harbor Village executed three different documents,
each of which contained an arbitration provision: a document entitled "Retail
Installment Contract, Security Agreement, Waiver of Trial by Jury, and
Agreement to Arbitration or Reference or Trial by Judge Alone" ("the retail
contract"); a document entitled "Acknowledgment and Agreement" ("the acknowledgment"),
which Buccaneer also executed; and a document entitled "Agreement for Binding
Arbitration and Waiver of Jury Trial" ("the freestanding arbitration agreement").
After purchasing the mobile home, Thomas discovered numerous alleged defects.
He then sued Buccaneer and Harbor Village in the Washington Circuit Court,
alleging fraud, breach of express and implied warranties, and violation
of the Magnuson-Moss Warranty-Federal Trade Commission Improvement Act,
15 U.S.C. § 2301 et seq. The complaint also alleged a negligence
claim against Harbor Village. Buccaneer and Harbor Village moved
to compel arbitration. Thomas filed a brief in opposition to their
motions to compel arbitration. Specifically, Harbor Village asked
the circuit court to enter an order "compelling the parties to the controversy
to submit all claims and causes of action in this present case to binding
arbitration before the American Arbitration Association ...." Harbor
Village also included with its motion copies of the arbitration provisions
and a supporting affidavit. Thomas filed a response to Buccaneer's
motion only, but filed a motion to strike the affidavit filed in support
of Harbor Village's motion. Thomas also sent a letter to the trial
court arguing that even if the court compelled arbitration, arbitration
did not have to be conducted under the Commercial Arbitration Rules of
the American Arbitration Association (hereinafter "the AAA rules").
On August 27, 2002, the trial court issued an order in response to the
motions to compel arbitration filed by Buccaneer and Harbor Village
stating that Curtis Thomas is entitled to a jury trial against Buccaneer
for the express warranty claims and the claims brought pursuant to the
Magnuson-Moss Warranty Act and that the other claims between the parties,
including the implied warranty claims, are due to be arbitrated pursuant
to the terms of the agreements for arbitration. Harbor Village appealed.
Harbor Village claims that the trial court, in ordering that the arbitrator
be selected by "the seller with the consent of the buyer and selected and
agreed upon by both the buyer and seller," erroneously compelled arbitration
under the freestanding arbitration agreement. Harbor Village argues
that the trial court should have instead compelled arbitration under the
retail contract and the acknowledgment, which call for arbitration under
the AAA rules. Those rules, Harbor Village argues, set out a procedure
for selecting an arbitrator different from the procedure found in the freestanding
arbitration agreement. Buccaneer did not appeal, and Thomas did not
cross-appeal. HOLDING: The Supreme Court reversed. The
Court held that the retail contract is the only fully integrated agreement
between Harbor Village and Thomas because the retail contract contains
all of the terms necessary to the contract, including a description of
the mobile home, the identities and signatures of the parties, the price
of the mobile home and the terms of the financing, the assignment, and
an arbitration provision, plus the retail contract contains a merger clause.
The Court concluded that the acknowledgment, despite the fact that it contains
a merger clause, is not the final and complete agreement of the parties.)
*Download or view
PDF version of opinion*
-
Edward D. Jones
& Co. v. Wehby,
No. 1020689 (Ala.
Nov. 21, 2003)
(arbitration; interstate
commerce; John Herbert Wehby sued Jefferson Bruce McKittrick, his former
business partner, alleging fraud and breach of contract. Wehby later
amended his complaint to include claims of breach of fiduciary duty and
suppression against Edward D. Jones & Co., LP, d/b/a Edward Jones,
and its agent, Frank Preziuso (hereinafter collectively "Jones").
In March 2000, Wehby and McKittrick formed a general partnership, J&J
Com, to manage specific investment accounts located at AmSouth Bank in
Jefferson County, Alabama, and at Edward D. Jones & Co. in Cleveland,
Ohio. Wehby's complaint alleges that McKittrick engaged in trading
not authorized under the partnership agreement, resulting in losses to
the partnership of approximately $385,000. Wehby sought $500,000
in compensatory, consequential, and incidental damages, as well as costs,
attorney fees, and interest on the debt. McKittrick failed to answer
Wehby's complaint, and the trial court entered a default judgment against
McKittrick in the amount of $500,000. Edward D. Jones & Co. and
J&J Com had previously entered into a customer account agreement that
addressed the partnership account the parties maintained with Edward D.
Jones & Co. This agreement contained an arbitration provision.
Jones moved the court to dismiss the action by Wehby and the partnership
and to compel arbitration. The trial court denied Jones's motions
to dismiss and to compel arbitration. HOLDING: The Supreme
Court reversed. The Court held that the transaction at issue in this
case between Jones and Wehby involves interstate commerce.)
*Download or view
PDF version of opinion*
-
Ex parte Alloy Wheels
Int'l, Ltd.,
No. 1020778 (Ala.
Nov. 21, 2003)
(personal jurisdiction;
Katherine Victoria Vance was killed in the rollover wreck of her 1998 Land
Rover Discovery sport-utility vehicle. Katherine's mother, Sue Vance,
as the personal representative of Katherine's estate, sued a number of
defendants, and eventually added Alloy Wheels International, Ltd.
as a defendant, for Katherine's wrongful death. The plaintiff alleged product
liability claims and Alabama Extended Manufacturer's Liability Doctrine
claims against the defendants. The plaintiff specifically alleged
that Alloy Wheels had defectively designed and manufactured the aluminum
alloy wheels on Katherine's Land Rover and that a crack in at least one
of the wheels caused the fatal wreck. Answering the amended complaint,
Alloy Wheels asserted, among other defenses, the lack of personal jurisdiction.
Thereafter, Alloy Wheels moved for a summary judgment on the ground that
the trial court lacked personal jurisdiction over Alloy Wheels. Alloy
Wheels relied on the allegations of the complaint and on two affidavits
of Paul Merritt, the operations director of Alloy Wheels in the United
Kingdom. The trial court denied that motion. Alloy Wheels filed a
petition for writ of mandamus. HOLDING: The Supreme
Court granted the writ of mandamus and directed the trial court to grant
Alloy Wheels' motion for summary judgment. The Court found that the
plaintiff had not submitted substantial evidence that Alloy Wheels "purposefully
directed" any action "at the forum State [other] than the mere act of placing
a product in the stream of commerce" and that no evidence establishes sufficient
minimum contacts between Alloy Wheels and the State of Alabama.)
*Download or view
PDF version of opinion*
-
Conference Am.,
Inc. v. Telecommunications Cooperative Network, Inc.,
No. 1021047
(Ala. Nov. 21, 2003)
(contracts; assignability;
jury misconduct; Conference America, Inc. is an Alabama corporation that
provides conference-call services. In 1995, Conference America was
selected by Telecommunications Cooperative Network of New York, Inc. ("Old
TCN"), a not-for-profit membership cooperative that assisted nonprofit
entities in using telecommunications services, to provide conference-call
services to members of Old TCN. In 1997, Conference America and Old
TCN entered into an agreement ("the 1997 agreement") pursuant to which
Conference America would pay Old TCN a 24% commission on the services Conference
America provided to members of Old TCN. The term of the 1997 agreement
extended from January 27, 1997, through December 31, 2000. The 1997
agreement was silent as to whether the agreement was assignable.
By early 1998, Old TCN was having financial difficulties and was close
to filing a petition for involuntary bankruptcy. Around that time,
David Altshuler, who had served as vice chairman on the board of directors
of Old TCN through July 1997, formed a for-profit corporation named Telecommunications
Management, Inc. ("TMI"). Pursuant to a management agreement between
Old TCN and TMI, Altshuler, as president of TMI, took over the management
of Old TCN. In July 1998, TMI changed its name to Telecommunications Cooperative
Network, Inc. ("New TCN"). In September 1998, the assets of Old TCN
– including its name, its goodwill, and the 1997 agreement -- were transferred
or assigned to New TCN and Old TCN was subsequently dissolved. New
TCN is a for-profit corporation, run by Altshuler as its sole officer and
director. Conference America claims to have had no knowledge of the
transfer of assets of Old TCN to New TCN, of the dissolution of Old TCN,
or of the creation of New TCN. After New TCN acquired the assets
of Old TCN, Conference America continued to provide services and to remit
commissions to New TCN pursuant to its 1997 agreement with Old TCN.
In December 1998, Conference America executed another agreement ("the 1998
agreement") virtually identical to the 1997 agreement that, among other
things, extended the term of the 1997 agreement through September 30, 2002.
The 1998 agreement referred to "TCN"; it did not distinguish between "Old"
TCN and "New" TCN. According to Conference America, New TCN held
itself out as being the same company as the dissolved Old TCN. Subsequently,
the relationship between Conference America and New TCN became strained.
Conference America sued New TCN, Altshuler, Chris Lipscomb, and others,
seeking, among other things, 1) damages for fraud, breach of contract,
repudiation of contract, and moneys paid by mistake under a void assignment
of the 1997 agreement, and 2) declaratory and injunctive relief.
New TCN and Lipscomb each filed a counterclaim. Following the trial,
however, the only claims that went to the jury were Conference America's
breach-of-contract and fraud claims, New TCN's counterclaim alleging breach
of contract and repudiation of contract, and Lipscomb's counterclaim alleging
breach of contract. The trial court granted New TCN's motion for
a judgment as a matter of law as to Conference America's claim that it
was entitled to moneys paid to New TCN by mistake because, it argued, the
1997 agreement was unassignable. The jury returned a verdict for
New TCN and Lipscomb on Conference America's breach-of-contract and fraud
claims and on their counterclaims. The jury awarded damages on the
counterclaims in the amounts of $1,007,499.97, and $1,000 to New TCN and
Lipscomb, respectively. The trial court entered a judgment on this
verdict. Following the verdict, Conference America discovered that
a juror had given erroneous answers in his questionnaire and on voir dire
examination. It confirmed this fact through investigation and memorialized
its discovery and initial investigation in a letter to the Court dated
November 8, 2002, enclosing its investigative material. On
November 22, 2002, Conference America filed motions for a judgment as a
matter of law, a new trial, and to alter, amend, or vacate the judgment,
asserting, among other things, juror misconduct and the alleged unassignability
of the 1997 agreement. The trial court denied Conference America's
postjudgment motions. HOLDING: The Supreme Court held
that that the trial court's rulings based on the assignability of the 1997
agreement were correct. However, the Court held that the juror misconduct
warrants a new trial. The Court also held that the trial court's
resolution of the equitable claims in this case is unaffected by any juror
misconduct and its judgment as to those claims is affirmed. The Court
held that the trial court did not err in denying Conference America's motion
for judgment as a matter of law regarding New TCN's counterclaims.)
*Download or view
PDF version of opinion*
-
Pittman v. United
Toll Sys., LLC,
No. 1021188 (Ala.
Nov. 21, 2003)
(automobile accident;
negligence; wantonness; assumption of the risk; summary judgment; Gayle
Pittman sued United Toll Systems, LLC ("United Toll"), State Farm Mutual
Automobile Insurance Company ("State Farm"), and certain fictitiously named
defendants, seeking to recover damages for injuries she sustained in an
automobile accident that occurred on the approach to a toll bridge operated
by United Toll. The accident was caused by a chain reaction set in
motion by icy conditions on the bridge. Pittman alleged negligence
and wantonness against United Toll and alleged breach of contract as to
both State Farm and United Toll. United Toll moved for a summary
judgment on all pending claims against it on the sole basis of the defense
of assumption of the risk. Pittman responded and the trial court,
after hearing oral arguments on the motion, entered a summary judgment
for United Toll on all claims without stating its rationale.
Pittman filed a motion to alter, amend, or vacate the trial court's judgment;
the court denied that motion. Pittman appealed. Pittman argues
that the trial court erred in entering a summary judgment for United Toll
because, she says, in response to its summary-judgment motion she presented
substantial evidence creating genuine issues of material fact (1) as to
whether she had actual knowledge and appreciation of the danger of ice
on the bridge and (2) as to whether she voluntarily proceeded onto the
approach to the bridge with an understanding that there was ice on the
bridge. HOLDING: The Supreme Court reversed as to the
summary judgment on the negligence and wantonness claims. The Court
held that no evidence was presented to indicate Pittman's "actual awareness"
that there was ice on the bridge before the driver of the truck lost control
of it. The Court also concluded that Pittman did not voluntarily
proceed with knowledge of the danger posed by ice on the bridge.
Therefore, the Court held that there exist genuine issues of material
fact to be resolved by the fact-finder as to whether Pittman assumed the
risk. The Court noted that Pittman did not challenge the summary
judgment on the breach-of-contract claim.)
*Download or view
PDF version of opinion*
-
Ex parte Leasecomm
Corp.,
Nos. 1021281 &
1021308 (Ala. Nov. 21, 2003)
(outbound forum-selection
clause; Aaron Cobb filed a putative class action against Galaxy Mall, Inc.
, a Utah company, and MicroFinancial, Inc., and its subsidiary, Leasecomm
Corporation, both Massachusetts companies (the Massachusetts companies
will hereinafter be collectively referred to as "Leasecomm"). The
complaint sought compensatory and punitive damages "in an amount not to
exceed $74,000 per class member." Recovery was sought on theories
of (1) breach of contract, (2) fraud, (3) fraudulent suppression, (4) conspiracy,
(5) theft by deception, (6) conversion, and (7) violation of statutory
usury laws. Galaxy Mall filed a "Motion to Enforce Forum Selection
Clause." The motion was based on a clause on the reverse side of
the order form provided by Galaxy Mall and signed by Cobb, which provided:
"[T]he parties agree that any and all disputes arising out of this transaction
... shall be resolved in the courts of the State of Utah in the County
of Utah or the United States District Court for the State of Utah."
Leasecomm had filed a similar motion based on a forum-selection clause
in the lease agreement entered into between Leasecomm and Cobb; that clause
provided: "The Parties hereby ... consent and submit to the exclusive jurisdiction
of the Courts of the Commonwealth of Massachusetts and expressly agree
to such exclusive forum for the bringing of any suit, action or other proceeding
arising out of their obligations hereunder, and expressly waive any objection
to venue in any such Courts ...." The trial court denied the motions,
stating: "[E]nforcement of either forum selection clause would be unreasonable
under the circumstances because the clauses effectively deny [Cobb] and
remaining Alabama customers ... their day in court." The trial court
held that enforcement of the outbound forum-selection clauses would be
"seriously inconvenient," and "unreasonable under the circumstances."
Glaxy Mall and Leasecomm filed petitions for writs of mandamus challenging
the trial court's ruling. HOLDING: The Supreme Court
denied the petitions for writ of mandamus. The Court noted that Galaxy
Mall and Leasecomm anticipate the splitting of Cobb's claims for separate
trials against Galaxy Mall and Leasecomm in Utah and Massachusetts, respectively.
The Court also noted that Alabama has a strong policy against splitting
causes of action or claims. The Court further noted that where a
plaintiff's suit is truly broader than the forum selection clause and the
structure of the complaint is not an attempt to avoid the forum selection
clause, enforcement of the forum selection clause would be unreasonable.
The Court concluded that the claims against Galaxy Mall and Leasecomm are
inextricably intertwined. The Court held that under the circumstances
of this case, it cannot conclude that the trial court exceeded its discretion
in denying the petitioners' motions.)
*Download or view
PDF version of opinion*
-
Ex parte Jackson,
No. 1021330 (Ala.
Nov. 21, 2003)
(tenure; dismissal
of public school teacher; Lucy Jackson was a teacher at Howard Elementary
School in Mobile. The principal at Howard Elementary recommended
that Jackson's employment be terminated, and the Mobile County School Board
voted 4-0 to terminate her employment. Jackson appealed her termination
to the Alabama State Tenure Commission ("the Commission"). As part
of discovery during her appeal, she requested all documents that would
be presented against her at the Commission's hearing. She was timely
provided with those documents and with summaries of the testimony that
would be presented against her at the hearing. Many of the documents
came from her personnel file -- to which all public-school teachers have
access upon request. However, some of the documents had been retained
outside her personnel file; Jackson was unaware of the existence of those
documents until the documents were provided to her pursuant to her discovery
request. After the hearing, the Commission upheld the decision of
the school board to terminate Jackson's employment. Jackson petitioned
the Mobile Circuit Court for a writ of mandamus ordering the Commission
to reverse its decision. The circuit court issued the writ, holding
that Jackson was not properly notified of the grounds of her termination.
The Commission appealed to the Court of Civil Appeals, which reversed the
judgment of the trial court issuing the writ. HOLDING:
The Supreme Court affirmed the Court of Civil Appeals. The Court
rejected Jackson's argument that certain records were unlawfully "retained,"
because their retention anywhere outside her "personnel file" was inconsistent
with Ala. Code §16-22-14. The Court held that even assuming
that the retention of the records violates §16-22-14, Jackson's argument
lacks merit, because she asserts no recognizable injury stemming from this
alleged violation.)
*Download or view
PDF version of opinion*
-
Ex parte Horton
Family Housing, Inc.,
No. 1021679 (Ala.
Nov. 21, 2003)
(discovery; arbitration;
Sabrina Burton and John Burton ordered a manufactured home from Horton
Family Housing, Inc. Mrs. Burton appears to have handled all aspects
of the transaction. The Burtons specially ordered linoleum for the
bedroom floor and a large Palladian window. Horton processed special
order homes such as the Burtons' only after financing was approved through
GreenPoint Credit, L.L.C., a financing company. On December 12, 2001,
GreenPoint Credit informed Horton that it had approved the financing for
the Burtons' home, stating on the application Mrs. Burton had submitted:
"all conditions have been met." Kim Temple, an employee of Horton,
then informed Mrs. Burton that her credit application had been approved.
Mrs. Burton signed three documents to complete the transaction: a buyer's
order form, an installment sales contract/security agreement, and a separate
arbitration agreement. The installment sales contract/security agreement
also contained an arbitration provision that contained the following language,
which did not appear in the separate arbitration agreement: "Any controversy
concerning whether an issue is arbitrable shall be determined by the arbitrator(s)."
When the manufactured home was complete, Horton delivered it to the Burtons'
property. However, Horton was unable to place the home on its designated
site because the property had not been adequately prepared. After
its unsuccessful attempt at delivery, Horton returned the home to its place
of business. At some point after delivery of the manufactured home
was attempted, GreenPoint Credit informed both parties that it could not
confirm Mrs. Burton's income and thus that it was withdrawing its approval
of the loan. The Burtons filed this action in the Elmore Circuit
Court claiming fraudulent misrepresentation, fraud by forgery, failure
to disclose, conversion, negligence, wantonness, negligent delivery and
removal, and wanton delivery and removal. Horton and Temple filed
an answer and a motion to dismiss, or, alternatively, to compel arbitration.
The Burtons immediately filed notice of their intent to serve a subpoena
on GreenPoint Credit and noticed the taking of the deposition of Horton's
president, Trey Horton. At this point, Horton and Temple filed a
motion for a protective order to halt discovery, which the trial court
initially denied on June 25, 2003. Horton and Temple subsequently
filed a petition for a writ of mandamus. The day Horton and Temple
filed the petition, the trial court issued a protective order "as to issues
beyond the substance of the existence of the sales/financing agreement." HOLDING: The
Supreme Court denied the petition. The Court held that whether
GreenPoint Credit extended financing to the Burtons is central to this
dispute, and the Burtons are entitled to conduct limited discovery on matters
related to the financing. The Court stated that on June 25, the trial
judge denied Horton and Temple's motion for a protective order, which would
have placed some limit on discovery, and that in so deciding, the judge
exceeded his discretion. The Court stated that if the order had stood,
the trial court would have committed reversible error. However, on
July 9, the judge issued a protective order which appropriately limited
the Burtons' discovery to whether financing had been approved; if it had
been approved, when; and if and when financing was later withdrawn.
The Court stated that if the trial court permits discovery beyond those
bounds, Horton and Temple are free to again petition for mandamus relief.)
*Download or view
PDF version of opinion*
-
Ex parte Town of
Valley Grande, Alabama,
No. 1021744 (Ala.
Nov. 21, 2003)
(municipal incorporation;
appellate procedure; On December 13, 2002, residents of the Valley
Grande community who were inhabitants, property owners, and qualified electors
filed a petition for incorporation of the community of Valley Grande in
the Dallas County Probate Court. On December 16, 2002, the probate
court held a hearing and after reviewing the petition and the evidence
granted the petition to incorporate and ordered an election on the question
of whether to incorporate the Town of Valley Grande, Alabama. The
election was held on January 9, 2003. On January 8, 2003, Rita M.
Lett and Tamara Duncan Smith filed a petition in the Dallas Probate Court
seeking to vacate the probate court's order granting the petition to incorporate
and ordering an election. The probate court, on that same day, entered
an order allowing the January 9 election to proceed, and it agreed to address
the matters raised in Lett and Smith's petition to vacate after the election.
On January 9, 2003, the election on the incorporation question was held.
The results of that election were 821 votes for incorporation and 90 votes
against incorporation. Election inspectors certified the election
results and their certificate was filed with the probate court on January
11, 2003. On January 16, 2003, the probate court held a hearing on
Lett and Smith's petition to vacate and on several other objections raised
by Lett and Smith, including allegations that the metes and bounds description
in the petition for incorporation was incorrect, that some parties who
signed the petition were not residents, and that absentee ballots had not
been provided for the election. On January 30, 2003, the probate
court issued an order rejecting Lett and Smith's objections. Specifically,
in its order the probate court found that the description of the property
to be incorporated included with the petition for incorporation was an
accurate description by metes and bounds of the area proposed to be incorporated
and that it met the statutory requirements as interpreted by Alabama Supreme
Court caselaw; that Lett and Smith's challenge with regard to the alleged
failure to provide absentee ballots was meritless, in light of Ala. Code
§11-41-1 et seq.; and that the statutory and jurisdictional requirements
in effect on the date the petition for incorporation was filed had been
met and that, therefore, the jurisdiction of the probate court was properly
invoked. On January 31, 2003, Smith and Lett filed a petition for
a writ of mandamus and prohibition in the Dallas Circuit Court, asking
that court to direct the probate court to vacate its order granting the
petition to incorporate and setting the date for the incorporation election
and to issue a writ prohibiting the probate judge from certifying and recording
the results of the election. On February 3, 2003, the probate court
entered an order of incorporation for the Town of Valley Grande.
On July 7, 2003, the persons who petitioned for an order of incorporation
for the Town of Valley Grande (hereinafter "the Valley Grande citizens")
filed in the circuit court a motion to dismiss Lett and Smith's petition
for the writ of mandamus. In its motion, the Valley Grande citizens
argued that the circuit court did not have jurisdiction to entertain Smith
and Lett's petition because, it said, the probate court's order of incorporation,
entered on February 3, 2003, constituted a final judgment, and the
only remedy available to Lett and Smith was by an appeal. On July
15, 2003, the circuit court denied the motion to dismiss filed by the Valley
Grande citizens. On July 18, 2003, the Valley Grande citizens
filed a petition for a writ of mandamus with the Supreme Court. In
its petition, the Valley Grande citizens argued that the circuit court
should have dismissed Lett and Smith's petition for the writ of mandamus
because, it said, Smith and Lett's proper means of review of the probate
court's order was by an appeal. HOLDING:
The Supreme Court granted the petition. The Court held that Lett
and Smith had an adequate remedy by appeal; accordingly, a petition for
a writ of mandamus filed in the circuit court was not the appropriate means
of review in this case. The Court directed the circuit court to dismiss
Lett and Smith's petition for a writ of mandamus and prohibition.)
*Download or view
PDF version of opinion*
-
Ex parte B.D.S.,
No. 1021936 (Ala.
Nov. 21, 2003)
(The Supreme Court
denied the petition for writ of certiorari without opinion, but the
Court stated that in denying the petition for the writ of certiorari, the
Court does not not wish to be understood as approving all the language,
reasons, or statements of law in the Court of Civil Appeals’ opinion.)
*Download or view
PDF version of opinion*
-
Ex parte B.D.S.,
No. 1021939 (Ala.
Nov. 21, 2003)
(The Supreme Court
denied the petition for writ of certiorari without opinion, but the
Court stated that in denying the petition for the writ of certiorari, the
Court does not not wish to be understood as approving all the language,
reasons, or statements of law in the Court of Civil Appeals’ opinion.)
*Download or view
PDF version of opinion*
Opinions Released Nov. 17, 2003
-
Ex parte Anonymous,
No. 1030172 (Ala.
Nov. 17, 2003)
(Opinion quoted in
full: "This Court, by order of November 7, 2003, reversed the Court
of Civil Appeals' judgment and remanded this matter for that court
to "remand this cause to the trial court and order that court to
detail sufficiently the basis for appropriate findings and immediately
to conduct such further proceedings, to include taking additional
testimony or admitting further evidence, that may be necessary in order
to do so." Ex parte Anonymous,
[Ms. 1030172, November 7, 2003] ___ So. 2d ___, ___ (Ala. 2003).
The burden of proof with respect to both the maturity/well-informed prong
and the best-interest prong of § 26-21-4(f), Ala. Code 1975,
lies with the minor. In re
Anonymous, 833 So. 2d 75, 78 (Ala. Civ. App. 2002). After
having reviewed the trial court's order entered on November 13, 2003,
on remand, this Court concludes that the trial court's finding as
to the maturity/well-informed prong is sufficiently supported by
the record. This Court further concludes that the minor failed to
carry her burden of proof as to the best-interest prong, particularly in
light of the absence of evidence as to the attitude or ability of
the minor's father to assist her and as to whether an abortion is
in her physical or emotional best interest. AFFIRMED.")
*No PDF version of
this opinion is available*
Opinions Released November 14, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON FRIDAY, NOVEMBER 14, 2003
-
Ex parte Sears Roebuck
& Co.,
No. 1020251 (Ala.
Nov. 14, 2003)
(discovery; The underlying
dispute in this case involves a workplace injury a Sears Roebuck and Co.
employee, Sonya Salter, suffered on December 1, 2000. On October 3, 2001,
Salter sued Sears Roebuck and Co., and its employees Debbie McCarley, Frank
Blankenship, and Larry Collins (hereinafter collectively "Sears"), alleging
fraud, concealment, misrepresentation, intentional infliction of emotional
distress, and suppression arising from the injury to her right foot. Sears
denied Salter's claims and moved for a summary judgment. The trial
court entered a scheduling order that provided that all discovery in Salter's
action was to be completed by March 31, 2002. On March 23, 2002, Salter
served Sears with interrogatories and requests for the production of documents.
On April 26, 2002, Sears responded to Salter's discovery requests, objecting
to the production of certain documents. Salter moved to compel Sears to
produce the documents. On May 10, 2002, the trial court denied Sears's
summary-judgment motion and granted Salter's motion to compel. On May 17,
Sears moved the trial court to certify its denial of Sears's summary-judgment
motion for an interlocutory appeal pursuant to Rule 5, Ala.R.App.P. On
May 20, Salter moved pursuant to Rule 37, Ala.R.Civ.P., to enforce the
trial court's discovery order, and on May 24, Sears moved for a protective
order. On May 31, the trial court certified its denial of Sears's summary-judgment
motion for an interlocutory appeal, stayed the proceedings in the case
except for discovery, denied Sears's motion for a protective order, and
ordered Sears to provide Salter with the requested discovery within 10
days. Sears sought permission for an interlocutory appeal of the
denial of its summary-judgment motion with the Supreme Court, but
did not provide Salter with any of the requested documents pursuant to
the trial court's discovery order. On June 19, 2002, Salter again moved
to compel production of the documents. On June 26, the trial court entered
an order explaining that it did not stay discovery in its May 31, 2002,
order. The trial court ordered Sears to provide Salter the requested discovery
by July 1, 2002, and warned that it would sanction Sears by striking its
pleadings if Sears failed to comply with the order. On July 1, 2002,
Sears filed with this Court an earlier petition for a writ of mandamus
seeking protection from the discovery order. Sears also moved the
trial court for a stay of discovery while its mandamus petition was pending.
On July 19, 2002, the Supreme Court denied Sears's petition for permission
to take an interlocutory appeal, finding that the trial court's certification
failed to include a statement of the controlling issue of law, and it also
denied Sears's mandamus petition. On July 25, 2002, Sears moved the
trial court to amend its May 31 order to include a proper statement of
the controlling issue of law, and to recertify its order for an interlocutory
appeal. On August 26, the trial court denied Sears's motion to recertify
its order. The trial court also struck Sears's "pleadings as they relate
to the fraud claims of [Salter]" as a sanction, because Sears had failed
to comply with the July 1, 2002, discovery deadline. Sears moved
the trial court to reconsider the sanction it had imposed for Sears's violation
of its discovery order. The trial court conducted a hearing on the issue.
On October 1, 2002, the trial court denied Sears's motion to reconsider
the discovery sanction. Sears now petitions the Supreme Court for a writ
of mandamus ordering the trial court to vacate its order striking Sears's
pleadings as to Salter's fraud claims. HOLDING: The
Supreme Court denied the petition. The Court held that because Sears
failed to comply with the trial court's June 26, 2002, order to provide
Salter with the requested discovery by July 1, the trial court judge was
well within his discretion to sanction Sears for discovery abuse.
The Court left it to the trial court to clarify what aspect of the
"pleadings" it intended to strike.)
*No PDF version of
this opinion is available*
Court of the Judiciary Judgment Released November 13, 2003
Opinions Released November 7, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON FRIDAY, NOVEMBER 7, 2003
-
Harrelson v. R.J.,
No. 1012233 (Ala.
Nov. 7, 2003)
(assault and battery;
the tort of outrage; punitive damages; R.J. allowed her 15-year-old
daughter, J.B., to spend the night with J.B.'s 15-year-old friend, M.B.,
after the two had returned from a weekend ROTC meet. At that time,
M.B. lived with her mother and with her stepfather, Anthony Harrelson.
Later that night, M.B.'s mother and Anthony went to a nightclub to celebrate
Anthony's birthday, leaving M.B. and J.B. alone in the house. The
girls spent the evening watching television, talking on the telephone,
and using the computer. Eventually, they went to sleep in M.B.'s
bed, which was positioned under the window in her bedroom. M.B. testified
that she always locked her bedroom door before going to sleep at night,
and that when she and J.B. went to sleep, her bedroom door was locked.
In the early morning hours of March 15, 1999, M.B. and J.B. were awakened
when Anthony tapped on M.B.'s bedroom window. Anthony told M.B. that
he and her mother were locked out of the house. Apparently, M.B.'s
mother was very intoxicated and had become ill in the car on the way home.
M.B. got up and unlocked one of the doors for Anthony and her mother.
M.B. went back to her bedroom, locked the door, and she and J.B. fell asleep.
A short time later, the girls were awakened again when Anthony tapped on
the window. M.B. opened the window, and Anthony began talking with
them. Anthony gave them a wine cooler through the window and M.B.
and J.B. drank it. J.B. testified that while Anthony was talking
to her through the window, she could tell that he had been drinking because
she could smell alcohol and because he was talking and acting differently
than he normally did. She said that Anthony told her that she was
"hot," and she believed that he was flirting with her. M.B. testified
that she did not know what to think about Anthony's demeanor toward J.B.,
but that the conversation made her uncomfortable. During the course
of the conversation with Anthony, M.B. and J.B. each left the bedroom to
go to the bathroom. J.B. was the last one to come back into the bedroom,
and she did not lock the door. After the girls finished the wine
cooler, they passed the empty bottle back through the window to Anthony,
who threw it into a nearby field. Anthony left to feed his pet wolves,
and the girls closed the window and went back to sleep. J.B. testified
that she was awakened a short while later by Anthony, who was standing
over her and touching her. After Anthony left, J.B. and M.B. both
got out of bed. When J.B. told M.B. what Anthony had done, both girls
started crying. They did not sleep for the rest of the night.
The next day at school, J.B. told one of her teachers what had happened.
The teacher insisted that J.B. inform the principal and assistant principal;
she did so and the principal and assistant principal then contacted the
Department of Human Resources ("DHR"). The State brought criminal
charges against Anthony Harrelson. He was tried and convicted of
sexual abuse in the second degree, a Class A misdemeanor. R.J., individually
and as mother and next friend of J.B., sued the Harrelsons. In her
complaint, R.J. alleged assault and battery and the intentional infliction
of emotional distress, i.e., the tort of outrage, against Anthony, negligence
against M.B.'s mother, and loss of services of a child against Anthony
and M.B.'s mother. The case was tried before a jury. At the
close of the evidence, the trial court entered a judgment as a matter of
law in favor of both defendants as to R.J.'s claim for loss of services
of a child and in favor of M.B.'s mother as to R.J.'s negligence claim.
M.B.'s mother was then dismissed from the action. The assault-and-battery
and tort-of-outrage claims were then submitted to the jury. The jury
returned a verdict in favor of R.J. on both counts. The jury awarded
R.J. $5,000 compensatory damages and $25,000 punitive damages on the assault-and-battery
claim. The jury awarded R.J. $10,000 compensatory damages and $50,000
punitive damages on the tort-of-outrage claim. HOLDING:
The Supreme Court affirmed. The Court held that, despite Anthony's
contentions, R.J. presented substantial evidence from which a jury could
find that J.B. suffered severe emotional distress as a result of Anthony's
conduct. The Court held that the punitive damages award was justified
because Anthony's conduct was extremely reprehensible, the punitive damages
in this case were five times the relatively low compensatory-damages award,
Anthony's behavior is punishable by criminal statutes in the State of Alabama,
and the record does not support Anthony's allegations that the punitive-damages
awards against him "will result in complete financial devastation for which
there can be no relief.")
*Download or view
PDF version of opinion*
-
Cashion v. Torbert,
No. 1020886 (Ala.
Nov. 7, 2003)
(estate administration;
insolvent estate; attorney fees; The appeal of a related case involving
the same parties was decided in Cashion v. Torbert, No. 1020449
(Ala. Aug. 29, 2003). This appeal arises out of the same "fairly
convoluted procedural history." Mary Dixon Torbert, an attorney in
Montgomery, served during Dot Smith's life as the court-appointed conservator
of her estate, and, upon final settlement of that conservatorship, was
awarded an attorney's fee of $15,298.75. After Ms. Smith died, Torbert
filed a claim against her estate, of which Cashion was the successor executrix,
for her attorney-fee award as conservator. Cashion subsequently determined
that the estate was insolvent and filed a report of insolvency with Reese
McKinney, Jr., Judge of Probate of Montgomery County. She listed
the total assets of the estate as $18,511.46. In her report of insolvency,
Cashion itemized the claims had been filed against the estate, indicating
as to each claim the subsection in Ala. Code §43-2-371 to which Cashion
believed it should be assigned. Additionally, Cashion requested reimbursement
of expenses incurred by her and her predecessor executrix in the amount
of $1,800, and payment of "attorneys fees of approximately $4,000.00 to
date." Cashion asserted that the $5,800 represented by those two
items was due to be paid as a debt under §43-2-371(2), representing
"fees and charges of administration." On January 18, 2002, Judge
McKinney issued a "Decree of Insolvency," declaring the estate insolvent
and ordering "that Amanda Linn Cashion, as executrix, appear and make a
statement of her administration for final settlement of said estate on
the 25th day of February, 2002, at 1:30 o'clock p.m." The hearing
was held as scheduled on February 25, and Judge McKinney heard Cashion's
statement of her administration of the estate "and any objections to same."
On March 5, Judge McKinney issued his "Order on Final Settlement," in which
he found, "upon consideration of all the evidence, testimony, and briefs,"
that the available assets of the estate amounted to $18,511.46, and that
they should be disbursed to satisfy certain claims and expenses of the
estate, including Torbert's claim, reduced from the $15,298.75 awarded
by Judge McCooey to $15,286.11." In his March 5 order, Judge McKinney
further declared that Torbert would "be responsible for paying outstanding
debts that were incurred under the Conservatorship of Dot C. Smith (Treasure
[Chest] Antiques $2,070.00 and [Green] $478.79) from the funds she will
receive from this Estate ...." The order also directed payment of
the bill of Hamilton Funeral Home, the expenses incurred by Cashion and
her predecessor executrix in the amount of $1,800, and court costs in the
amount of $414.50. Thus, the aggregate amount of the claims and court
costs approved was $18,511.46, exactly matching the funds available for
payment of claims and expenses. No mention was made of the claims
of South Haven Health & Rehabilitation ("South Haven"), American Pharmaceutical
Services, and Alabama Gas Company. Although in the report of insolvency
Cashion characterized the $4,000 component of her $5,800 claim as "attorney
fees," in her brief in support of the report of insolvency she clarified
the $5,800 claim as one being made on behalf of herself and the predecessor
executrix "under Ala. Code §43-2-371(2), for $5,800 for fees and charges
that accrued for the administration of the Estate." On July 11, 2002,
Cashion filed in the circuit court formal objections to the claims against
the estate filed by Alabama Gas Company, Green, Treasure Chest, and Torbert.
On August 9, Torbert moved to strike all of the objections, contending
that Ala. Code §43-2-747 required such obligations to be presented
to, and resolved by, the probate court and that, therefore, they could
not be presented for the first time in the circuit court, because the circuit
court's review was not de novo but was limited to the record from the probate
court. Cashion argued that, under Ala. Code §43-2-747 she had
six months after the estate was declared insolvent to file an objection,
but that Judge McKinney had "prematurely" entered the final settlement
order, leaving her with no choice but to file the objections in the circuit
court. On December 5, 2002, Judge Shashy granted Torbert's motion
to strike Cashion's objections and affirmed Judge McKinney's order on final
settlement.
HOLDING: The Supreme Court held that the probate court erred
in disallowing entirely Cashion's claim for compensation for the services
she rendered to the estate, but the Court held that the maximum allowable
amount of compensation was $925.58. The Court found no reversible
error with respect to Judge McKinney's classification of Torbert's claim.
The Court affirmed as to most of the other issues raised.)
*Download or view
PDF version of opinion*
-
Dickinson v. Land
Developers Constr. Co.,
Nos. 1021276 &
1021277 (Ala. Nov. 7, 2003)
(statute of limitations;
discovery rule; claims of breach of contract, fraud, mental anguish and
emotional distress, negligent and/or wanton inspection, breach of the warranty
of habitability, and breach of the implied warranty of merchantability
arising from the construction of a house; claims of breach of contract,
fraud, negligence, and negligence per se arising out of termite damage
to a house; Douglas and Barbara Dickinson and Land Developers Construction
Company, Inc. entered into a contract for the construction of a house.
Cook's Pest Control, Inc. issued the Dickinsons a "Subterranean Termite
Control Damage Replacement Guarantee" for this house on February 25, 1993.
This guarantee was effective for one year and was renewable annually.
Pursuant to this guarantee, Cook's provided an initial inspection and pretreatment
of the Dickinsons' house against termites and conducted annual inspections
thereafter. Those annual inspections checked, among other things,
the moisture level of the house. The Dickinsons moved into their
house on December 20, 1993. Shortly after moving in, the Dickinsons
began to notice a number of problems with their house. In early January
1994, the Dickinsons provided Land Developers with a "punch list" of items
that needed to be completed. On October 2, 1994, the Dickinsons sent
Land Developers another list of items that still needed to be addressed.
Six to nine months after moving into their residence, the Dickinsons discovered
seals on certain of the windows were broken. On November 17, 1994, the
Dickinsons' architect prepared a list of problems with the French doors
in the house. In early 1995, the Dickinsons documented a leak in
their "pool bath." On May 1, 1995, the Dickinsons wrote a letter to Land
Developers stating that they would like Land Developers to address the
noted problems as soon as possible and listing seven areas of concern with
the house. On May 13, 1995, the Dickinsons sent a memorandum to Land
Developers concerning cracks in the driveway and a water leak under their
driveway and asking when it would address the previously noted problems.
The inspection report prepared by Cook's in 1995 noted that there was some
water seepage in the crawl space under the house and that some wood material
was "below grade," i.e., below the ground level. However, the reports
prepared by Cook's in 1996 through 2000 failed to note any water seepage;
the 1996 report stated that everything "Looks good!" Furthermore,
the 1996, 1998, and 1999 reports prepared by Cook's concurred with the
1995 report in stating that there was wood in the Dickinsons' house that
was below the outside grade level, but the 1994, 1997, and 2000 reports
indicated that there was no wood below the outside grade level. On
April 26, 1996, the Dickinsons sent Land Developers a letter by certified
mail; the letter outlined 11 residual problems with the house. Land
Developers never responded to this letter. On October 30, 1999, the
Dickinsons sent another letter via certified mail to Land Developers requesting
that it fix several problems with the house. After Land Developers
failed to respond to the October 30, 1999, letter, the Dickinsons hired
a structural engineer, Joel Wehrman, to inspect their house. In his
report, Wehrman found that there was a separation between the brick veneer
and the doorframes of the French doors at the rear of the house.
Wehrman opined that the separation was caused by the rotting of the wooden
basement wall, which had resulted from the use of untreated wood in constructing
the basement wall. Wehrman stated that the decay of the belowground
wooden wall was inevitable. Wehrman also found that the use of the
wooden wall resulted in a lack of lateral support for the house and could
contribute to the separation of the superstructure from the foundation.
In addition, Wehrman found that the driveway, walkway, and patio were cracking.
Wehrman stated that this resulted from their having been constructed on
fill soils, which had settled since construction. At Wehrman's suggestion,
and with his oversight, the Dickinsons began the demolition and reconstruction
of part of their house in February 2000. The cost of the demolition
and reconstruction was $731,833.50. Before the demolition and reconstruction,
no termite activity was reported and the moisture-content levels measured
by Cook's in its annual inspections were never at or above 20% (a level
of 20% or above would have indicated a greater chance of wood decay and
insect infestation). During the demolition and reconstruction of
the Dickinsons' house, however, Cook's discovered termite activity in the
belowground wooden wall, which was located at the rear of the house.
After being informed by Cook's of the termite infestation, the Dickinsons
hired a termite consultant to inspect their home. This consultant
observed the termite infestation in the rear of the house and, after evaluating
Cook's pretreatment of the Dickinsons' house, concluded that Cook's should
have applied 600 to 700 gallons of the insecticide Dursban to the Dickinsons'
house. The records maintained by Cook's reflect that it applied only 444
gallons of Dursban. On December 21, 1999, following receipt of the
Wehrman report, the Dickinsons sued Land Developers in the Shelby Circuit
Court, seeking damages for breach of contract, fraud, mental anguish and
emotional distress, negligent and/or wanton inspection, breach of the warranty
of habitability, and breach of the implied warranty of merchantability
arising from the construction of the Dickinsons' house. On October
27, 2000, the Dickinsons sued Cook's in the same court, seeking damages
for breach of contract, fraud, negligence, and negligence per se arising
out of termite damage to their house. The actions were consolidated
following a motion filed by the Dickinsons. Land Developers and Cook's
both filed motions for a summary judgment; the trial court granted
both motions, holding that the Dickinsons' claims against Land Developers
and Cook's were time-barred. HOLDING: The Supreme Court
noted that the Dickinsons discovered a number of problems with their house
at an early stage, including roof leaks, problems with the French doors
and window seals, a leaking pool bath, water damage in parts of their home,
and cracks in and moisture on the driveway. The Court held that insofar
as the Dickinsons' claims against Land Developers arise out of these problems,
they are barred by the two-year statutory limitations period of Ala. Code
§6-5-221. The Court held that Land Developers failed to show
that the problems the Dickinsons experienced with their house shortly after
construction was completed would cause a reasonable person to discover
the existence of the rotten belowground wooden wall or the allegedly improperly
compacted fill soil. The Court held that the question of when the
Dickinsons should have discovered the serious structural defects in their
house, such as the rotten belowground wall and the allegedly improperly
compacted fill soil, may not be decided as a matter of law, and a jury
question exists as to when the Dickinsons discovered facts sufficient to
maintain their claims against Land Developers. The Court affirmed
the summary judgment in favor of Cook's.)
*Download or view
PDF version of opinion*
-
Randall v. Water
Works & Sewer Bd. of the City of Birmingham,
No. 1021289 (Ala.
Nov. 7, 2003)
(municipal referendum;
jurisdiction; standing; ripeness; On or about October 2, 2002, a group
of electors in the City of Birmingham (hereinafter referred to collectively
as the "electors") filed with Michael F. Bolin, the probate judge for Jefferson
County, a "Petition for Ordinance to Reclaim the Water Works Assets for
the City of Birmingham." The electors requested that the probate
judge certify their petition and submit the proposed ordinance to the Birmingham
City Council for adoption by initiative or by referendum election.
The electors filed their petition pursuant to the authority purportedly
granted by Act No. 294, Ala. Acts 1965. The purpose of the proposed
ordinance was "to implement a plan to satisfy and redeem the debt of the
Water Works and Sewer Board of the City of Birmingham in order to administer
more effectively such systems and use the surplus revenues therefrom for
needed improvements in city schools and other projects." In order
to accomplish this purpose, the ordinance authorized the City of Birmingham
to redeem the debts of the Water Works and Sewer Board of the City of Birmingham
("the Board") and to cause the dissolution of the Board by operation of
law, which would then vest title to the assets of the Board in the City.
At the time the electors submitted their petition, the outstanding indebtedness
of the Board was $550 million. The ordinance submitted by the electors
would appoint David A. Sullivan as a special attorney for the City and
would grant him virtually unlimited authority to accomplish the purpose
of the ordinance. In addition, the proposed ordinance requires the
mayor and all employees, consultants, and attorneys for the City to assist
and cooperate with Sullivan and to pay "all invoices for actual expenses
incurred and provid[e] all information and assistance as requested by Mr.
Sullivan." Under the ordinance, Sullivan was to be compensated
for his services as special attorney for the City on a contingent basis,
depending upon whether the City successfully reclaimed the Board's
assets. If the City was successful in its effort to take over the
Board's assets, Sullivan would receive $350 per hour for the hours he worked
or 3% of the dollar amount of the bonds issued, whichever was greater.
Because the Board's outstanding debt is $550 million, Sullivan stood to
earn a contingent fee of at least $16.5 million if the purpose of the ordinance
was accomplished. The probate judge determined that the petition,
as amended, contained the signatures of a sufficient number of qualified
electors. Judge Bolin indicated that he intended to certify the petition
and submit the proposed ordinance to the Birmingham City Council unless
and until a court of competent jurisdiction instructed him otherwise.
Before the probate judge could certify the petition and order that the
proposed ordinance be submitted to the Birmingham City Council for consideration,
the Board filed a declaratory-judgment action in the Jefferson Circuit
Court. In its declaratory-judgment action, the Board alleged (1)
that Act No. 294, under the authority of which the ordinance was presented,
no longer applied to the City of Birmingham; (2) that Act No. 294 was unconstitutional;
(3) that the action contemplated by the proposed ordinance was beyond the
authority of the Birmingham City Council; (4) that the proposed ordinance
was invalid on its face; (5) that the proposed ordinance improperly delegated
to Sullivan, the special attorney, the legislative authority of the Birmingham
City Council; (6) that the actions contemplated by the proposed ordinance
would violate the Board's contractual obligations; (7) that the proposed
ordinance contained subjects that were improper for initiative ordinances;
and (8) that the proposed ordinance was overbroad, vague, and ambiguous.
In addition to seeking declaratory relief, the Board sought a temporary
restraining order and a permanent injunction preventing the probate judge
from certifying the petition for consideration by the Birmingham City Council.
The trial court entered a temporary restraining order prohibiting Judge
Bolin from certifying the petition and from presenting the proposed ordinance
to the Birmingham City Council. Shortly after the issuance of the
temporary restraining order, the electors moved to intervene in the Jefferson
Circuit Court action as defendants; the trial court granted their motion.
The trial court also granted the City's motion to intervene as a defendant.
The Board and the electors filed motions for a summary judgment.
On December 13, 2002, the trial court held a hearing on the motions.
On February 5, 2003, the trial court entered a summary judgment for the
Board, finding that the proposed ordinance "unlawfully and unreasonably
delegates the power of the City. The Court finds that the ordinance
is void and is not to be certified." The trial court then dissolved
the temporary restraining order directed at Judge Bolin, finding no further
need for the restraining order. On appeal, the electors argued that
the Jefferson Circuit Court lacked jurisdiction to hear the Board's declaratory-judgment
action because (1) the issue whether the Board's debt might be paid in
full by the issuance of refunding bonds pursuant to the ordinance is a
mere possibility and therefore is not ripe for judicial resolution; thus,
no case or controversy exists; (2) the Board failed to allege that it would
be injured by the City Council's consideration of the proposed ordinance
and, therefore, the Board lacked standing to obtain a judicial ruling on
the proposed ordinance; and (3) pursuant to Act No. 294, the probate court,
not the circuit court, has been specially designated to resolve claims
regarding proposed ordinances like this one. HOLDING:
The Supreme Court affirmed. The Court concluded that in its complaint
the Board alleged an actual controversy even though the proposed ordinance
had not yet been adopted or enacted. The Court held that the circuit
court had subject-matter jurisdiction of this action because the Alabama
Constitution grants the circuit courts of this state general jurisdiction
over all cases except as may be limited by law and it found no statutory
limitation in this case. The Court also held that all necessary parties
were present. The Court held that the Board had standing. The
Court held that the proposed ordinance is invalid, but for a different
reason from the trial court. The Court noted that the ordinance proposed
to place David A. Sullivan, a special attorney, in control of the waterworks
system. Thus, the Court held that the ordinance proposed to transfer
to Sullivan those powers that by virtue of Ala. Code §11-50-230
et seq. have been squarely placed in the hands of the board of directors
of the waterworks system. The Court therefore held that the proposed
ordinance conflicted with §11-50-230 et seq. and is invalid.)
*Download or view
PDF version of opinion*
-
Ex parte Perfection
Siding, Inc.,
Nos. 1021363 &
1021369 (Ala. Nov. 7, 2003)
(venue; doing business
by agent; Chris Sealy filed a complaint in the Hale Circuit Court, seeking
damages for injuries he sustained in a fall from the roof of a building
in Tuscaloosa County. Sealy alleges that he sustained his injuries
while he was an employee of Perfection Siding, Inc. ("Perfection"), which,
at the time of Sealy's fall, was performing subcontracting work for Bill
Lunsford Construction, Inc. Sealy sued Perfection and Lunsford Construction,
as well as Dennis Hall and Russ Lewis (Sealy's supervisors at Perfection),
seeking damages based on negligence and negligent hiring or contracting.
Sealy also sought damages from the petitioners for intentionally failing
to provide a safe workplace, and Sealy sought workers' compensation benefits
from Perfection. The defendants moved to transfer the case to Tuscaloosa
County, either because venue in Hale County was improper or, in the alternative,
because the doctrine of forum non conveniens mandated a transfer to Tuscaloosa
County. The trial court denied the motions. Perfection, Hall,
and Lewis (the "petitioners") filed petitions for writ of mandamus.
HOLDING: The Supreme Court denied the petitions. The
Court noted that because the petitioners are all residents of Tuscaloosa
County and a substantial part of the events giving rise to the claim occurred
in Tuscaloosa County, which is also where the principal office of Perfection
is located, venue was proper in Tuscaloosa County. However, the Court
noted that because Sealy resided in Hale County when the cause of action
arose, venue would be proper in Hale County under Ala. Code §6-3-7(a)(3)
if Perfection "does business by agent" currently in Hale County.
The Court noted that although of the approximately 1,000 jobs Perfection
performs annually, only two or three were located in Hale County in the
year Sealy sustained his injuries. However, the Court held that the
trial judge could have determined that Perfection was doing business in
Hale County in the present, not the past, primarily because Perfection's
work there was performed within the same calendar year as Sealy sustained
his injuries. The Court found it meaningful that Perfection actually
performed services in Hale County. The Court also held that Tuscaloosa
County was not shown to be significantly more convenient than Hale County.)
*Download or view
PDF version of opinion*
-
Elizabeth Homes,
L.L.C. v. Gantt,
No. 1021661 (Ala.
Nov. 7, 2003)
(arbitration; interstate
commerce: Elizabeth Homes, L.L.C. is in the business of constructing single-family,
semicustom residential structures. Customers of Elizabeth Homes select
a design from the house plans available; according to Elizabeth Homes,
the customers are then allowed to modify those plans to meet their individual
needs and tastes. Roy G. Gantt and Patty R. Gantt are residents of
Elmore County. On or about March 7, 2001, they contracted with Elizabeth
Homes for the construction of an "Ambassadore" style house on property
the Gantts owned in Wetumpka. The Gantts agreed to pay Elizabeth
Homes $76,500 for the construction of the house. The Gantts entered
into a purchase agreement with Elizabeth Homes; that agreement contained
an arbitration agreement. Elizabeth Homes completed the Gantts' house
in December 2001. In June 2002, the Gantts notified Elizabeth Homes
of numerous defects and deficiencies in the house. On January 16,
2003, the Gantts sued Elizabeth Homes, James D. Flanagan, and Carl Smith
in the Elmore Circuit Court, alleging breach of warranty, negligence and/or
wantonness, fraudulent misrepresentation, breach of contract, breach of
an implied warranty of habitability, unjust enrichment, and breach of implied
duties of good faith and fair dealing. Elizabeth Homes filed a motion
seeking to enforce the Gantts' agreement to arbitrate "any and all disputes
arising under" the purchase agreement. The Gantts' only argument
to the trial court was that the transaction did not meet the interstate-commerce
requirement. The trial court denied Elizabeth Homes' motion.
HOLDING: The Supreme Court reversed. The Court held
that Elizabeth Homes also established that the transaction at issue – the
construction and sale of the Gantts' house – involved interstate commerce.)
*Download or view
PDF version of opinion*
-
Ex parte Perry,
No. 1022093 (Ala.
Nov. 7, 2003)
(The Supreme Court
denied the petition for writ of certiorari without opinion, but the Court
stated that in denying the petition, it did not wish to be understood as
approving all the language, reasons, or statements of law in the Court
of Civil Appeals' opinion.)
*Download or view
PDF version of opinion*
-
Ex parte Anonymous,
No. 1030172 (Ala.
Nov. 7, 2003) (plurality opinion)
(abortion; minor;
judicial bypass for parental consent; An unemancipated 16-year-old girl
(the "minor") filed a petition on October 8, 2003, pursuant to the Parental
Consent Act, Ala. Code §26-21-1 et seq. ("the Act"); when she filed
the petition she was approximately eight weeks pregnant. The trial
court appointed separate guardians ad litem for the minor and for the baby.
The trial court conducted a hearing at which the minor testified on direct
examination by her attorney, was cross-examined by the guardian ad litem
for the baby, and answered questions posed by the trial court. After
hearing the evidence, the trial court entered an order concluding as follows:
"Based on the evidence and its observation of the petitioner, the Court
cannot find that she is mature enough and well-informed enough to make
this decision on her own. Taking into consideration the risks involved
and her lack of understanding or even knowledge of all of them, the Court
cannot find that the granting of this petition is in her best interest."
HOLDING: The Supreme Court reversed. The plurality opinion
concluded that the trial court's findings are conclusory and therefore
fail to state grounds essential to meaningful appellate review. The
Court remanded the case, and the plurality opinion directed the trial court
to detail sufficiently the basis for appropriate findings and immediately
to conduct such further proceedings, to include taking additional testimony
or admitting further evidence, that may be necessary in order to do so.
The plurality opinion directed that the trial court should submit its findings
to the Supreme Court by 5:00 p.m. on Thursday, November 13, 2003.)
*Download or view
PDF version of opinion*
Opinions Released October 31, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON FRIDAY, OCTOBER 31, 2003
-
Jefferson County
v. Acker,
No. 1010843 (Ala.
Oct. 31, 2003)
(occupation privilege
tax in Jefferson County; federal district judges; Certified Question from
the United States District Court for the Northern District of Alabama;
Jefferson County, Alabama, sued the defendants William M. Acker, Jr., and
U.W. Clemon, United States district court judges, to collect from them
an occupational tax consisting of one-half percent of their respective
salaries, levied by the plaintiff county. The U.S. District Court
where the case is pending certified the following question to the Supreme
Court of Alabama: "Is exemption from payment of Jefferson County's
occupation privilege tax imposed pursuant to its Ordinance No. 1120 of
1987 a privilege or benefit of membership in the Alabama Bar Association
to which defendants are entitled by virtue of their payment of 50% of the
dues of active members of that association?" HOLDING:
The Supreme Court answered the question in the negative and held that the
defendant federal district judges are not exempt from the tax. The
Court noted that the defendant judges claim only that they are exempted
by section 2 of the defendants' bar association statute, now §34-3-17,
providing that, "[u]pon payment of said sum as prescribed in the preceding
sentence, such persons shall be entitled to all the privileges and benefits
common to other members of such Association," and noted that the
defendant judges claim only that §34-3-17 entitles them to share in
the practicing, state-license-buying attorneys' exemption from the county
tax pursuant to the above-quoted exceptions in the county tax enabling
act and the plaintiff's county tax ordinance, because that exemption is
a "privilege" or "benefit" "common to" those practicing, state-license-buying
attorney members. The Court noted that the defendants' bar association
statute does not mention any county tax or any exemption from any tax.
The Court concluded that the county tax enabling act and the plaintiff's
county tax ordinance, by the express terms of these measures, spare practicing
attorneys from the county tax not because of their membership in the bar
association but because of the mandate of §40-12-49 that the practicing
attorneys "pay an annual license tax to the state, but none to the county."
The Court held that the Legislature did not likely intend for the ambiguous
language in the plaintiff's bar association statute to provide an exemption
from the then nonexistent county tax because §34-3-17 was originally
adopted in 1945, more than two decades before the Legislature even authorized
the plaintiff county to impose the county tax and over four decades before
the plaintiff county imposed the tax by adopting the plaintiff's county
tax ordinance.)
*Download or view
PDF version of opinion*
-
Newson v. Protective
Indus. Ins. Co.,
No. 1011342 (Ala.
Oct. 31, 2003)
(claims for misrepresentation,
suppression, conversion, and conspiracy; claim for negligent or wanton
employment practices; Rule 12(b)(6), Ala. R. Civ. P.; standing; Betty Newson
and Willie Newson, a married couple, took out a number of Protective Industrial
Insurance Company of Alabama ("PIICO") life insurance policies on their
lives. In addition, Mrs. Newson took out two policies insuring the life
of the Newsons' son, James D. Newson ("James"), and one policy insuring
the life of the Newsons' grandson, Keyon Orr ("Keyon"). Mrs. Newson,
using joint funds belonging to her and Mr. Newson, paid all of the premiums
on the policies insuring the lives of James and Keyon. The policies insuring
the lives of James and Keyon do not identify an owner of the policies by
name or generic description. The two policies insuring James's life
provide that "upon written request to the Company [subject to conditions
not pertinent to this case] the Company will pay a cash surrender value."
To whom, these two policies do not say. The policy insuring Keyon's life
provides that "the Insured [Keyon], while living, may [subject to conditions
not pertinent to this case] obtain the cash surrender value of this Policy."
PIICO agents Felicia Scott Nichols ("Nichols") and Rosetta Randolph ("Randolph")
usually came to the Newsons' home to collect the premiums on policies the
Newsons had taken out. To induce the Newsons to pay these premiums, Nichols
and Randolph falsely represented that the premium payments would be applied
to these policies. However, Nichols, Randolph, and Shareef Id Deen ("Deen"),
a PIICO manager, did not apply all of the Newsons' premium payments to
the payment of premiums on these policies. About May or June 1999,
Nichols and Randolph falsely told the Newsons that they needed to
surrender five policies, consisting of a $1,000 policy insuring Mr. Newson's
life, a $1,000 policy insuring Mrs. Newson's life, the two policies insuring
James's life, and the policy insuring Keyon's life, to use the cash surrender
values to "catch up" the payments on some of their other policies. Nichols
and Randolph told the Newsons also that they should use some of the cash-surrender-value
proceeds they received from surrendering these policies to buy two new
PIICO life insurance policies, one insuring the life of Mr. Newson for
$2,000 and the other insuring the life of Mrs. Newson for $2,000.
During this conversation, Nichols and Randolph did not disclose to the
Newsons: (1) that they could maintain all of their policies without surrendering
any of them because the cash values that had accumulated in their
policies would fund the payment of premiums under the automatic extended
insurance provisions in the policies; (2) that the first $1,000 of coverage
provided by each of the proposed $2,000 replacement policies on their respective
lives would cost more than the corresponding $1,000 policy they would be
surrendering; or (3) that their keeping the policy insuring the life
of Keyon and paying the premiums would pay the policy up within six years.
The Newsons surrendered the five policies to Nichols and Randolph. In exchange,
PIICO issued four checks, each payable to the insured named in the surrendered
policy or policies on that insured's life. At the direction of Nichols
and Randolph, Mrs. Newson signed the respective names of the respective
payees on the backs of the four checks, including the checks payable to
James and Keyon. The back of each check bore the printed statement:
"Endorsed and accepted as payment in full and releasing the Company of
any and all liabilities under claim on policy number [appropriate policy
number inserted]." After Mrs. Newson endorsed the checks, Nichols
and Randolph took the checks, and the defendants used the proceeds of the
checks to "catch up" premiums on other existing policies that supposedly
were unpaid, to pay the cost of issuing the new $2,000 policies on the
lives of Mr. and Mrs. Newson, and to pay other premiums that the Newsons
had not authorized. On the basis of these facts, the Newsons claimed
against PIICO, Nichols, Randolph, and Deen for misrepresentation, suppression,
conversion, conspiracy, and "felonious injury." Against PIICO only, the
Newsons claimed additionally for negligent or wanton hiring, training,
and supervision of Nichols, Randolph, and Deen. The four defendants
jointly moved the trial court to dismiss the Newsons' claims or, in the
alternative, to enter summary judgments for the defendants. The defendants
attached to the motion copies of the five policies the Newsons had surrendered,
the four checks PIICO issued in exchange for the policies, and an affidavit
by the custodian of these documents authenticating them. The defendants
contended that the trial court should dismiss the Newsons' claims
because: (1) the Newsons released the defendants from all claims when Mrs.
Newson endorsed the checks, (2) the Newsons did not suffer any damage,
(3) the Newsons did not have standing to sue for torts relating to the
policies insuring the lives of James or Keyon, and (4) the counts for "felonious
injury" did not state cognizable claims. The defendants agreed that
the motion to dismiss or, in the alternative, motion for summary judgment
should be treated as a motion to dismiss only. The trial court, holding
that "the releases were final releases," dismissed all of the Newsons'
claims. HOLDING: The Supreme Court reversed as to most
of the claims. The Court held that the Newsons' "releasing the Company
of any and all liabilities under claim on policy number [appropriate policy
number inserted]" did not release PIICO from the tort claims and did not
release Nichols, Randolph, or Deen from any claims. The Court also
held that the dismissal of the Newsons' claims could not be affirmed on
the ground of accord and satisfaction. The Court held that
the Newsons sufficiently alleged that they had suffered damage by alleging
that the defendants' torts caused the Newsons to suffer the loss of the
cash surrender values of the policies they surrendered. The Court
further held that the Newsons also sufficiently alleged that they had suffered
damage by alleging that the defendants' torts caused them to replace their
$1,000 policies with new $2,000 policies and thereby unnecessarily to incur
a higher premium cost for the first $1,000 of coverage under each replacement
policy. The Court held that the Newsons' allegations of misapplied
premium payments also sufficiently allege damage. The Court further
held that it could not affirm the dismissal of the Newsons' conversion
claims on the ground that the policies, cash-surrender-value checks, and
premium payments no longer belonged to the Newsons once they relinquished
possession of them. The Court also held that because the determination
of whether conversion will lie for the recovery of money paid as insurance
premiums depends on the evidence of the form, source, and mode of the payments,
it cannot hold that the Newsons "can prove no set of facts entitling [them]
to relief" under their claim for conversion of the money paid by them as
insurance premiums. The Court held that it cannot, on the ground
that the Newsons lacked standing to sue, affirm the dismissal of their
claims for misrepresentation, suppression, or conspiracy to defraud relating
to the policies insuring the lives of James and Keyon. The Court
held that because Mrs. Newson, using joint funds belonging to her and Mr.
Newson, paid all of the premiums on the policies insuring the lives of
James and Keyon, it cannot, on the ground that the Newsons lacked standing,
affirm the dismissal of their claims for conversion of the premiums paid
on the policies insuring the lives of James and Keyon. The Court
held that because the policies insuring James's life do not identify the
owner or the person entitled to the cash surrender values, the Newsons
could prove that they were entitled to these cash surrender values.
However, the Court held that because the policy insuring Keyon's life provides
that Keyon was entitled to the cash surrender value of that policy, the
Newsons do not have standing to sue for the conversion of the cash surrender
value of that policy.)
*Download or view
PDF version of opinion*
-
Mobile Infirmary
Med. Ctr. v. Hodgen,
No. 1011932 (Ala.
Oct. 31, 2003)
(invited error; punitive
damages; collateral-source rule; medical malpractice; In February 2000,
58-year-old James Hodgen was a patient in the intensive care unit of the
Mobile Infirmary Medical Center recovering from cardiac bypass surgery.
Hodgen's recovery progressed normally until he began to develop cardiac
arrhythmia, or abnormal heart rhythms, two days after the surgery.
The Mobile Infirmary employee overseeing Hodgen's care, Dawn Byrd, a recent
nursing school graduate, informed a supervising nurse, Tammy Espiritu,
that Hodgen was experiencing arrhythmia. Espiritu instructed Byrd
to telephone Hodgen's cardiologist, Dr. Chris Brown. When Byrd telephoned
Dr. Brown and advised him of Hodgen's condition, Dr. Brown prescribed .25
milligrams of digoxin. Byrd mistakenly informed Espiritu that Dr.
Brown had prescribed 1.25 milligrams of digoxin, and Espiritu telephoned
the order to the pharmacy. Espiritu, believing that Hodgen's condition
was worsening, told Byrd not to wait for the pharmacy to deliver the medication.
Instead, Espiritu instructed Byrd to obtain the digoxin from the stock
of medicine maintained in the intensive care unit and to administer it
to Hodgen. Without supervision from Espiritu, Byrd obtained three
vials, or ampules, of digoxin and emptied at least two and a half of the
vials directly into Hodgen's intravenous tube. Shortly after Byrd
had administered the digoxin to Hodgen, the pharmacy called Espiritu, questioning
the amount of digoxin she had ordered. It was then that Byrd and
Espiritu realized that Byrd had administered to Hodgen five times the amount
of digoxin Dr. Brown had actually prescribed. When Hodgen began to
experience complications the next evening resulting from digoxin toxicity,
he was administered Digibind, an antidote for digoxin toxicity. After
the Digibind was administered, Hodgen's heart stopped beating and one of
the nurses began to "mechanically pace his heart." Hodgen's blood
pressure then dropped to a very low level and the oxygen-saturation level
in his blood became extremely low. Hodgen stopped breathing, and
the hospital staff began CPR and other forms of intervention to revive
Hodgen. Hodgen was revived, but he suffered damage to various organs
as a result of severe oxygen deprivation. Hodgen later underwent
surgery to remove a portion of his intestines and to amputate his right
leg. Hodgen is now unable to walk, must use a colostomy bag, and
claims that his mental capacity is diminished. Hodgen sued Mobile
Infirmary in the Mobile Circuit Court under the Alabama Medical Liability
Act, Ala. Code §6-5-480. Hodgen alleged that Mobile Infirmary
had been negligent and/or wanton in administering the digoxin and in supervising
its employees. James's wife, Judy Hodgen, also sued Mobile Infirmary,
stating a derivative claim alleging loss of consortium. The Hodgens
sought both compensatory and punitive damages. The case went to trial
in April 2002. The evidence at trial indicated that Byrd, although
assigned to care for various patients in the intensive care unit at Mobile
Infirmary, was not a licensed nurse. She was a recent graduate of
nursing school and, when she administered the digoxin overdose to Hodgen,
she had taken but had not yet received the results from her nursing board
examination. The supervising nurse that evening, Espiritu, had passed
her nursing board examination only seven months before the overdose was
administered and had never worked with Byrd before that occasion.
Additionally, the charge nurse for that evening had assigned Byrd and Espiritu
separate patients, instead of having Byrd work under Espiritu's direct
supervision. Espiritu testified that she understood that her responsibility
in supervising Byrd was merely to answer any questions Byrd might have
had. Dr. Ray Lash, the Hodgens' medical expert, testified that Hodgen's
symptoms after the digoxin overdose were consistent with digoxin toxicity.
Dr. Lash further testified that, generally, digoxin that is to be given
intravenously is delivered to hospitals in prepackaged vials, or ampules.
According to Dr. Lash, a normal dosage of digoxin is about one-half of
a vial, but the maximum dosage that should be administered to an average
person is one vial. Dr. Lash testified that a medical professional
in an intensive care unit should have known that medications are generally
packaged so that one container is the maximum dose for one person.
He further stated that a qualified nurse should have known something was
wrong when, to administer the prescribed dose of digoxin to a patient,
she had to use three vials of the medicine. Dr. Lash expressed his
opinion that Byrd was inadequately trained, that she was put in a position
where she was "in over her head," and that Mobile Infirmary failed to put
safeguards into place to prevent Byrd's inexperience from hurting patients.
After the close of all of the evidence, the trial court charged the jury
on negligence and wantonness and on compensatory damages and punitive damages.
The jury's verdict form stated that it found in favor of the Plaintiff,
James Hodgen, and awarded zero past damages, zero future damages, $2,250,000
in punitive damages, and $2,250,000 total damages. The jury awarded
Judy Hodgen zero damages. Immediately after the jury read its verdict
in this case, the trial court dismissed the jurors into the jury room to
await a final discharge from their duties. The trial court then held
a conference with the attorneys during which the trial court stated that
it thought the award was strange but that it thought they could do it.
Counsel for Mobile Infirmary agreed. The trial court entered a judgment
in favor of James Hodgen awarding him $2,250,000 in punitive damages and
a judgment in favor of Judy Hodgen awarding her $0. After the jury
was discharged, Mobile Infirmary filed a motion for a judgment as a matter
of law ("JML"), arguing, despite its earlier representation to the trial
court that the jury could make such an award, that the trial court's judgment
on the jury verdict was improper because the jury failed to award compensatory
or nominal damages. At the hearing on the motion, counsel and co-counsel
for Mobile Infirmary admitted that they had previously represented to the
trial court that they believed the verdict was proper, but that they were
taking a different position on the posttrial motion. The trial court
denied Mobile Infirmary's posttrial motions and refused to remit the punitive-damages
award. In support of its refusal to remit the award, the trial court
purported to find that, at trial, James Hodgen produced evidence that he
had incurred $1,600,000 in compensatory damages. The trial court
further stated that if Mobile Infirmary had indicated there was anything
wrong with the jury's verdict, had indicated anything less than its total
acceptance of the jury's verdict, or had even voiced suspicions or doubts
about the form or substance of the jury's verdict, then it would have proceeded
to bring back the jury and recharge it. HOLDING:
The Supreme Court affirmed conditionally. The Court held that the
Mobile Infirmary invited error because it cannot, on the one hand, represent
to the trial court that the jury verdict was proper, thus inducing the
trial court to enter a judgment on that verdict, and then, on the other
hand, argue in posttrial motions that the jury verdict was improper and
that Mobile Infirmary is entitled to have a judgment rendered in its favor.
The Court declined to revive the $400,000 cap on the noneconomic damages
that could be awarded in a medical-malpractice case imposed by Ala. Code
§6-5-544(b) which was declared unconstitutional in Moore v. Mobile
Infirmary Association, 592 So.2d 156 (Ala. 1991). In so holding,
the Court noted that §6-11-21 was rewritten in 1999 and has been recognized
as a complete replacement of the old statutory restrictions on punitive
damages. The Court held that in addressing compensatory damages that
could have been awarded, in the context of the renewed vitality of Ala.
Code §6-5-545, which abrogates the collateral-source rule, a special
interrogatory should be propounded to the jury that gives the jury the
opportunity to state the amount of compensatory damages it would have awarded,
but did not so award because of the evidence of the availability of compensation
to the plaintiff from a collateral source. The Court recognized the
inequity of allowing Mobile Infirmary to capitalize on the fact that the
jury entered a verdict awarding no compensatory damages. Nonetheless,
the Court recognized the problem inherent in accepting the trial
court's conclusion as to causation as a means of determining compensatory
damages that could have been awarded. The Court was therefore unwilling
to permit the trial court's finding as to $1,600,000 in past and future
medical expenses to function as the amount of compensatory damages that
could have been awarded for purposes of the rule established in Life
Insurance Co. of Georgia v. Smith, 719 So.2d 797, 814-15 (Ala. 1998).
Under the unique circumstances of this case, the Court affirmed the judgment
of the trial court, on the condition that Hodgen file with this Court,
within 14 days of the date of the opinion, a remittitur of the punitive-damages
award to $1,500,000, the amount appropriate under Ala. Code §6-11-21(d).)
*Download or view
PDF version of opinion*
-
Image Marketing,
Inc. v. Florence Television, L.L.C.,
No. 1020395 (Ala.
Oct. 31, 2003)
(appellate procedure;
timeliness of appeal; amendment of complaint; Image Marketing, Inc.
(hereinafter "IM"), sued Florence Television, L.L.C., and Valley Television,
L.L.C. The controversy stems from a television show IM produced,
entitled "Cooper & Company" (hereinafter "the show"), which, based
on several contractual agreements, Florence and Valley agreed to air on
a television station they operated in Lauderdale County. In its original
complaint, IM sought an injunction, a declaratory judgment, and remedies
established by § 43(a) of the Lanham Act, 15 U.S.C. § 1125(a),
for service-mark/trade-dress infringement. IM amended the complaint
to add additional defendants, including Gary Kneller, co-owner and general
manager of the station. IM also amended the complaint to assert claims
of breach of contract, intentional interference with business relations,
fraud, negligence, wantonness, conspiracy, and negligent or wanton supervision.
Florence, Valley, and the other defendants separately moved for a summary
judgment as to all the claims. IM filed a response and contemporaneously
filed a second amended complaint, adding a claim for specific performance.
The trial court entered a partial summary judgment for Florence, Valley,
and the other defendants on July 18, 2001, dismissing IM's claims of intentional
interference with business relations, fraud, negligence, wantonness, conspiracy,
and negligent or wanton supervision. The trial court did not rule on the
breach-of-contract and specific-performance claims. On August 15,
2001, the trial court issued an order supplementing the July 18, 2001,
summary-judgment order, which dismissed all of the individual defendants,
including Kneller, from the case. The trial court did not dismiss
Florence and Valley, leaving them as the only defendants in the case.
Florence and Valley filed a second motion for a summary judgment addressing
IM's remaining claims of breach of contract and specific performance.
As the litigation proceeded, the parties continued their business
relationship, although it was strained. Kneller, as general manager
of the station, implemented a policy requiring IM to provide a transcript
of the show, detailing what would take place on the show, 24 hours before
the airing of each show. Considering this requirement to be a breach of
contract, IM filed a third amended complaint on October 21, 2002, without
seeking leave of court. Florence and Valley filed a motion to strike
IM's third amended complaint on the basis that it was untimely because
the case "was first set for trial on November 1, 2001," and IM "did not
and has not sought leave of court to amend the complaint." On October
23, 2002, the trial court granted Florence and Valley's pending motion
for a summary judgment, thus disposing of IM's remaining claims.
On October 29, 2002, Florence and Valley filed a motion to strike IM's
third amended complaint on the basis that it was untimely because the case
"was first set for trial on November 1, 2001," and IM "did not and has
not sought leave of court to amend the complaint." On October 31,
the trial court granted that motion. On December 6, 2002, IM filed
its notice of appeal. On March 17, 2003, Florence and Valley filed with
the Supreme Court a motion to dismiss the appeal, as well as a supporting
brief, alleging that the trial court's October 23, 2002, ruling was the
final judgment from which the time for appeal began to run. On March
24, 2003, IM filed an opposition to the motion to dismiss and a supporting
brief. HOLDING: The Supreme Court dismissed the appeal
as untimely filed. The Court held that IM's third amended complaint
was without legal effect and was therefore ineffectual to present an additional
claim to the trial court when it entered the October 23, 2002, summary
judgment. The Court concluded that the October 23, 2002, summary
judgment adjudicated every claim before the trial court and that IM's time
for filing an appeal began to run when that judgment was entered.
The Court held that because the trial court's October 23, 2002, summary-judgment
order completely adjudicated all issues remaining after the entry of its
earlier partial summary judgment and was therefore final, the time for
appeal began to run from that date, and the appeal filed on December 6,
2002, was two days late.)
*Download or view
PDF version of opinion*
-
Coca-Cola Bottling
Co. Consolidated v. Hollander,
No. 1020520 (Ala.
Oct. 31, 2003)
(retaliatory discharge;
workers' compensation; Louis Frank Hollander was employed by Coca-Cola
Bottling Co. Consolidated ("CCBCC") at its facility in Florence, Alabama,
to deliver soft-drink vending machines and coolers. He was injured on Friday,
August 27, 1999, when a fully loaded soft-drink vending machine, weighing
between 700 and 1,000 pounds, fell on him while he and another worker were
moving it into an elementary school in Collinwood, Tennessee.
On the day of the incident, Hollander reported this incident to his supervisor,
William Talley. According to CCBCC, Talley asked Hollander if he
had been injured when the machine fell on him and if he needed medical
care, and Hollander said that he had suffered a cut on his leg but that
he did not require medical treatment. Hollander says that Talley did not
ask him if he needed to see a doctor and that he waited for guidance from
Talley instead of asking to see a doctor. CCBCC's employee handbook requires
that all injuries, "no matter how minor," be reported immediately to the
injured employee's supervisor, "who will take whatever actions necessary
to insure required medical treatment is authorized and attained and that
the First Report of Injury is completed. The Employee will be referred
to a doctor of CCBCC's choice." It is undisputed that Hollander complied
with that policy. Talley reported the accident to CCBCC's third-party
accident claims administrator. The administrator completed a "first report
of injury" form. In accordance with CCBCC's standard procedure, Talley
also completed a supervisor's accident report. Hollander and his coworker
continued to deliver and retrieve vending machines on the day Hollander
was injured. Hollander claims that he could not drive the delivery truck
after the machine fell on him on August 27 because of the condition of
his legs and that his coworker, who did not have a commercial driver's
license, drove the truck the rest of the day. However, Hollander's coworker
testified that he did not drive the truck. After arriving at CCBCC's facility
in Tennessee at approximately 5:00 p.m., Hollander and his coworker began
using a forklift to load machines onto the truck for delivery the next
day. As Hollander was driving the forklift to load a machine, the machine
fell off the forklift. On Monday August 30, Hollander visited Dr.
Glen Sockwell complaining of stress and shortness of breath. On August
31, Hollander left Talley's office, stating, "I can't do this." On that
same day Hollander visited Dr. Sockwell again. Dr. Sockwell's office notes
from August 30 and 31 mention nothing about an injury to Hollander's legs
or his August 27 injury. Also, on August 31 Dr. Sockwell gave Hollander
a work-release slip excusing him from work for the period August 31 through
September 12. On September 1, 1999, Hollander visited the North Alabama
Bone and Joint Clinic, a group of physicians approved by CCBCC to treat
work-related injuries of its employees. Hollander saw Dr. Lee Nichols,
one of the physicians at the clinic, and complained of pain in his right
knee and left ankle as a result of the August 27 incident. Dr. Nichols
did not consider it necessary to excuse Hollander from work because of
the injury to his legs. Hollander has not made any claim based on the injuries
he suffered as a result of the August 27 incident other than a claim for
the medical expenses incurred in his September 1 visit to Dr. Nichols.
On September 7, Joe Clayton, general manager of CCBCC's Florence facility,
learned for the first time that Hollander was seeking workers' compensation
benefits for a heart condition and stress, for which Dr. Sockwell treated
him on August 30 and 31. Clayton informed the claims administrator of Hollander's
claim and completed a first report of injury form related to Hollander's
heart condition and stress-related complaint. Robyn Masoner, a benefits
coordinator with CCBCC, forwarded Dr. Sockwell's work-release slip to Lou
Jane Miller, CCBCC's environmental safety manager at its offices
in Brentwood, Tennessee, who was responsible for deciding whether an employee's
claim was compensable. Miller told Masoner that CCBCC did not consider
Hollander's heart condition and stress claim to be based on a compensable
injury. On September 8, Hollander returned to Dr. Sockwell's office;
he denies that he returned to Dr. Nichols's office on that date. Dr. Nichols
reported in his notes that he saw Hollander on September 8, but he admits
that those notes are incorrect and that he actually had a telephone conversation
with Hollander on that date. Dr. Nichols testified that in that telephone
conversation Hollander asked him to "write a work release or an excuse
from work from the date of his [August 27] injury, because he said that
when he presented the work release Dr. Sockwell gave him, his employer
would not accept Dr. Sockwell's work release because he was not their company
doctor." Dr. Nichols admitted that his notes were in error in stating
that he saw Hollander on September 8; he testified, however, that he could
not have been mistaken as to Hollander's asking him to backdate a work-release
slip for him. As part of the regular claims procedure, Dr. Nichols's office
faxed the medical record notes of September 1, 1999, and September 8, 1999,
to Miller at CCBCC's offices in Brentwood, Tennessee. On September 13,
1999, Miller faxed the notes to Clayton at CCBCC's Florence facility, and
he determined that, in asking Dr. Nichols to backdate a work-release slip,
Hollander had been dishonest. Before the conversation with Dr. Nichols
related above, Hollander had made numerous telephone calls to Masoner and
Miller inquiring about his workers' compensation claim. According to Masoner's
testimony, at some point after learning the above, Hollander asked:
"What if I call my Worker's Comp doctor [Dr. Nichols] back, the original
doctor back that I went to for my Worker's Comp injury, and get them to
say that the reason I was off was due to the Worker's Comp [August 27]
injury?" Masoner's answer was that Hollander could not do that and
that such an action "would be dishonest, and it would be a falsification."
Hollander denies that he told Masoner what she claims he did. After the
telephone call with Hollander in which she says he inquired about talking
to Dr. Nichols, Masoner telephoned Miller and told her about the conversation.
It is at this point that Hollander allegedly telephoned Dr. Nichols to
tell him that his employer would not accept Dr. Sockwell's work-release
slip because Dr. Sockwell was not a doctor approved by CCBCC and to ask
Dr. Nichols to backdate a work-release slip so that Hollander could be
paid for his time off. Dr. Nichols informed him that he would not backdate
a work-release slip, and that, in any event, in his opinion Hollander could
perform his work without any restrictions. On September 13, 1999,
Hollander returned to work. On September 14, Talley and Clayton informed
Hollander that he was being terminated from his job for attempting to have
Dr. Nichols backdate a work-release slip. Clayton testified that
the sole reason Hollander's employment was terminated was for dishonesty,
based on Dr. Nichols's notes indicating that Hollander had attempted to
get Dr. Nichols to backdate a work-release slip. Hollander himself testified
that because of the nature of his job –– carrying large amounts of cash
for use in the vending machines –– dishonesty was a legitimate reason for
CCBCC to terminate his employment. Hollander saw two counselors after his
employment was terminated to help him with his anguish about being terminated
and with other problems. Hollander testified that he had lost income of
$30,000 as a result of the termination and that he had used his own funds
to pay to go to school to become a long-distance truck driver.
Hollander sued CCBCC, alleging retaliatory discharge in violation of Ala.
Code §25-5-11.1. CCBCC filed motions for a judgment as a matter
of law ("JML") at the close of Hollander's evidence and again at the close
of all the evidence. The trial court denied the motions. The jury returned
a verdict in favor of Hollander, awarding compensatory damages of $150,000
and punitive damages of $250,000. After the trial court entered a judgment
on that verdict, CCBCC filed a postverdict motion for a JML and a motion
for a new trial or, in the alternative, a remittitur. The trial court denied
those motions, and CCBCC appeals, contending that the trial court erred
in denying the postjudgment motions. HOLDING: The Supreme
Court reversed. The Court held that evidence in the record shows
no causal connection between Hollander's filing of a workers' compensation
claim and the termination of his employment. The Court held that
Hollander presented no evidence indicating that CCBCC used dishonesty as
a pretext for terminating employees who had filed workers' compensation
claims, that CCBCC's termination of Hollander violated any company policy,
or that CCBCC ever acknowledged that its stated reason for terminating
Hollander's employment was pretextual. Therefore, the Court held
that CCBCC's stated reason for terminating Hollander's employment precludes
a finding that the fact that he filed a workers' compensation claim was
the "sole" cause of his termination.)
*Download or view
PDF version of opinion*
-
Ex parte Moore,
No. 1020599 (Ala.
Oct. 31, 2003)
(right to trial by
jury; eviction action; Andrea Moore, a tenant in Smiley Court, a
housing complex in Montgomery, was served with a notice of eviction on
November 13, 2002, and thereafter failed to deliver possession of the apartment
at 3704(B) Smiley Circle. On December 12, 2002, the Montgomery Housing
Authority ("MHA") filed an eviction action against Moore under the
Sanderson Act in the Montgomery County District Court. The purpose
of the Sanderson Act, Ala. Code §35-9-80 et seq., is to provide a
more speedy remedy to a landlord for recovering possession of his or her
land after expiration of a lease or when possession is wrongfully withheld
by the tenant. The Sanderson Act also vests Alabama district courts
with jurisdiction to hear cases brought under that act. The basis
of MHA's eviction action was that Moore had held possession of the premises
over and beyond the term of her lease. Moore responded by filing
an affidavit, contending that her lease had not been terminated and that
she had a right to continue as a tenant of the residence. On January
6, 2003, the district court entered an order evicting Moore. The
next day, Moore filed a notice of appeal to the Montgomery Circuit Court
in which she requested a trial by jury. Thereafter, MHA filed a motion
to strike Moore's jury demand, which Moore opposed. The circuit court
entered an order denying Moore's request for a trial by jury and set the
case for a nonjury trial. Moore sought a writ of mandamus ordering
the circuit court to vacate its order denying her request for a jury trial.
HOLDING: The Supreme Court granted the petition for writ of
mandamus. The Court held that Moore is entitled to a trial by jury
on her appeal to the circuit court challenging the district court's judgment
rendered in favor of MHA. The Court noted that an action brought
pursuant to the Sanderson Act is an action in the nature of unlawful detainer
and that, historically, the right to a trial by jury in unlawful-detainer
actions has been recognized by the courts of this State. The
Court concluded that a cause of action under the Sanderson Act serves the
same function as did an ejectment action at common law, which was previously
recognized as a triable issue.)
*Download or view
PDF version of opinion*
-
Steele v. Walser,
No. 1020652 (Ala.
Oct. 31, 2003)
(arbitration; construction
of a new house; interstate commerce; unconscionability; Maxine Walser sued
Robert L. Steele, president of S.S. Steele and Company, Inc. (hereinafter
"the company"), alleging fraud, mental anguish, and emotional distress
arising from the construction of a new house. Steele filed a "Motion
to Dismiss and Compel Arbitration," with supporting evidentiary submissions.
Walser filed a response in opposition. The trial court entered an
order denying Steele's motion. HOLDING: The Supreme
Court reversed. The Court concluded that Steele showed that the aggregate
effect of the transaction evidenced by the construction and sales contract
satisfied the Federal Arbitration Act's "involving commerce" test.
The Court noted that although Walser argues that the scope of the arbitration
agreement in the construction and sales contract is overly broad, she made
no showing that it assigned the threshold issues of arbitrability to the
arbitrator, that there was a lack of mutuality of remedies, that it set
a limit on the amount the arbitrator could award, or that any other terms
of the agreement were "grossly favorable" to the company. The Court
further noted that Walser presented no evidence showing that the company
had overweening bargaining power. Therefore, the Court rejected Walser's
unconscionability argument.
*Download or view
PDF version of opinion*
-
City of Huntsville
v. Rowe,
No. 1020868 (Ala.
Oct. 31, 2003) (Opinion withdrawn and substituted on application for rehearing)
(condemnation; easement;
valuation; The City of Huntsville ("the City") condemned a portion of property
owned by Roland H. Rowe, as trustee of the Dimitriu Family Trust, and Elvina
Geauque ("the owners") to secure an easement for constructing, maintaining,
repairing, altering, replacing, or removing an underground sanitary sewer
line, and erecting manholes on the surface. The easement is a 40-foot-wide
strip, comprising 3.624 acres of a 290.19-acre tract of unimproved land.
The probate court awarded the owners compensation for the property taken
for the easement. The owners appealed the probate court's award to
the Madison Circuit Court for a jury trial on the issue of damages pursuant
to Ala. Code §18-1A-283. The owners moved for a partial summary
judgment in the circuit court, asking the court to determine the proper
method of valuing, under Ala. Code §18-1A-170(b), the property taken
for the easement. Section 18-1A-170(b) provides: "If there
is a partial taking, the valuation rule is the difference between the fair
market value of the entire property before the taking and the fair market
value of the remainder after the taking." More specifically, the
owners sought a judgment declaring "that the taking of an easement must
be valued as if the entire fee is taken," and an order prohibiting the
City from contending or testifying at trial "that the damage[s] to be awarded
the property owner for the land actually taken within the easement are
less than the value of the entire fee of said land within the easement
at the time of the taking." The trial court granted the owners' motion.
At trial, the owners moved in limine for an order prohibiting the City's
appraisal experts from testifying in a manner inconsistent with the partial
summary judgment. In other words, the owners sought to preclude testimony
that the value of the 3.624 acres constituting the easement after the taking
was greater than $0. The trial court granted the motion. Before
the jury returned its verdict, the City's appraisal expert made an offer
of proof that the value after the taking was 75% of the value of the land
before the taking. The jury awarded the owners $68,856. The
trial court entered a judgment on that verdict. The trial court denied
the City's motion for a new trial, and the City appealed, specifically
challenging the partial summary judgment and the order on the motion in
limine. HOLDING: The Supreme Court reversed. The
Court held that the trial court erred in ruling that the taking of property
for an easement for an underground pipeline must be compensated as if the
entire fee-simple title to the property on which the easement lies had
been taken. The Court directed the trial court on remand to permit
the jury to consider evidence that the market value of the 3.624 acres
after the taking was greater than $0.)
*Download or view
PDF version of opinion*
--(The substituted
opinion released March 26, 2004, in Rowe that reaches a different
outcome is available on the web site of Wallace, Jordan, Ratliff &
Brandt, L.L.C.)--
-
SouthTrust Corp. v. James,
No. 1021103 (Ala.
Oct. 31, 2003)
(arbitration; interstate
commerce; unconscionability; Hessie James sued the SouthTrust Corporation
and SouthTrust Bank of Russell County (hereinafter jointly referred to
as "SouthTrust") in the Russell Circuit Court. James sought compensatory
and punitive damages from SouthTrust on claims of conversion, negligence,
wantonness, willful misconduct, and fraud. On July 11, 2002, SouthTrust
filed its answer, denying liability. The controversy centers around
a checking account opened by James on or about December 5, 2001.
To fund the account, James deposited a check, drawn on the First Bank of
Chicago, payable through FCC National Bank, located in Wilmington, Delaware,
in the amount of $14,342.60. One prerequisite for opening the account
was signing a deposit agreement. The deposit agreement James signed
states that it includes and incorporates SouthTrust's "Rules and Regulations
Governing Deposit Accounts," internal rules adopted by SouthTrust (hereinafter
"the rules"). The deposit agreement also states that James agreed
to be bound by the rules, including any amendments to the rules.
James admits that she was given a copy of the rules when she opened the
account, as the deposit agreement itself stated. Contained within
those rules was an arbitration provision. After opening her account,
James ordered checks; SouthTrust informed her that her checks would arrive
by mail in approximately one week. After one week had passed and
James's checks had not arrived, she contacted SouthTrust. SouthTrust
informed James that it had mailed the checks to the wrong address and the
checks had been returned to SouthTrust. SouthTrust further told James
that pursuant to SouthTrust's policy, the checks had been destroyed.
SouthTrust assured James that she soon would receive checks SouthTrust
had ordered to replace the destroyed checks. James received the new
checks; however, she was notified that forged checks and forged deposit
slips were being used to conduct transactions on her account. James's
account was assessed fees associated with the forgeries, which in the aggregate,
totaled 13 separate incidents. Of those 13 incidents, at least 5
occurred in other states. As a result, James closed the account and
opened at SouthTrust a new account. However, James asserts that the
fraudulent activity on her bank account negatively impacted her credit,
caused collection agencies to attempt collection of unpaid debts created
by the forgeries, and may subject her to criminal prosecutions. On
August 26, 2002, SouthTrust filed a motion to dismiss or, in the alternative,
to stay the proceedings and to compel arbitration. On November 26,
2002, one day after a hearing on the issue, the trial court, without making
any findings of fact or stating any conclusions of law, denied SouthTrust's
motion. HOLDING: The Supreme Court reversed. The
Court concluded that the banking transaction in this case had a sufficient
nexus with interstate commerce. The Court also held that enforcement
of the arbitration provision is not unconscionable.)
*Download or view
PDF version of opinion*
-
ECS, Inc. v. Goff
Group, Inc.,
No. 1021293 (Ala.
Oct. 31, 2003)
(arbitration; nonsignatory;
This dispute arose out of the termination of a "Program Manager's Agreement"
("the agreement") executed in the spring of 2001 by Goff Group, Inc. ("Goff"),
Greenwich Insurance Company ("Greenwich"), and XL Specialty Insurance Company
("XL"). As "manager" under the agreement, Goff had authority to bind
"insurance policies for insureds introduced to it by independent agents"
in Alabama and several other southeastern states. Policies were underwritten
by ECS Underwriting, Inc., and issued by Greenwich and XL. The agreement
contained an arbitration provision providing for arbitration of "any dispute
arising out of this Agreement." Fowler sent Goff a letter dated June
28, 2002, purporting to terminate the agreement. On August 9, 2002, Goff
sued ECS on theories of (1) fraud, (2) tortious interference with a contractual/business
relationship, (3) the tort of outrage, (4) conspiracy, (5) unfair competition,
(6) violation of trade secrets, (7) conversion, and (8) tortious training
and supervision. In addition to compensatory and punitive damages,
Goff sought equitable relief, including an order enjoining ECS from "soliciting,
brokering, or marketing services or competing with [Goff's] rights under
the Program Manager's Agreement," and from "interfering with the Program
Manager's Agreement." In a separate action in the Montgomery Circuit Court,
Goff also sued Greenwich and XL, alleging breach of contract. That
action, originally styled Goff Group, Inc. v. Greenwich Insurance Company;
XL Specialty Insurance Company, CV-2002-2199, was removed to the United
States District Court for the Middle District of Alabama, which ultimately
ordered the parties to proceed to arbitration. ECS moved to compel
arbitration of this dispute. The trial court denied the motion, and
ECS appealed.
HOLDING: The Supreme Court reversed. The
Court held that ECS, which is not a signatory to the agreement, may, nevertheless,
enforce the agreement's arbitration provision as to Goff's claims against
it.)
*Download or view
PDF version of opinion*
Opinions Released October 24, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON FRIDAY, OCTOBER 24, 2003
-
Southern Pine Elec.
Coop. v. Burch,
No. 1020066 (Ala.
Oct. 24, 2003) (on return from remand)
(excessive punitive
damages; mental distress damages; public utility; The Supreme Court previously
remanded this case for the trial court to enter an order in compliance
with Hammond v. City of Gadsden, 493 So.2d 1374 (Ala. 1986), stating
its reasons for denying the motion of the appellant, Southern Pine Electric
Cooperative ("Southern Pine"), for a remittitur of a compensatory-damages
award of $20,000 and a punitive-damages award of $75,000 in favor of Christopher
Burch, without providing a statement of its reasons for the denial.
Following a hearing on remand, the trial court, in a written order, again
denied Southern Pine's motion. Southern Pine is a "[c]ooperative,
nonprofit membership corporation[]," as defined by Ala. Code §37-6-2,
"organized under [Ala. Code §§37-6-1 to -49,] for the purpose
of supplying electric energy and promoting and extending the use thereof."
This action arose out of an attempt by Southern Pine to collect payment
for electrical service it provided to Tracy Burch, who, at some time, was
married to Brian Burch, the cousin of the plaintiff, Christopher Burch.
That service was provided to a mobile home located on County Road 27 in
Castleberry. Southern Pine terminated electrical service at the site
in April or May 2001, after it was unable to collect $677.31 on Tracy Burch's
past-due account. On May 7, 2001, Christopher Burch submitted an
"Application for Membership and Electrical Service," seeking to reestablish
electrical service at the mobile home. Southern Pine approved the
application and dispatched district supervisor James Brown and service
technician Chet Dolihite to the site to reestablish electrical service.
Brown and Dolihite completed their assignment and were leaving the
premises, when, they say, they met an automobile, with a male driver and
a blonde female passenger, driving toward the mobile home. According
to Brown and Dolihite, the vehicle was a white Mercury automobile that
had customarily been parked at the mobile home while the account for electrical
service to the mobile home was in Tracy Burch's name. Subsequently,
Brown reviewed the account file of Christopher Burch, which contained a
copy of Christopher's driver's license. From the photograph on the
copy, Brown concluded that Christopher Burch was the driver of the white
Mercury. He further concluded that he had seen Christopher at the
mobile home on an earlier occasion, while the account was in Tracy's name,
and that, on that occasion, Christopher had identified himself to Brown
as Tracy Burch. Southern Pine concluded that Christopher's membership
application was merely an attempt to circumvent the past-due account, for
which service to the mobile home had been discontinued. It concluded,
in other words, that "Southern Pine was dealing with the not-uncommon problem
of members attempting to avoid indebtedness for electrical service by simply
changing the name on the account from one resident of the household to
another." Therefore, the first electrical bill mailed to Christopher
was for $737.39. Of that amount, $60.08 was designated as "current
bill," while $677.31, the amount due on Tracy Burch's delinquent account,
was designated as "previous balance." On June 15, 2001, Christopher
paid the "current bill" amount of $60.08. On June 27, 2001, Southern
Pine discontinued electrical service to Christopher for failure to pay
the alleged delinquency. Christopher sued Southern Pine, alleging
(1) breach of contract, (2) "wrongful termination of electrical power,"
and (3) "wanton or willful termination of electrical service." Electricity
was restored to the mobile home on July 31, 2001, pursuant to a court order;
Southern Pine offered no opposition. Subsequently, Southern Pine
counterclaimed against Christopher for the delinquent amount on Tracy's
account. After the complaint was filed, Southern Pine's personnel
began surveilling Christopher's premises. While doing so, James Brown
took a number of photographs of a blonde woman on the premises. A
jury trial began on June 24, 2002. At the close of all the evidence,
the trial court granted Burch's motion for a JML on the counterclaim.
The case was submitted to the jury on claims of breach of contract and
wantonness. The jury awarded Burch $20,000 in compensatory damages
and $75,000 in punitive damages. Southern Pine filed a posttrial
motion for JML, as well as a motion for a remittitur or, in the alternative,
a new trial. Those motions were denied. HOLDING:
The Supreme Court affirmed. The Court held that in actions alleging
the wrongful termination of utility services, damages for mental distress
are recoverable, and, when the circumstances justify it, so are punitive
damages. The Court held that the award of $19,900 in damages for
mental distress was supported by evidence that Burch was without electricity
for 34 days, that for two weeks of that time he slept at the home of relatives,
that he was inconvenienced, that he lost the use of his home, and that
he was embarrassed at having to move back in with his relatives when his
power was off. With regard to the punitive damages, the Court noted
that Tracy Burch was never identified for the record, that none of Southern
Pine's personnel ever asked the woman they allegedly saw on the premises
to identify herself, that Southern Pine did not ask Christopher whether
Tracy was still living on the premises before it assessed the past-due
balance on her account against his account or before it terminated his
electrical service for the failure to pay the past-due balance, and that
Southern Pine conducted regular surveillance of Burch's property and took
a number of photographs of an unidentified woman it saw there. The
Court therefore concluded that if the jury believed Burch, and disbelieved
Southern Pine -- as it apparently did -- it could have found the evidence
that Southern Pine terminated Burch's electrical service in "reckless or
conscious disregard of [his] rights," that Southern Pine's conduct was
based on mere unfounded suspicion, that Southern Pine never made a reasonable
effort to identify the woman it alleged was Tracy Burch, that Southern
Pine terminated Burch's service before it made any effort to determine
whether he had lived on the premises, that Southern Pine conducted an ongoing
campaign of surveillance of Burch's property -- which included peeping
into windows -- solely for improper purposes such as harassment or intimidation.
The Court held that Southern Pine has presented no reason for a reversal
of the judgment or a remittitur of the punitive damages awarded.
The Court agreed with the trial court that nothing in Ala. Code §37-6-30(b)
authorizes a rural electrical cooperative to sue one member of a household
for a debt incurred by another member of the household, so the trial court
did not err in entering a JML on the counterclaim.)
*Download or view
PDF version of opinion*
-
Ex parte Bruno's,
Inc.,
No. 1020404 (Ala.
Oct. 24, 2003)
(The Supreme Court
quashed writ of certiorari as improvidently granted, citing
Ex parte
Fort James Operating Co., No. 1020678 (Ala. June 27, 2003).)
*Download or view
PDF version of opinion*
-
Wilson v. Manning,
No. 1020432 (Ala.
Oct. 24, 2003)
(medical malpractice;
state-agent immunity; Sherrian Y. Wilson sued Rhoda Manning, a registered
nurse and an employee of the Mobile County Sheriff, asserting medical-malpractice
claims, alleging that Manning's negligence resulted in further amputation
of Wilson's leg. Manning filed a motion for a summary judgment, with
supporting evidentiary submissions, and Wilson filed a brief opposing the
motion. The trial court granted the Manning's motion for summary
judgment on grounds of state-agent immunity and on grounds of the failure
of Wilson to present substantial evidence which raises a genuine issue
of material fact regarding the breach of the standard of care. The evidence
showed that Wilson was arrested at her home on Wednesday, May 21, 1997,
and was taken to the Mobile County Metro Jail for failing to appear at
a hearing on a charge of negotiating a worthless instrument. Wilson
was brought to the jail at 6:30 p.m., and a corrections officer noted on
her "Jail Receiving Screening Form" that she had "bone cancer." At
the time of her incarceration, Wilson was receiving intravenous antibiotic
medication twice daily, through a Groshong shunt in her chest, to treat
what she termed a "bone disease" in her left leg, which had been amputated
below the knee. When she was admitted to the jail, she had not had
her second daily dosage of the antibiotic medication. Manning, an
employee of the Mobile County Sheriff's Department, was director of nursing
at the jail and was responsible for supervising two medical secretaries,
five registered nurses, and seven licensed practical nurses. She
testified in her deposition, filed in support of her motion for a summary
judgment, that the warden ran the jail and that his immediate supervisor
was the chief, who answered to the chief deputy, who answered to the sheriff.
On Thursday, May 22, Wilson signed a "consent for medical care" form and
filled out a "request for medical evaluation," on which she wrote "PAIN,
leg stump - need IV treatm[ent]. I have a shunt in my chest for bone
disease." That same day, in response to Wilson's request for a medical
evaluation, Manning visited Wilson and filled out a "medical encounter
record." Manning noted in the medical encounter record that Wilson
informed her that she was a patient of Infirmary Home Health Agency, Inc.,
and she provided her doctor's name, Dr. Steven G. Alsip, and a telephone
number for Infirmary Home Health. Manning telephoned Infirmary Home
Health and spoke to Jackie Woolfolk, the nurse who administered Wilson's
medications to her at Wilson's home. Manning recorded in the medical
encounter record, and subsequently testified on deposition, that Woolfolk
told her that Wilson was taking one gram of Cefotan, an antibiotic, intravenously
twice daily, at 6:00 a.m. and 6:00 p.m., and was having the dressing changed
on the Groshong shunt three times per week. She also stated in her
deposition: "The assessment from this lady, Jackie, was osteomyelitis,[]
amputee, car accident two years ago, long-standing, chronic." In
regard to her conversation with Infirmary Home Health, Manning also stated
that she telephoned them "to make them aware that [Wilson was] there so
they [could] continue the treatment or whatever they do ...." Woolfolk
testified somewhat differently, by deposition, concerning the content of
that telephone conversation. She stated that she telephoned the jail
"and left a message for the head nurse to call me back." Woolfolk
stated that when she talked to Manning, "I introduced myself, told her
that I was the one who had been primarily seeing Sherrian. I told
her what medication she was getting ... how often she was getting it, and
who her doctor was, and I also gave her the doctor's phone number."
Woolfolk testified that there was no discussion during that conversation
about Infirmary Home Health's delivering Wilson's medication and she stated
that Manning did not request that Infirmary Home Health send the medicine.
On Wednesday, May 28, Wilson, who was still incarcerated, filled out another
request for medical evaluation form; that form stated, "I have an infection
of the bone that is VERY active at present. I have a shunt in my
chest and I need antibiotics I.V. and pain medication." Manning testified
that Wilson was given a dose of antibiotics on May 28, at 6:00 p.m.
Wilson was released from the jail on May 29. According to Wilson's
brief opposing Manning's summary-judgment motion and her brief to this
Court, she was "taken immediately to Mobile Infirmary hospital where the
remainder of her leg was amputated." HOLDING: The Supreme
Court reversed. The Court held that the facts of this case raise
a genuine issue of material fact as to whether Manning provided Wilson
the "necessary medicines and medical attention" required by Ala. Code §14-6-19.
The Court stated that even if Manning was "exercising ... her judgment
in the administration of a department or agency of government," she had
no discretion to decline to provide necessary medicines and treatment in
violation of Ala. Code §14-6-19. Accordingly, the Court held
that the trial court erred in entering the summary judgment on the basis
that Manning was entitled to state-agent immunity. The Court also
concluded that there was substantial evidence from which a reasonable juror
could infer that Manning accepted Wilson as her patient with full knowledge
of Wilson's "necessary medicines" and with full appreciation of the importance
of continuity of care in antibiotic treatment, yet failed to provide that
care beginning with the dosage due at 6:00 p.m. on May 21, 1997, through
the 6:00 a.m. dosage due on May 28, resulting in a total of 14 missed doses.
Thus, the Court held that the trial court erred in entering the summary
judgment on the basis that there was not substantial evidence to prove
a breach of the standard of care.)
*Download or view
PDF version of opinion*
-
Jim Walter Homes,
Inc. v. Saxton,
No. 1020513 (Ala.
Oct. 24, 2003)
(arbitration; unconscionability;
existence of agreement to arbitrate; David Saxton entered into a contract
with Jim Walter Homes, Inc., and Jerry Tinch (collectively "JWH") for the
construction and financing of a new house; attached as Exhibit D to the
contract was a document entitled "Arbitration Agreement-Alabama."
The house was to be built by JWH on land Saxton owned in Hurtsboro, at
a total cost of $178,596, including financing charges. After the
house was constructed, Saxton sued JWH, alleging breach of warranty, fraud,
negligence, and breach of contract, and asserting a products-liability
claim. JWH moved to compel arbitration of the claims pursuant to
Exhibit D. Saxton filed a response in opposition to JWH's motion
to compel arbitration asserting six reasons the arbitration provision should
not be enforced. The trial court, without identifying the specific
grounds for its decision, denied JWH's motion to compel arbitration. HOLDING:
The Supreme Court reversed. The Court noted that Saxton does not
dispute that he signed an agreement to arbitrate any claims that might
arise from the contract he entered into with JWH and that JWH presented
evidence indicating that the transaction at issue affects interstate commerce.
The Court rejected Saxton's arguments concerning unconscionability based
on an alleged lack of a "meaningful choice," lack of mutuality of
remedy, and unequal bargaining power because Saxton failed to carry his
burden of proof. The Court held that Saxton cannot reasonably assert
that he did not knowingly, willingly, and voluntarily waive his right to
a jury trial when the arbitration agreement he signed states that "[t]he
parties agree and understand that they choose arbitration instead of litigation
to resolve disputes." The Court held that because Saxton has taken
the position that JWH breached its contract with him, he cannot now claim
that the contract is invalid because JWH failed to sign it.)
*Download or view
PDF version of opinion*
-
Middleton v. Lightfoot,
No. 1020666 (Ala.
Oct. 24, 2003)
(wrongful death; medical
malpractice; evidence; expert testimony; Lula Mae McDougle was admitted
to the University of South Alabama Knollwood Park Hospital for surgery
to relieve a condition diagnosed by Dr. Robert Lightfoot as "cholelithiasis"
(gallstones). Dr. Lightfoot performed a "cholecystectomy," that is,
surgical removal of the gallbladder. He first attempted to remove the
gallbladder "laparoscopically," that is, by inserting a series of "ports,"
or "trocars," into the abdominal wall, through which the gallbladder could
be removed. He inserted an "umbilical trocar," which was approximately
11 millimeters in diameter, through the lower abdomen; however, he abandoned
the laparoscopic procedure because his vision of and access to the gallbladder
were obscured by "adhesions," that is, scar tissue or "extra-fibrous tissue."
He then removed the trocars and made a larger incision in the lower abdomen,
through which he extracted the gallbladder. McDougle was released
from the hospital at approximately 9:15 a.m. the following morning, April
25. By 6:30 a.m. on April 26, McDougle was dead. An autopsy
revealed an 11-millimeter perforation of the "jejunum," that is, the "small
bowel," near the incision into which Dr. Lightfoot had inserted the "umbilical
trocar" during the abortive laparoscopic cholecystectomy. Katherine
Middleton, as administratrix and personal representative of McDougle's
estate, sued Lightfoot. The complaint alleged, among other things,
that Lightfoot "caused or negligently allowed the [gallbladder surgery]
to be performed in such a manner that [McDougle] suffered a perforated
[bowel], which led to acute peritonitis and infection that caused [her
death]." It also alleged that Lightfoot allowed McDougle "to go without
proper and necessary evaluation, work-up, diagnosis and treatment of her
perforation and resulting peritonitis and prematurely and improperly discharged
[her] in spite of signs and symptoms of her problems." Finally, the
complaint averred that Lightfoot "negligently caused or allowed the perforation
and resulting peritonitis to occur without proper and timely evaluation
of the patient in spite of conditions which should have caused further
concern and evaluation of potential complications." Subsequently,
Ernest Middleton was substituted for Katherine Middleton as the administrator
of McDougle's estate and thus the plaintiff. The jury trial of the
case focused primarily on two issues: (1) the cause of death, and (2) the
standard of care. As for the cause of death, the autopsy report failed
to attribute death to a specific cause. Middleton's theory of the
case was that Dr. Lightfoot inadvertently punctured the bowel with the
umbilical trocar during the laparoscopic procedure and failed to discover
and treat the injury. According to this theory, the contents of the
bowel escaped through the puncture, resulting in "acute peritonitis," infection,
and ultimately McDougle's death. Middleton presented expert testimony
indicating that Dr. Lightfoot had breached the standard of care in failing
to discover and repair the perforation. Lightfoot did not challenge
the autopsy finding that McDougle's bowel was perforated at the time of
her death, but challenged the theory that the perforation occurred during
the surgical procedure, as well as Middleton's theory as to the cause of
McDougle's death. According to Lightfoot, the perforation resulted,
not from the insertion of the trocar, but from a bowel "impaction."
According to that theory, death resulted, not from peritonitis or infection,
but from a "pulmonary embolus," having no connection with the perforated
bowel. The jury returned a verdict in favor of Lightfoot. Middleton
moved for a new trial, on the ground, among others, that the trial court
erred in allowing Lightfoot to cross-examine Middleton's expert witness
regarding medical-malpractice actions that have been brought against the
witness. The trial court did not rule on the new-trial motion, and
it was denied by operation of law. HOLDING: The Supreme
Court reversed. The Court held that the prior medical malpractice
action against the Middleton's expert witness was not relevant because
the fact that the expert has himself been a medical-malpractice defendant
has no tendency to prove bias in favor of plaintiffs. The Court further
noted that even if a malpractice defendant would, in some case, be entitled
to impugn the credibility of the plaintiff's expert witness through reference
to extraneous lawsuits, it could not be done in this case, because , contrary
to Lightfoot's contention, Middleton's expert's laparoscopic-cholecystectomy
case is not remotely similar to the allegedly negligent conduct in this
action.)
*Download or view
PDF version of opinion*
-
John Deere Constr.
Equip. Co. v. England,
No. 1020984 (Ala.
Oct. 24, 2003)
(agency; fraudulent
suppression; Earnest England and Johnny England are brothers; together
they operate a business known as England Logging. John Deere Construction
Equipment Company ("Deere") manufactures, among other things, heavy industrial
equipment. In the early 1990s, it developed and marketed a line of
skidders designated as the E-series. This line included the 548-E
model, the 648-E model, and the 748-E model skidder. Shortly after
these skidders were placed on the market, Deere learned of various problems
with the E-series skidders. Although the problems manifested themselves
in various ways, it appeared that the most recurrent problem was in the
hydraulic system. In 1993, Deere issued an update kit to its authorized
dealers in an attempt to deal with the problems that had been identified
in the E-series skidders. In 1995, Deere issued another update kit
designed to address the overheating of the E-series skidders. Deere
denominated this kit as a "fix-as-fail" update, rather than a "mandatory"
update. Warrior Tractor and Equipment Company is a heavy equipment
dealer with six retail locations in Alabama. As an authorized Deere
dealer, Warrior had entered into a dealership agreement with Deere; that
agreement outlined the relationship between Deere and Warrior. Warrior
is also an authorized dealer for numerous other manufacturers of heavy
equipment. In June 1995, the Englands decided to purchase a Deere
skidder for use in their logging business. Tommy Moore, a sales representative
with Warrior, came to the Englands' job site to show them a used 648-E
model Deere skidder Warrior had for sale. Warrior had received this
skidder as a trade-in, had performed some repairs on it, and then offered
it for sale. The Englands decided to purchase the used Deere skidder.
Warrior provided a 30-day power-train warranty. Earnest England testified
that he knew Warrior, not Deere, was providing this warranty, because any
warranty provided by Deere on the skidder would have expired by the time
the Englands purchased the skidder. He also testified that in negotiating
the purchase he met only with representatives of Warrior and negotiated
only with Warrior, and that during the negotiations and while the Englands
owned the skidder he never contacted Deere for any reason. Six months
after they purchased the skidder, the Englands began experiencing various
problems with the skidder. Finally, in October 1999, while the skidder
was at Warrior's service department for repairs, Warrior's service manager
asked the Englands if the 1995 update kit had been installed on the skidder.
Apparently, it had not. Warrior installed the 1995 update kit that
same day. According to Earnest England, the update kit solved the
overheating problem but the other problems continued. Over six years
after they purchased the skidder from Warrior, Earnest England, individually,
Johnny England, individually, and Earnest England and Johnny England d/b/a
England Logging sued Deere and Warrior in the Perry Circuit Court.
In their complaint, they alleged that Deere (1) fraudulently represented
to them that the skidder was free of defects and was suitable for its intended
use; (2) fraudulently suppressed material facts regarding the hydraulic
system of the skidder; (3) negligently or wantonly failed to complete warranty
work, to service, to maintain, or to repair the skidder; (4) breached implied
warranties; (5) breached express warranties; and (6) failed to exercise
reasonable and ordinary care in the operation of its business. Deere
and Warrior each moved for a summary judgment as to all claims asserted
by the Englands. The trial court granted the motions as to both defendants
except as to count II of the complaint, which alleged that Deere and Warrior
had fraudulently suppressed material information regarding the defects
in the hydraulic system of the skidder. The Englands' claim of fraudulent
suppression against Deere went to trial. The undisputed evidence
at trial indicated that the Englands had had no contact with Deere, that
the Englands had never attempted to contact Deere regarding problems with
the skidder, and that Deere had no knowledge that the Englands had purchased
a used 648-E model skidder. It was also undisputed that Deere had
repeatedly notified Warrior and its other authorized dealers of problems
with the hydraulic system of the 648-E model skidder and had provided the
dealers an update kit to address those problems. At trial, counsel
for the Englands stipulated that the Englands' fraudulent-suppression claim
against Deere was premised entirely upon their allegation that, in its
dealings with the Englands, Warrior was acting as Deere's agent.
At the close of the Englands' case and again at the close of Deere's case,
Deere moved for a judgment as matter of law. Deere argued that the
Englands had not established sufficient evidence of the existence
of an agency relationship between Warrior and Deere and that, therefore,
Deere could not be liable for any alleged suppression by Warrior.
Deere also argued that the Englands had failed to present any evidence
to support their claim for punitive damages. The trial court denied
Deere's motion and submitted the fraudulent-suppression claim to the jury.
On September 25, 2002, the jury returned a verdict against Deere, assessing
compensatory damages in the amount of $289,000 (consisting of lost profits,
repair costs, and damages for emotional distress) and punitive damages
in the amount of $1,500,000. On October 7, 2002, the trial court
reduced the punitive-damages award, pursuant to § 6-11-21, Ala. Code
1975, to $867,000, resulting in a total award of $1,156,000. The
trial court entered a judgment on the verdict as reduced. Deere filed
a motion for a remittitur, a motion for a new trial, and a postverdict
motion for a judgment as a matter of law. Those motions were denied
by operation of law. HOLDING: The Supreme Court reversed.
The Court held that, as a matter of law, the evidence is insufficient to
create a jury question on the issue of actual agency. The Court noted
that the dealer agreement neither gave Deere the right to control Warrior's
day-to-day activities nor gave Deere any authority to dictate how Warrior
fulfilled its requirements under the agreement. The Court also found
that there was no evidence that presented a jury question on the issue
of apparent agency or agency by estoppel.)
*Download or view
PDF version of opinion*
-
Smith Family Cos.
v. The Home Depot, U.S.A., Inc.,
No. 1021291 (Ala.
Oct. 24, 2003)
(tortious interference;
promissory fraud; breach of contract; The Supreme Court affirmed without
opinion. Justices Johnstone and Harwood wrote opinions concurring
in part and dissenting in part.)
*Download or view
PDF version of opinion*
-
Liberty Nat'l Life
Ins. Co. v. Ester,
No. 1021395 (Ala.
Oct. 24, 2003)
(arbitration; fraud
in the inducement; Willie Ester and Dorothy Ester sued Liberty National
Life Insurance Company ("Liberty National") and Chris Reese, who
they alleged told them that their mortgage-insurance policy had to be canceled
and converted to a whole life insurance policy. The Esters claimed
that this representation was false and that they suffered damage because
they "could not obtain similar insurance with similar limits for the same
or less premium being paid to [Liberty National]." Liberty National
and Reese filed a motion to compel arbitration, supported by an affidavit
of Anthony McWhorter, president of Liberty National. Liberty National
also asked the court to stay the action pending arbitration. The
trial court held a hearing on Liberty National and Reese's motion to compel
arbitration; after the hearing the trial court denied the motion, stating
in its order that "this Court looks 'beyond the maneuvering by [Liberty
National and Reese]' to force the [Esters] to arbitrate their justiciable
grievances and clearly sees Alabama plaintiffs seeking redress in an Alabama
Court against an Alabama agent and an Alabama company in which the subject
transaction should be regulated by the Insurance Department of Alabama....
[Liberty National and Resse's] motion to compel arbitration is denied."
Liberty National and Reese appealed. Willie Ester and Dorothy Ester,
the plaintiffs, recognize that the judgment of the trial court cannot
be affirmed on the ground that the transaction does not affect interstate
commerce; they argue, however, that even if the transaction evidenced by
the policy affects interstate commerce, a question remains as to whether
they were fraudulently induced to convert an existing policy, and that
that question is an issue that must be determined by the court, not an
arbitrator. They contend, further, that the trial court here determined
that issue adversely to the movants, the defendants, and that the judgment
of the trial court should therefore be affirmed. HOLDING:
The Supreme Court reversed. The Court held that the Esters did not
present substantial evidence to support a fraudulent-inducement claim.)
*Download or view
PDF version of opinion*
-
General Motors Corp.
v. Stokes Chevrolet, Inc.,
No. 1021446 (Ala.
Oct. 24, 2003)
(arbitration; judicial
estoppel; Stokes Chevrolet, Inc. ('the Stokes dealership'), operates a
dealership in Clanton that, in addition to the Chevrolet line of the Chevrolet
Motors Division of General Motors Corporation ('GM'), sold Chrysler, Plymouth,
Dodge, and Jeep vehicles (Stokes's non-GM lines are hereinafter referred
to as 'the Chrysler assets'). Rick Bush Motors ('Bush') was a GM
dealer that also operated in Clanton and that had the authority to sell
Buick, Oldsmobile, and Pontiac vehicles, and the GMC line of GM. The Stokes
dealership was interested in acquiring from Bush assets to be used in the
operation of an Oldsmobile, Pontiac, and Buick dealership. Bush's
dealership agreement with GM required GM's approval of the sale of its
assets to the Stokes dealership. The Stokes dealership obtained GM's
approval and purchased Bush's assets; however, a condition of the approval
was the Stokes dealership's agreement to relocate the Chrysler assets to
another site in Clanton. On April 8, 1999, GM and Stokes Chevrolet,
Inc. ("the Stokes dealership"), signed a "Relocation Agreement and Business
Plan" ("the relocation agreement"), which paved the way for the Stokes
dealership to obtain the authority to sell Oldsmobile vehicles. The
relocation agreement mandates that "all claims, disputes, and controversies
between the [parties] arising under or relating to [the] agreement" be
submitted to arbitration. On November 1, 2000, the Stokes dealership
and GM entered into a "Dealer Sales and Service Agreement" ("the Oldsmobile
dealer agreement"), which covered the Oldsmobile line. The Oldsmobile
dealer agreement states that the Stokes dealership and GM agreed to resolve
disputes in accordance with the terms of the dispute resolution process
set out in the agreement. Under this dispute resolution process,
disputes are to be resolved through mediation, with certain exceptions,
and if the dispute is not resolved through mediation, both parties may
then voluntarily agree to arbitrate. Just over a month later, on
December 12, 2000, GM announced that it had decided to halt development
of and "phase out" the Oldsmobile line. As a result of the announcement,
the Stokes dealership, Kirk A. Stokes, and James H. Stokes (hereinafter
referred to collectively as "the Stokeses") sought to recover damages they
alleged arose from GM's decision to discontinue the Oldsmobile line.
The Stokeses specifically alleged in count one of their complaint a violation
of the Alabama Motor Vehicle Dealer Act, Ala. Code §8-20-4 et seq.
(the "Act"), claiming that GM terminated the Oldsmobile line without notice
and without good cause as required by the Act. Count two alleged
an allocation claim under the Act. Count three alleged a fraud claim
based upon GM's alleged fraudulent suppression and concealment at the time
it presented the Oldsmobile dealer agreement to the Stokeses of the fact
that it would be shutting down the Oldsmobile line of vehicles. Count
four alleged breach of contract and breach of the implied covenant of good
faith and fair dealing. GM filed a motion to compel arbitration pursuant
to the relocation agreement. The Stokeses objected to arbitration,
arguing that their claims against GM arose solely out of the Oldsmobile
dealer agreement. After a hearing, the trial court denied GM's motion
to compel arbitration. GM appealed. HOLDING: The Supreme
Court affirmed. The Court noted that GM urged the Court in General
Motors Corp. v. Stokes, 850 So.2d 1239 (Ala. 2002) ("Stokes I"),
to reverse an order denying arbitration in an earlier proceeding between
it and the Stokeses by distinguishing the claim in that case from claims
that were part of the ongoing order of business between a dealer and GM
under existing dealer agreements, thereby indicating that such claims would
not be arbitrable. The Court held that GM cannot now be heard to
disavow the logic of its earlier argument in an effort to obtain arbitration
of this proceeding involving claims that are clearly part of the ongoing
order of business between a dealer and GM under an existing dealer agreement.
The Court noted that for it to come from the other direction and say a
dispute that is a part of the ongoing order of business between a dealer
and GM under an existing dealer agreement is also arbitrable under the
relocation agreement would suggest that it was misled by GM in Stokes
I when it accepted the distinction there advanced by GM between claims
arising under a dealer agreement and claims arising under the relocation
agreement. The Court concluded that such a facile construction would
unfairly advantage GM. The Court held that the claims asserted by
the Stokeses in the present action are not subject to the arbitration clause
contained in the relocation agreement. The Court concluded that the
arguments made below and reasserted here are sufficient to make the defense
of judicial estoppel to GM's demand for arbitration a ground for affirmance
presented by the record.)
*Download or view
PDF version of opinion*
-
Ex parte McWhorter,
No. 1021638 (Ala.
Oct. 24, 2003)
(sovereign immunity/State
immunity; Marilyn McCarley and four other plaintiffs (hereinafter referred
to collectively as "McCarley") sued Timothy L. McWhorter, a Lawrence County
deputy sheriff; the Lawrence County Commission; and Lawrence County on
theories of negligence and wantonness arising from a motor-vehicle accident.
The accident occurred on May 25, 2002, on Alabama Highway 157 in Lawrence
County, when a vehicle driven by Deputy McWhorter collided with a vehicle
occupied by McCarley. Deputy McWhorter filed a motion to dismiss
the complaint, asserting that he was entitled to sovereign immunity as
provided in Art. I, § 14, Ala. Const. of 1901. The trial court
denied the motion. McWhorter filed a petition for writ of mandamus.
HOLDING:
The Supreme Court granted the petition for writ of mandamus. The
Court noted that it is undisputed that Deputy McWhorter was acting within
the line and scope of his employment as a deputy sheriff at the time of
the accident. As such, the Court held that Deputy McWhorter is entitled
to sovereign immunity, now referred to as State immunity.)
*Download or view
PDF version of opinion*
Opinions Released October 17, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON FRIDAY, OCTOBER 17, 2003
-
LaFarge Bldg. Materials,
Inc. v. Stribling,
No. 1020623 (Ala.
Oct. 10, 2003)
(real estate; landlord-tenant;
fixtures; trade fixtures; Chattahoochee Valley Railway Company ("Chattahoochee")
leased land to Sidney Evans, who used the land to operate Valley Concrete
Company in Lanett. Evans paid $100 per month to lease the land and placed
improvements on the land to operate the concrete company. In 1987, Evans
sold his business and the equipment used in the business to Williams Brothers,
Inc., an entity that was LaFarge's predecessor in interest. Shortly after
Evans sold the business, LaFarge began to operate the concrete plant and
took the additional step of securely attaching the equipment to the property
by pouring concrete around the bases of the equipment. Evans remained involved
in the concrete plant, working as LaFarge's plant manager from 1987 to
1991. During LaFarge's operation of the concrete plant, it leased the land
from Chattahoochee under terms identical to those in the Chattahoochee-Evans
lease. In 1995, Phillip E. Stribling II, an acquaintance of Evans's,
purchased the land on which LaFarge's concrete plant was located from Chattahoochee
for $7,500. The purchase agreement assigned to Stribling all of Chattahoochee's
rights under its lease with LaFarge. Six days after Stribling purchased
the land, Evans acquired from Stribling a 50% interest in the land.
On December 31, 1996, LaFarge's lease expired. Stribling notified LaFarge
that it could renew the lease at the substantially higher rate of $2,000
a month or it could purchase the property for $100,000. LaFarge declined
both offers and opted to vacate the property. When LaFarge
vacated the property, it removed and dismantled several pieces of equipment,
apparently the same equipment Williams Brothers had previously purchased
from Evans. Additionally, LaFarge destroyed several structures and/or removed
several structures from the property. LaFarge admitted that when it vacated
the property it left the property in a state of disarray. Subsequently,
Stribling and Evans sued LaFarge, alleging breach of contract, wanton or
malicious destruction of property, and negligence in removing the equipment
and several structures from the plant. Paragraph 6 of the assigned
Chattahoochee-LaFarge lease regarding property improvements is the centerpiece
of Evans and Stribling's claim. It provides as follows: "6. Any buildings
and improvements erected on the leased property by the Lessee shall become
the sole property of Lessor at the expiration of the lease term or any
extension thereof as herein provided and it is hereby understood and agreed
that any building and improvements situated on the leased property at the
inception date of the lease is the sole property of the Lessor."
At trial, Evans and Stribling testified that they intended to operate a
concrete plant on the land after the lease expired, and that the removal
of the equipment caused them to lose profits of $424,598. LaFarge argued
that the removed items consisted of "trade fixtures" and that it was entitled
to remove the trade fixtures upon the termination of its lease. LaFarge
contends that it erected, placed, or attached to the ground all of the
equipment at issue, including structures and bins, in furtherance of its
trade or business. Stribling and Evans do not contradict this contention.
Stribling acknowledged that the purpose of putting the equipment on the
property was to carry on a trade or business. At the close of the evidence,
Stribling and Evans voluntarily dismissed their negligence and breach-of-contract
claims, leaving for consideration by the jury only the tort claims alleging
wantonness and intentional conduct. The trial court denied LaFarge's preverdict
motion for a JML and instructed the jury. The jury returned a verdict in
favor of Evans and Stribling, awarding them $500,000 in compensatory damages
and $1,500,000 in punitive damages. LaFarge then moved for a postverdict
JML, arguing that under Alabama law the equipment and structures were trade
fixtures. The trial court denied LaFarge's motion. In its order,
the trial court stated that "there was a legitimate and justiciable dispute
as to which items were trade fixtures and which items were a part of the
realty. HOLDING: The Supreme Court held that the trial
court's jury instruction incorrectly applied the law governing ordinary
fixtures to a case that should be governed by the law applicable to trade
fixtures because the trial court placed impermissible emphasis on the method
of attachment. The Court held that since it is undisputed that the
property in question was installed for the purpose of furthering LaFarge's
business, a judgment in favor of LaFarge was due to be entered on the issue
of whether the fixtures were trade fixtures, but the Court held that LaFarge
was still liable for the destruction or injury to the property resulting
from the removal of the trade fixtures in an amount equal to the cleanup
costs. The Court affirmed the trial court's order insofar as it denied
LaFarge's motion for a JML on the count of the complaint seeking damages
for cost of cleanup, and the Court remanded for a new trial as to the issue
of damages. However, insofar as the trial court's order awarded damages
for removal of trade fixtures, the Court reversed and rendered a judgment
in favor of LaFarge.)
*No PDF version of
this opinion is available*
Opinions Released October 10, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON FRIDAY, OCTOBER 10, 2003
-
Queen v. Belcher,
No. 1020061 (Ala.
Oct. 10, 2003)
(conservatorship;
trust; power of attorney; competence; Bettye Jan Belcher Queen, Beverly
Jean Belcher Scroggins, and Otha A. Belcher ("the petitioning children")
and the appellee, Brent Belcher ("Brent"), are all children of Olon Belcher,
an 87-year-old man who, they all acknowledge, suffers from dementia.
During his lifetime, Olon acquired a substantial estate, largely through
the success of Olon Belcher Lumber Company, a retailer of lumber and building
supplies. For some time, Brent has actively managed his father's
estate, first through a durable power of attorney executed in 1995, and
later through a family partnership formed in 1995, and amended in 1999,
and a trust agreement executed in 1998. On June 15, 2000, the petitioning
children petitioned the Probate Court of Bibb County to have a conservator
appointed for their father because of his diminishing mental capacity and
because of concern about the way their brother Brent was handling his estate.
On February 9, 2001, the probate judge granted the petition, concluding
that Olon "is a person unable to manage property and business affairs effectively
as described in [Ala. Code §26-2A-130]." The order also required
Brent to produce the 1998 trust agreement and to make an accounting of
that trust. Sanford E. Gunter was appointed conservator of Olon's
estate. Brent immediately removed the conservatorship to the Bibb
Circuit Court and, in June 2001, moved the court to issue an order: (1)
adopting the "Plan for Joint Care of Olon Belcher" Brent had submitted,
(2) directing the conservator to work with the instruments of Olon's estate
already in effect (the durable power of attorney, the partnership agreement,
and the trust agreement), and (3) setting June 15, 2000, the date the petitioning
children filed their petition for a conservator, as the effective date
for the appointment of a conservator. The petitioning children opposed
Brent's motion and moved the court to compel Brent to comply with the provisions
of the probate court's February 9 order that required him to produce the
1998 trust agreement and to make an accounting of that trust. They
further asked the court to find that Olon had been incapable of managing
his business affairs since 1994, and that, therefore, he did not have the
capacity in 1995 to execute the power of attorney or the partnership agreement
or subsequently in 1998 to execute the trust agreement and that those documents
were therefore invalid. On July 26, 2001, the trial court ruled that
Brent did not have to comply with the provisions of the probate court's
order requiring him to produce the trust agreement and to make an accounting
of the trust, but it did not address the other pending issues. Meanwhile,
on October 16, 2001, the court-appointed conservator filed his inventory
of Olon's estate. After listing Olon's then current assets and liabilities,
he noted numerous transactions in which Brent had been involved that the
conservator had not investigated, and he asked the court to clarify the
scope of his responsibility. The trial court scheduled a hearing
for December 17, 2001, to determine when Olon became incapable of effectively
managing his property and his business affairs. At the hearing, the
petitioning children presented deposition testimony from three doctors
in support of their contention that Olon was incapable of effectively managing
his property and business affairs at least as early as 1995, when he executed
the power of attorney in favor of Brent. They asked the court to
invalidate the power of attorney, the partnership agreement, and the trust
agreement, and to order a full accounting of the estate from 1995 to the
present. Brent presented six affidavits from witnesses who knew Olon
in varying degrees, both personally and in business settings, and who swore
that Olon had appeared lucid and intelligent during business interactions
they had had with him at different times between 1993 and 2000. Brent
also presented evidence indicating that the petitioning children had benefited
as well from transactions with Olon during this period. The petitioning
children moved to strike the affidavits as hearsay. On May 13, 2002,
the court denied the petitioning children's motion to strike the affidavits
and found that Olon had the legal capacity to execute the power of attorney
and the partnership agreement in 1995 and the trust agreement in 1998.
The court denied the petitioning children's request for an accounting of
the estate and ordered that the conservator manage the estate to reflect
the validity of all the documents executed by Olon before the conservator
was appointed. HOLDING: The Supreme Court reversed and
remanded. The Court held that the trial court's order was a final,
appealable order. The Court held that the trial court was correct
in recognizing that there are two standards of legal capacity--one for
"general business affairs" and one for "a will or other documents"; however,
the Court held that the trial court erred when it held the power of attorney,
the partnership agreement, and the trust agreement to the standard applicable
to wills because those are not testamentary documents. The Court
also held that neither Brent nor the trial court identified any exception
to the exclusionary hearsay rule that would permit the affidavits to be
admitted into evidence; accordingly, the Court held that they cannot be
considered.)
*Download or view
PDF version of opinion*
-
City of Prattville
v. Corley,
Nos. 1020075 et al.
(Ala. Oct. 10, 2003)
(damages for tort
claims for flood damage against municipalities; Ala. Code §§11-93-2,
11-47-190; failure to maintain storm drains; On September 1, 2000, eight
inches or more of rain fell in the City of Prattville within a few hours.
The City's storm drains and sanitary sewers overflowed, severely damaging
a number of residences and businesses. At the urging of the City's
mayor, the residents filed itemized claims with the City to recover damages.
The City quickly paid the damages claims filed by a few residents,
but it now contests a large number of the claims filed by other residents.
On December 5, 2000, a number of residents sued the City, alleging various
claims arising from the flooding, including negligence, trespass, inverse
condemnation, abatable nuisance, 42 U.S.C. § 1983 claims, and claims
seeking injunctive relief arising from what the residents argue is the
City's failure to properly maintain its storm drains. The City then
moved for a pretrial determination or declaration stating whether Ala.
Code §11-47-190 applied to limit its aggregate liability arising from
the September 1, 2000, flood. The trial court entered an order stating
that the issue of damages for those claims sounding in tort was controlled
by Ala. Code §11-93-2, not §11-47-190, and that §11-93-2
did not limit the City's aggregate liability for property damage.
The trial court certified its interlocutory order for permissive appeal,
and the Supreme Court granted the City's petition for permission to file
an interlocutory appeal. HOLDING: The Supreme Court
affirmed.)
*Download or view
PDF version of opinion*
-
Ex parte Alabama
Dep't of Youth Servs.,
No. 1020480 (Ala.
Oct. 10, 2003)
(sovereign immunity;
qualified immunity; state-agent immunity; Eleventh Amendment immunity;
Jane Doe 1 and Jane Doe 2, by and through their respective next friends
("Doe plaintiffs"), sued three Alabama Department of Youth Services ("DYS")
employees for committing various sexual assaults on the Doe plaintiffs
and for sexually harassing them while the Doe plaintiffs were in the custody
of DYS at its Chalkville campus. The Doe plaintiffs sued DYS for
violating Title IX of the Education Amendments of 1972, 86 Stat. 373, as
amended, 20 U.S.C. § 1681 et seq., by failing "to respond and/or their
inadequate response to" a "sexually hostile education environment and sexual
abuse and harassment." Against DYS, the Doe plaintiffs seek injunctive
relief, compensatory and punitive damages, and attorneys' fees. The
Doe plaintiffs sued executive director of DYS J. Walter Wood, Jr., under
various legal theories. All were based on Wood's, and certain
other supervisory defendants', being "entrusted with the security of elementary
students like the minor plaintiffs who are placed by operation of law into
their charge." The Doe plaintiffs alleged a claim against Wood under
42 U.S.C. § 1983 for deliberate indifference to their "right[s] to
personal safety, security and privacy, guaranteed by the Fourteenth Amendment"
while Wood was "acting under color of state law." The Doe plaintiffs
alleged that Wood "failed to develop, implement or administer procedures
or policies reasonably designed to provide protection for the minor Plaintiffs
from sexual harassment and abuse"; failed "to prevent male employees of
DYS from sexually abusing and harassing them"; failed "to investigate prior
complaints" against the three employees; and failed "to protect the Plaintiffs
from harm and from further harm after [Wood] received notice of the sexual
harassment and abuse and the potential for sexual harassment of" them.
The Doe plaintiffs seek compensatory and punitive damages, "equitable relief,"
attorneys' fees, and costs. The prayer for relief does not specifically
seek an injunction. The Doe plaintiffs also alleged state-law claims
against Wood, in his individual and official capacities, for "intentionally
and recklessly caus[ing] them to suffer extreme emotional distress by [his]
outrageous misconduct" and for negligently or wantonly hiring, supervising,
investigating, and monitoring the three employees, and their supervisor,
the principal of the school. The Doe plaintiffs alleged that Wood's
acts or omissions in the torts alleged in these two claims were "malicious
and intended to injure." The Doe plaintiffs also claimed against
Wood in his individual and official capacities for "willfully, recklessly,
and/or mistakenly represent[ing] to Plaintiffs a material existing fact,
which the Plaintiffs relied on said false representation that caused damage
to the Plaintiff[s] as a proximate result." The Doe plaintiffs asked
for compensatory and punitive damages and costs for all of these claims.
DYS and Wood moved to dismiss the Doe plaintiffs' claims against them.
DYS asserted that the claims against it should be dismissed on the ground
that DYS is an agency of the State of Alabama entitled to sovereign immunity
under the Eleventh Amendment to the United States Constitution and Art.
I, § 14, Alabama Constitution of 1901. Wood asserted that he
is entitled to a dismissal of the claims against him in his official capacity
on the ground of sovereign immunity under Art. I, § 14, Alabama Constitution
of 1901, and that he is entitled to a dismissal of the claims against him
in his individual capacity on the grounds of federal qualified immunity
and state-agent immunity. Both DYS and Wood asserted that they are
entitled to dismissal of the federal § 1983 claims against them on
the ground that § 1983 precludes respondeat superior liability.
The Doe plaintiffs responded in opposition to the motion to dismiss.
After a hearing, the trial court denied the motion to dismiss filed by
DYS and Wood. HOLDING: The Supreme Court held that DYS
is not entitled to Eleventh Amendment immunity from the Doe plaintiffs'
Title IX claim. The Court held that Wood has not shown a clear legal
right to a dismissal of the Doe plaintiffs' § 1983 claim on the ground
of federal qualified immunity. The Court held that the law of Eleventh
Amendment immunity, not of state constitutional sovereign immunity, governs
a Title IX claim brought against a state and, therefore, DYS is not entitled
to a dismissal of the Doe plaintiffs' Title IX claim on the ground of Art.
I, § 14, sovereign immunity. However, the Court held that Wood
has shown a clear legal right to a dismissal of the Doe plaintiffs' state-law
claims against him in his official capacity. The Court held that
because each of the plaintiffs' state-law claims against Wood expressly
alleges that his conduct was either malicious, willful, "intended to injure
the minor plaintiffs," or fraudulent, the allegations do not show, and
Wood has not shown, that he has a clear legal right to a dismissal of any
of these state-law claims on the basis of state-agent immunity.)
*Download or view
PDF version of opinion*
-
Frazier v. St. Paul
Ins. Co.,
No. 1020505 (Ala.
Oct. 10, 2003)
(uninsured-/underinsured-motorist
insurance; workers' compensation; Alan Jerome Frazier was employed by Charter
Communications as a line installer; a portion of his job responsibilities
involved driving the cable company truck to install, disconnect, and repair
cable. On December 7, 1999, Frazier was involved in a collision while
he was driving the company's truck in connection with his job when
Lee Roy Mullins pulled his vehicle out in front of the truck Frazier was
driving. Frazier could not stop, and he hit Mullins broadside.
As a result of the accident, Frazier suffered injuries to his neck and
back. He underwent fusion surgery and various other treatment.
Because Frazier was injured within the line and scope of his employment,
he qualified for workers' compensation benefits under the Workers' Compensation
Act. On June 11, 2002, Frazier reached a settlement with St. Paul,
Charter's workers' compensation insurance carrier. On May 8, 2001,
Frazier sued Mullins, the alleged tortfeasor, and St. Paul, Charter's automobile
insurance carrier, in the Marshall Circuit Court, seeking to recover damages
for his injuries. On February 22, 2002, the Marshall Circuit Court
entered a default judgment against Mullins. St. Paul filed a motion
for judgment as a matter of law, arguing that Frazier was precluded from
receiving workers' compensation benefits and uninsured-/underinsured-motorist
benefits for the same injury. The trial court granted St. Paul's
motion and entered a judgment for St. Paul. HOLDING:
The Supreme Court reversed. The Court noted that in Ex parte Carlton,
No. 1001781, (Ala. Apr. 11, 2003), it rejected the rationales of both cases
now relied upon by St. Paul, namely Auto-Owners Ins. Co. v. Holland,
832 So.2d 76 (Ala. Civ. App. 2002), and State Farm Mut. Auto. Ins. Co.
v. Carlton, No. 2991014, (Ala. Civ. App. May 11, 2001), aff'd
on other grounds, No. 1001781 (Ala. Apr. 11, 2003). The Court
held that assuming that Frazier meets the definition of an "insured" under
the St. Paul automobile insurance policy and assuming that no policy exclusion
applies, nothing in the Alabama Workers' Compensation Act would bar Frazier
from recovering the uninsured-/underinsured-motorist benefits to which
he may be entitled under the St. Paul automobile insurance policy issued
to Charter.)
*Download or view
PDF version of opinion*
-
UBS PaineWebber,
Inc. v. Brown,
No. 1020524
(Ala. Oct. 10, 2003)
(arbitration; E. Walton
Brown opened a brokerage account with J.C. Bradford in November 1999.
At that time, Glenn E. Brandon was working for J.C. Bradford. J.C.
Bradford was subsequently acquired by PaineWebber Group, Inc., the parent
company of UBS PaineWebber, Inc. ("PaineWebber"), in the spring of 2000.
In the acquisition, which was closed on June 9, 2000, J.C. Bradford Acquisition
Company, an acquisition subsidiary of PaineWebber Group, Inc., merged with
J.C. Bradford; J.C. Bradford continued to exist as a limited liability
company and became a wholly owned subsidiary of UBS Americas, Inc., which
also owns PaineWebber. The agreement Brown executed when he established
his brokerage account with J.C. Bradford contained an arbitration clause,
and there was also an arbitration agreement in materials PaineWebber contends
it sent to Brown on July 3, 2000, days before the transactions that form
the basis for this action. PaineWebber contends that, as a
result of corporate restructuring, it acquired all of the accounts of J.C.
Bradford's customers and that it sent Brown two "negative consent" letters
notifying him of that fact, as well as a "disclosure brochure" and a master
account agreement that contained the arbitration clause PaineWebber
contends governs Brown's transactions. Brown sued Brandon and PaineWebber.
In his complaint, Brown alleged that Brandon, acting as an agent of PaineWebber,
made unauthorized and unsuitable purchases of securities for Brown's account
and refused to sell the securities when Brown asked him to do so.
PaineWebber moved to compel arbitration. Brown denied that he received
from PaineWebber either a copy of the negative consent letters, the disclosure
brochure, or the master account agreement. Brown also contended that
the brokerage agreement entered into between Brown and J.C. Bradford, on
which PaineWebber partially relies, was not properly modified in accordance
with the terms of that agreement. The trial court denied the motion
to compel arbitration. HOLDING: The Supreme Court reversed.
The Court concluded that Brown received the master account agreement and
notice of the arbitration clause contained in that document. The
Court held that Brown's continuation of his relationship with PaineWebber
precludes his denial of acceptance of the terms of the PaineWebber agreement,
which unambiguously covers preexisting disputes.)
*Download or view
PDF version of opinion*
-
East Alabama Behavioral
Medicine, P.C. v. Chancey,
No. 1020828 (Ala.
Oct. 10, 2003)
(vicarious liability
under the doctrine of respondeat superior; vicarious liability under the
doctrine of ratification; In August 1996, Phillip Chancey sought treatment
from East Alabama for depression, anxiety, and panic attacks. Dr.
Kimberly Whitchard was Phillip's treating psychologist. On December
23, 1996, Whitchard and Phillip met for drinks at a local restaurant following
a therapy session. While at the restaurant, the two expressed romantic
feelings for each other. According to East Alabama, Whitchard
informed Phillip that same night that if she and Phillip engaged in a personal
relationship she would need to terminate their psychologist-patient relationship.
The Chanceys assert that the psychologist-patient relationship between
Phillip and Whitchard did not end until December 26, 1996. Nonetheless,
Phillip never objected to the termination of the professional relationship,
and it is undisputed that that relationship ended no later than December
26, 1996. On December 28, 1996, Phillip sent messages to the pager
Whitchard used in conjunction with her work at East Alabama, expressing
his love for her. Somehow, the messages were faxed to East Alabama
on December 30. Upon receiving these messages, the administrators
of East Alabama, Ed Sweeney and Joe Beacham, learned about Phillip's infatuation
with Whitchard and confronted Whitchard about the matter. Sweeney
and Beacham instructed Whitchard to end all contact, both personal and
professional, with Phillip. Furthermore, Sweeney and Beacham prepared
a letter for Whitchard to send to Phillip informing him that Whitchard
would no longer be his psychologist and that, if he wished to continue
treatment at East Alabama, Phillip's case would be assigned to Eddie Lancaster.
Phillip declined further treatment and never returned to East Alabama.
Whitchard testified at trial that Sweeney and Beacham told her during her
meeting with them on December 30, 1996, to change Phillip's medical records
to make it appear as though he had expressed feelings for her during a
treatment session and that she had then discussed the limits of a therapeutic
relationship with him. Sweeney and Beacham conceded that Phillip's
medical records had been altered, but denied that they instructed Whitchard
to do so. By mid-January 1997, approximately three weeks after the
termination of their professional relationship, Phillip and Whitchard were
sexually involved. A friend of Beth Chancey, Phillip's wife, saw
Whitchard and Phillip together, and she told Beth. Beth then asked
Phillip to leave the marital home. At that time, Whitchard, who was
also married, told her husband that she was leaving him for Phillip.
On January 18, 1997, Whitchard met with Beacham and Sweeney at Beacham's
home to tell them that she and Phillip were still involved in a personal
relationship and that she was resigning from her position at East Alabama.
Shortly after Whitchard's resignation, Phillip ended the affair and sought
treatment from another physician. In March 1997, after the affair
had ended, Whitchard returned to East Alabama and requested that she be
rehired. Sweeney and Beacham agreed to rehire Whitchard under the
condition that she undergo a psychiatric evaluation and, if necessary,
psychiatric treatment. Also, if she was rehired, Whitchard would
be restricted to treating only female patients. Phillip and Beth
Chancey sued Whitchard and East Alabama alleging negligent or wanton hiring,
training, and supervision; negligent or wanton counseling; negligent or
wanton "abandonment"; and negligence or wantonness per se; Beth Chancey
alleged loss of consortium. East Alabama filed a motion for a summary
judgment. The Chanceys, in response to East Alabama's motion for
a summary judgment, conceded that the entire basis for East Alabama's liability
was the doctrine of respondeat superior and the agency relationship that
existed between Whitchard and East Alabama. The trial court granted East
Alabama's motion for a summary judgment as to the claims asserting negligent
hiring and supervision. The Chanceys then filed a second amended
complaint alleging the alteration or destruction of medical records.
The Chanceys entered into a pro tanto settlement with Whitchard, settling
all their claims against her for $5,000. The case against East Alabama
on the remaining claims against it proceeded to a jury trial. At
the close of the Chanceys' case, East Alabama moved for a preverdict JML,
which the trial court denied. The jury returned a verdict in favor
of the Chanceys awarding them $1 each in compensatory damages and a total
of $495,000 in punitive damages. East Alabama then filed a postjudgment
motion for a JML, or, alternatively, for a new trial, or a remittitur,
primarily asserting that the issues of vicarious liability, ratification,
and abandonment should not have been submitted to the jury because, as
a matter of law, East Alabama cannot be held liable for Whitchard's tortious
conduct. The trial court denied the motion. HOLDING:
The Supreme Court reversed. The Court held that the trial court erred
in refusing to grant the motions for JML. The Court held that Whitchard's
affair with Phillip was not a function of her employment at East Alabama.
The Court also held that the doctrine of ratification cannot form the basis
for liability on the part of East Alabama. The Court noted that the
case was not tried on the basis of direct liability on the part of East
Alabama because the jury was instructed that East Alabama could not be
liable to the Chanceys if they found that Whitchard was not acting within
the line and scope of her employment. The Court held that, assuming
the Chanceys' claim for direct liability against East Alabama was properly
before it, it concluded that it fails as a matter of law.)
*Download or view
PDF version of opinion*
-
Morris v. Cornerstone
Propane Partners, L.P.,
No. 1020949 (Ala.
Oct. 10, 2003)
(res judicata; privity;
"virtual representation"; In a previous proceeding in the Calhoun Circuit
Court certain named plaintiffs who were poultry farmers and members of
the Calhoun County Poultry Association ("the McDill plaintiffs") asserted
claims of breach of contract and fraud arising from an alleged agreement
by Cornerstone Propane and Dean ("the propane defendants") to sell propane
to the McDill plaintiffs at a stated price. The case was tried, and
the trial resulted in a judgment for the propane defendants. Although
the McDill proceeding was initiated on behalf of a putative class, it was
not certified as a class action. The Calhoun County Poultry Association
("the Association") was named as a plaintiff in the McDill proceeding,
but before the trial began in that case, the trial court limited the plaintiffs
to the individuals named in the caption of the complaint. Stanley
Morris and other new plaintiffs who were not named in the McDill proceeding
("the Morris plaintiffs") have filed the instant action seeking essentially
the same relief against the same propane defendants. The Morris plaintiffs
are also poultry farmers and members of the Association. After the
propane defendants moved for a summary judgment in this action, asserting
the defense of res judicata based on the outcome of the McDill proceeding,
the trial court entered a summary judgment in their favor. HOLDING:
The Supreme Court reversed. The Court concluded that the defense
of res judicata does not apply to this case because the fact that the Morris
plaintiffs were members of the same association to which the McDill plaintiffs
belonged does not constitute a sufficient basis for concluding that the
essential element of privity between the parties in the McDill proceeding
and in this proceeding exists.
*Download or view
PDF version of opinion*
-
United Wisconsin
Life Ins. Co. v. Tankersley,
No. 1021128 (Ala.
Oct. 10, 2003)
(arbitration; scope
of arbitration agreement; United Wisconsin Life Insurance Company is an
insurance underwriter and the issuer of the health-insurance policies involved
in this action. Its principal place of business is in Wisconsin.
American Medical Security, Inc. serves as the administrator of the United
Wisconsin policies; American Medical's principal place of business is also
in Wisconsin. The plaintiffs in the underlying action, Ruth Shuniak,
Susan N. Tankersley, Nathaniel Miller, Debbie Miller, and Gregory Shockley
(hereinafter referred to collectively as "the plaintiffs") are all individual
residents of Alabama. The various plaintiffs completed applications
for health insurance under a group policy with United Wisconsin.
American Medical approved the applications in Wisconsin and sent an insurance
certificate entitled "Certificate of Group Insurance" and a group insurance
policy to each plaintiff shortly after completion of the application.
At some point, United Wisconsin issued a rider to the policy; the rider
added an arbitration provision to the policy. In their complaint,
the plaintiffs allege that they are all current or former policyholders
of a United Wisconsin group health-insurance policy, namely "Master Policy
Number AB 2000." The plaintiffs allege that United Wisconsin and
American Medical, or presumably their agents, marketed this policy to the
plaintiffs by representing that it was a group insurance policy and that
the premiums charged the plaintiffs were or would be based on the group's
claims experience. The plaintiffs allege that beginning in 1998 and
continuing throughout 2002, United Wisconsin and/or American Medical increased
their premiums at various times in a manner that was not based upon the
group's claims experience but upon their individual claims experience.
They assert claims of intentional, reckless, and/or negligent misrepresentation;
suppression; fraudulent concealment; conspiracy to mislead the plaintiffs
concerning the premium increases and the actual basis of the premium charges,
conspiracy to constructively cancel the policies of certain policyholders
who made certain claims or who suffered from certain medical conditions,
and conspiracy to improve the profit margin on the policies; breach of
fiduciary duty; and breach of contract. United Wisconsin and American
Medical moved to compel arbitration of the plaintiffs' claims. The
trial court denied United Wisconsin and American Medical's motion to compel
arbitration. HOLDING: The Supreme Court affirmed.
The Court noted that the arbitration provision at issue in the present
case is identical to the provision in United Wisconsin Life Insurance
Co. v. Beaty, 775 So.2d 191 (Ala. 2000), and held, consistent with
that case, that the scope of the arbitration agreement was limited to disputes
regarding only claims for benefits made under the policy. Thus, the
Court held that the arbitration provision here is not broad enough to encompass
the plaintiffs' claims.)
*Download or view
PDF version of opinion*
-
Ex parte State of
Alabama (In re: Draper v. State),
No. 1021611 (Ala.
Oct. 10, 2003)
(criminal; evidence;
admission of evidence of a prior conviction; The Supreme Court denied the
petition for writ of certiorari without opinion. Justice Stuart wrote
a dissenting opinion.)
*Download or view
PDF version of opinion*
Opinions Released October 3, 2003
-
DECISIONS ANNOUNCED BY
THE SUPREME COURT OF ALABAMA ON FRIDAY, OCTOBER 3, 2003
-
Bowen v. Security
Pest Control, Inc.,
No. 1010783 (Ala.
Oct. 3, 2003) (on application for rehearing; withdrawing and substituting
opinion of February 28, 2003)
(arbitration; interstate
commerce; This is a case in which the Supreme Court had originally reversed
the trial court's order compelling arbitration by application of Sisters
of the Visitation v. Cochran Plastering Co., 775 So.2d 759 (Ala. 2000).
On rehearing, the Court changed its decision and affirmed on the authority
of the U.S. Supreme Court's disapproval of the
Sisters of the Visitation
standard in Citizens Bank v. Alafabco, Inc., 123 S. Ct. 2037 (2003).)
*Download or view
PDF version of opinion*
--(The original, withdrawn
opinion released in Bowen on Feb. 28, 2003, is also available on
the website of Wallace, Jordan, Ratliff & Brandt, L.L.C.)--
-
Royal Ins. Co. of
Am. v. Thomas,
No. 1011518 (Ala.
Oct. 3, 2003)
(insurance coverage;
Certified Question from the United States District Court for the Northern
District of Alabama; The certified questions relate to the coverage afforded
Sandra Hill Thomas ("Thomas"), a customer of Carl Cannon Chevrolet-Olds,
Inc. ("Carl Cannon"), by two insurance policies issued to Carl Cannon:
a garage policy issued by Certain Interested Underwriters at Lloyd's of
London ("Lloyd's London") and an umbrella policy issued by Royal Insurance
Company of America ("Royal"). About October 9, 1998, Carl Cannon
lent a car to Thomas while Carl Cannon repaired Thomas's car. On October
13, 1998, Thomas was driving the Carl Cannon car when it collided with
another car occupied by Velma Daniel ("Daniel"). To recover for injuries
she suffered in the collision, Daniel sued Thomas and Carl Cannon in the
Walker Circuit Court. The Walker Circuit Court entered a summary judgment
for Carl Cannon. The Lloyd's London and Royal policies constituted
Thomas's only potential sources of liability insurance for the collision.
Lloyd's London contended that Section II, paragraph A.1.a.(2) of the Lloyd's
London garage policy ("the exclusion") excluded Thomas as an insured unless
she either had no other available primary, excess, or contingent insurance
or had insufficient coverage under such insurance to meet the $20,000 minimum
required by the Motor Vehicle Safety-Responsibility Act, Ala. Code §32-7-1
et seq., ("the Act"). Lloyd's London further contended that, if Thomas
did not have other available primary, excess, or contingent insurance or
had insufficient coverage under such insurance to meet the $20,000 minimum
required by the Act, then the exceptions to the exclusion preserved coverage
for Thomas under the Lloyd's London garage policy but limited the coverage
to the amount necessary for her to meet the $20,000 minimum required by
the Act. The exclusion and the two exceptions to the exclusion appear
within the subsection of the Lloyd's London garage policy defining "who
is an insured" under the policy. After that subsection of the policy initially
defines "insured" as including Carl Cannon and anyone else while using
a Carl Cannon car with the permission of Carl Cannon, the exclusion then
excludes customers of Carl Cannon. The two exceptions to the exclusion
then preserve coverage for customers who either have no other available
primary, excess, or contingent insurance or have insufficient coverage
under such insurance to meet the $20,000 minimum required by the Act.
To resolve the coverage disputes, Royal sued Thomas, Daniel, and Lloyd's
London for a declaratory judgment in the federal district court. Thomas,
whom neither Lloyd's London nor Royal provided with counsel for the coverage
disputes, depended on Daniel to advocate Thomas's rights to coverage under
the policies. After Royal moved for a partial summary judgment and Lloyd's
London cross-moved for a summary judgment, the federal district court certified
the following questions: "1. Is the exclusion or limiting clause
contained in Section II, paragraph A.1.a.(2) of the Lloyd's Garage Liability
Policy issued to Carl Cannon Chevrolet-Olds, Inc., as the insured's primary
liability coverage, valid under Alabama law? Put another way, does the
Alabama law allow an insurer to limit its exposure under a so-called 'garage'
policy by reducing its liability limit to the statutory minimum in cases
in which a permitted driver qualifies as an 'insured,' but does not possess
automobile liability coverage?" and "2. Depending upon the answer to question
1, what coverage, if any, is provided to the driver of the automobile that
was furnished by Carl Cannon Chevrolet-Olds to her under the language of
Section VI.6 of Royal's Big Shield Commercial Catastrophe Liability Policy?"
HOLDING:
The Supreme Court answered the first certified question in the affirmative
for the time pertinent to this case. As to the second question, the
Supreme Court concluded that because Thomas does not have "underlying insurance"
and the Royal policy affords primary coverage to Thomas instead of excess
coverage, the drop-down provision does not apply to the coverage Royal
owes Thomas. That is, the Court held that (a) the Lloyd's London
garage policy exclusion validly excludes Thomas as an insured under that
policy, (b) the Royal umbrella policy affords Thomas primary coverage for
the collision, and (c) the drop-down provision in the Royal policy has
no application to the coverage for Thomas under the Royal policy.)
*Download or view
PDF version of opinion*
-
Eagle Products,
Inc. v. Glasscock,
No. 1020206 (Ala.
Oct. 3, 2003)
(claims of breach
of contract, misrepresentation of facts, and deceit; excessive damages;
judgment as a matter of law; John Glasscock sued Eagle Products, Inc. (hereinafter
"Eagle"), alleging claims of breach of contract, misrepresentation of facts,
and deceit. The case proceeded to trial on June 17, 2002. The
dispute centered around a distributor agreement in which Glasscock became
a distributor of Eagle products. Eagle manufactures premium dog food
and pet supplies. At the close of Glasscock's case,
Eagle moved for a judgment as a matter of law ("JML"). The trial
court granted Eagle's motion for a JML "as it relate[d] to fraud and den[ied]
as it relate[d] to the contract." Eagle rested its case without calling
any witnesses and then renewed its motion for a JML on the breach-of-contract
claim; the trial court denied the motion. The jury returned a verdict
in favor of Glasscock and awarded him $500,000 in damages. Eagle
filed a postverdict motion for a JML, or, in the alternative, a new trial,
which it subsequently amended to request, in the alternative, a remittitur.
The trial court denied Eagle's posttrial motion. HOLDING:
The Supreme Court reversed and rendered a judgment for Eagle. The
Court held that the distributor contract was terminable at will.
The Court noted that in 1996 Eagle notified Glasscock, initially by letter
and then in person, that in order to retain his distributorship status,
Glasscock would have to meet specified criteria. Glasscock testified
that he did not meet many of the required criteria, and in July 1996 Eagle
notified Glasscock that he was being classified as a direct-buy account,
rather than as a distributor. Glasscock conceded at trial that he
knew at the time that Eagle's opinion was that he was no longer their distributor.
The Court noted that at trial, Glasscock did not dispute that Eagle had
the right to sever the distributorship agreement, he argued only that in
doing so it did not comply with the terms of the contract. Under the distributorship
agreement between Glasscock and Eagle, in the event Eagle severed the distributorship
relationship, Eagle was required to "pick up and pay for any product that
[was] dated not more than 90 days old." Glasscock testified that
he knew that Eagle could terminate the distributorship "if they bought
back the product from [him]." Glasscock testified that he did not
have any product less than 90 days old at the time he received the July
1996 letter. The Court concluded that, therefore, at the time Eagle terminated
the relationship, July 11, 1996, there was no product Eagle was required
to buy back in conjunction with the termination of Glasscock's distributorship
status, and Eagle effectively terminated the distributorship agreement
by notifying Glasscock of his direct-buy classification in Hurst's July
1996 letter.)
*Download or view
PDF version of opinion*
-
Ex parte Patel,
No. 1020364 (Ala.
Oct. 3, 2003)
(on application for
rehearing; criminal; capital offense; The Court overruled the application
for rehearing without opinion. Justice Houston wrote a concurring
opinion stating that he would revise the portion of the opinion in which
the Court quoted from Roan v. State, 24 Ala. App. 517, 137 So. 320
(1931), in order to clarify that, under the circumstances presented here,
the State has the burden of proving that the crime was committed and showing
"facts that would convince the judge that upon final trial the judge would
sustain a verdict pronouncing the defendant guilty and imposing the death
penalty [or a sentence of life imprisonment without parole].")
*Download or view
PDF version of opinion*
--(The original opinion
released May 23, 2003, in Patel is also available on the website
of Wallace, Jordan, Ratliff & Brandt, L.L.C.)--
-
Ex parte Tomlin,
No. 1020375 (Ala.
Oct. 3, 2003)
(criminal; capital
murder; death penalty; sentencing; jury override; On January 2, 1977, the
bodies of Richard Brune and Cheryl Moore were found on an exit ramp from
I-10 in Mobile County. Both had died as the result of multiple gunshot
wounds. In 1999, Phillip Wayne Tomlin was convicted, for the fourth
time, of the intentional murders of Brune and Moore, an offense made capital
because two people were intentionally killed pursuant to one act or a series
of acts. See Ala. code §13-11-2(a)(10) (repealed). The
jury at Tomlin's fourth trial was not asked to make a sentencing recommendation.
Instead, the parties stipulated that the jury at Tomlin's third trial,
by a vote of 12-0, had recommended that Tomlin be sentenced to life imprisonment
without the possibility of parole. After a sentencing hearing, the
trial court overrode the jury's recommendation and sentenced Tomlin to
death. In its sentencing order, the trial court found only one aggravating
circumstance: "The only aggravating circumstance ... in this case is the
one contained in the definition of the capital offense itself: that [Tomlin]
committed murder in the first degree wherein two human beings were intentionally
killed by the defendant by a series of acts." While the trial court
found no statutory mitigating circumstances, it found several nonstatutory
mitigating circumstances. The Court of Criminal Appeals affirmed
Tomlin's conviction and sentence. The dispositive issue in the petition
for writ of certiorari is whether the decision of the Court of Criminal
Appeals conflicts with the Alabama Supreme Court's decision in Ex parte
Carroll, No. 1010546 (Ala. July 26, 2002). HOLDING:
The Supreme Court reversed. The Court concluded that, under the circumstances
presented here, the trial court's override of the jury's recommended sentence
of life imprisonment without parole and that court's subsequent sentence
of death were improper because the court did not give proper deference
to the unanimous jury recommendation.)
*Download or view
PDF version of opinion*
-
Mobile Airport Authority
v. HealthSTRATEGIES, Inc.,
No. 1020376 (Ala.
Oct. 3, 2003)
(stop-loss insurance;
claims of unjust enrichment, money had and received, and quasi-contract,
among others; The Mobile Airport Authority ("MAA") offers health-insurance
coverage to its employees and certain dependants of its employees through
its self-funded employee health-care plan. MAA bears all of the risks
and financial obligations associated with funding benefits under its health-insurance
plan. MAA sought to acquire a stop-loss insurance policy to limit its financial
exposure under its health-insurance plan. Stop-loss insurance "protects
a self-insured employer from catastrophic losses or unusually large health
costs of covered employees." MAA directed HealthSTRATEGIES, Inc.
its third-party administrator ("TPA"), to obtain stop-loss insurance for
it. HealthSTRATEGIES chose a product offered by Pan American Life Insurance
Company ("PALIC"). PALIC did not provide stop-loss policies directly
to those entities seeking such insurance. Instead, its stop-loss policies
were issued by managing general underwriters, who were directly authorized
by PALIC to issue such policies. The particular managing general underwriter
that dealt with HealthSTRATEGIES in procuring stop-loss insurance for MAA
was Sympson & Associates, Inc. ("SAI"). PALIC provided SAI with
the forms necessary to issue its insurance policies, including applications
for stop-loss insurance policies. On July 1, 1998, HealthSTRATEGIES
sent an application to MAA for a PALIC stop-loss insurance policy. The
blanks on the application, which was drafted by PALIC, had been completed
by Anthony Allen of HealthSTRATEGIES. MAA's representative signed the application,
entitled "Application to Pan American Life Insurance Company for Aggregate
and Specific Excess Loss Insurance" ("the application"), and submitted
it to PALIC. The application requested coverage for the period from
July 1998 to June 1999. On the last page of the application is a blank
for the signature of the applicant and a blank for a signature labeled
"Acceptance by Carrier." No signature appears in the latter blank.
MAA paid premiums upon its application for the insurance and every
month during the period for which it requested coverage. MAA paid the premiums
to HealthSTRATEGIES; HealthSTRAGEGIES would deduct its commission from
the premium amount and would then pay SAI, which would also deduct a commission
and then pay PALIC. Following the submission of the application,
SAI sent most of its communications regarding the policy to HealthSTRATEGIES.
At some point, SAI assigned MAA a policy number -- PAL 6901. In a letter
dated September 18, 1998, SAI requested several documents from HealthSTRATEGIES.
In the letter, SAI stated, "[T]he purpose of this letter is to initiate
the Binder/Issue process." The letter also stated: "SAI will require the
following information in order to complete this file and issue the contract
... (1) Plan Document signed by the employer[,] (2) Medical Disclosure
Statement[, and] (3) Sold Census ...." An applicant must submit
a plan document and a medical disclosure statement before PALIC will issue
a policy. The plan document is a comprehensive description of the
medical benefits provided under a health-benefit plan to employees of the
company seeking stop-loss insurance. The stop-loss insurance coverage
is defined in reference to the plan document. In fact, the plan document
is attached to and becomes part of the policy. The medical disclosure
statement is a document on which the employer's TPA, in this case HealthSTRATEGIES,
or broker must list the names of beneficiaries under the company's health-benefit
plan who fall into certain defined categories. MAA, however, could
not complete a medical disclosure statement form because federal privacy
laws prevent an employer from having the information necessary to complete
the form. The medical disclosure statement gives the insurer the
ability to exclude certain high-risk beneficiaries from stop-loss coverage.
SAI's TPA manual states that "[b]efore coverage can be bound, the following
... must be submitted to SAI within 15 days after proposed effective date
of the new sold case: ... 8. Medical Disclosure Statement (Form DS-1) signed
by the employer." The medical disclosure statement form states: "The
Plan Sponsor [MAA] further acknowledges, understands and agrees that this
information may be used in evaluating and determining the acceptability
of the Plan Sponsor's risk and that no coverage shall become effective
until specifically agreed to in writing by the Underwriter." In December
1998, MAA hired a new TPA, Bluebonnet Administrators of Jackson, Mississippi
("Bluebonnet"), and discontinued its relationship with HealthSTRATEGIES.
In a letter dated February 26, 1999, from Mark Bieze, senior vice president
of SAI, SAI responded to a letter from Bluebonnet. In the February
26, 1999, letter, SAI stated, in pertinent part: "4) The policy for
this group cannot be issued because the following documentation remains
outstanding: A) a copy of the signed plan document, and B) a completed
disclosure statement. ... Hopefully, the outstanding issues can be
resolved quickly and to everyone's satisfaction. However, unless complete
and satisfactory information is received in this office within ten days
of the date of this letter, we will have no choice but to send written
notice of cancellation to the client." The information requested
in SAI's letter was never sent, and no "written notice of cancellation"
was sent to MAA. SAI sent a second letter to Bluebonnet on May 7,
1999. That letter stated: "In order to issue the policy on [MAA] we need
the plan document signed by the employer and I have enclosed a medical
disclosure form for you to complete." SAI never received the
medical disclosure statement or the plan document. On June 9, 1999,
July 8, 1999, and August 5, 1999, SAI faxed requests to Bluebonnet; those
requests read: "In order to issue the policy for [MAA] we need the Medical
Disclosure Statement and the Plan Document signed by the employer."
On August 5, 1999, SAI faxed a document to MAA for the first time; that
document stated: "In order to issue the policy for [MAA] I need the
plan document signed by the employer and the medical disclosure statement.
I am so sorry for the inconvenience but this is the only way I can issue
this policy[.] I need the two above items taken care of. I am sorry I had
been faxing [Bluebonnet] but [it] told me to contact you." On October
7, 1999, SAI faxed another request to MAA requesting the same documents
"[i]n order to issue the policy for MAA ... because we got a claim pending."
At some point before October 7, 1999, MAA had filed a claim with SAI for
stop-loss insurance coverage. MAA asserts that it filed the claim before
it was aware that no stop-loss insurance policy had been issued by PALIC.
Finally, on October 18, 2000, PALIC sent a letter to MAA repeating SAI's
request for "a signed copy of the plan document" so it could "issue the
stop loss policy." PALIC requested the document because it wished to adjudicate
the claim filed by MAA that had been pending since before October 7, 1999.
MAA asserts that it was not aware that it did not have a stop-loss insurance
policy in place until after the desired coverage period. At that point,
MAA had paid over $90,000 in premiums to PALIC. On June 28, 2001,
MAA sued HealthSTRATEGIES, SAI, and PALIC in the Mobile Circuit Court.
Including the claims that are alleged in MAA's second amended complaint
filed on June 22, 2002, MAA alleges equitable claims of unjust enrichment,
money had and received, and quasi-contract against all the appellees; various
tort claims against all the appellees; and a breach-of-contract claim against
HealthSTRATEGIES. On May 31, 2002, PALIC and SAI filed motions for a summary
judgment; HealthSTRATEGIES did the same on June 14, 2002. On September
30, 2002, MAA filed a motion for a partial summary judgment against all
the appellees with respect to its equitable claims. On October 17, 2002,
the trial court granted the appellees' motions for a summary judgment and
denied MAA's motion for a partial summary judgment. MAA appeals.
HOLDING:
The Supreme Court reversed the trial court's summary judgment in favor
of PALIC, SAI, and HealthSTRATEGIES. The Court affirmed the trial
court's denial of MAA's motion for a partial summary judgment, and the
Court remand the cause for further proceedings.)
*Download or view
PDF version of opinion*
-
American National
Red Cross v. ASD Specialty Health Care, Inc.,
No. 1020446 (Ala.
Oct. 3, 2003)
(Certified Question
from the United States District Court for the Southern District of Alabama:
"Whether the [Alabama Uniform Fraudulent] Transfer Act, Ala. Code
§§8-9A-1 et seq., includes blood products, as provided for in
Ala. Code §7-2-314(4)." Plaintiff Red Cross alleges that, during
1999, it entered into an arrangement with an individual named Peter Woolley
and a company with which he was affiliated, LA Pharmaceutical, to sell
blood products to LA Pharmaceutical, LLC ('LA Pharmaceutical'). Plaintiff
further alleges that LA Pharmaceutical, through one of its principals,
Peter Woolley, then transferred the blood products to certain of the defendants
in violation of the Alabama Uniform Fraudulent Transfer Act ("AUTFA").
(A default judgment has previously been entered against LA Pharmaceutical
and Peter Woolley, neither of which are defendants in this current action.)
The defendants (ASD Specialty Health Care, Inc.; Midwest Drug Supply,
LLC; and Raymar Worldwide Sales, Inc.) deny any liability under the AUFTA.
The defendants have also asserted that the AUFTA has no application in
this case because the blood products in question are considered, for all
purposes, to be a 'service' under Ala. Code §7-2-314(4) and, therefore,
not 'property' under the AUFTA. All parties agree that the blood
products in question are governed by §7-2-314(4). Plaintiff
asserts that the AUFTA is applicable because the definition of 'property'
under the AUFTA includes the blood products in question; however, defendants
assert that the AUFTA is not applicable because the definition of 'property'
under the AUFTA does not include services. HOLDING:
The Supreme Court answered the certified question in the affirmative.
The Court reasoned that because §7-2-314(4) does not exclude blood
products from the application of the AUFTA and because blood products "may
be the subject of ownership," they are "property" for purposes of the AUFTA.)
*Download or view
PDF version of opinion*
-
Ex parte Bender
Shipbuilding & Repair Co.,
No. 1020545 (Ala.
Oct. 3, 2003)
( Longshoremen and
Harbor Workers' Compensation Act, 33 U.S.C. § 901 et seq. ("the LHWCA");
fraud; preemption; In 1990, Faron Walley injured his upper back while he
was working at Bender Shipbuilding & Repair Co.'s shipyard as a shipfitter
for a company known as T.J. Adams, a subcontractor of Bender. For
the next two years, Walley was unable to work because of his injury.
During this time, T.J. Adams, through its workers' compensation insurance
carrier, Liberty Mutual, paid for Walley's medical treatment and also paid
Walley temporary disability compensation pursuant to the LHWCA. Dr.
James West, Walley's treating physician, eventually assigned him a 5% permanent
impairment rating and released him for full-duty work with no restrictions
in 1992. After his release, Walley worked for the next three years
as a shipfitter, welder, and fabricator for two companies other than T.J.
Adams and Bender. In 1995, Walley was again employed by a subcontractor
to work at Bender's shipyard. After approximately three months, however,
Bender hired Walley to work directly for Bender. At that time, Walley
was examined by Bender's physician and was determined to be physically
and mentally fit for work as a shipfitter. On December 9, 1996, Walley
injured his back while lifting a mooring hook on a ship at Bender's shipyard.
Walley informed his foreman of the injury and finished his shift despite
the injury. The next morning, Walley's back pain had worsened and
he contacted his foreman, who told him to contact Vicki Wagner, an employee
in Bender's safety department. When Wagner asked Walley whether his
injury was related to his 1990 upper-back injury, Walley stated that it
might be, but that his entire back was hurting. Conflicting evidence
was introduced at trial as to whether Walley's December 1996 injury was
a recurrence of his 1990 injury, as opposed to an aggravation of his 1990
injury or a new injury. There was also conflicting evidence as to
whether Bender understood and believed Walley's December 1996 injury to
be a recurrence of his 1990 injury, rather than an aggravation of that
injury or a new injury. Although a December 18, 1996, entry by Dr.
West on Walley's medical chart contains a statement that "[t]he patient
states that this is related to his old injury and not [a] new injury,"
Dr. West's subsequent January 22, 1997, notes reflect his opinion that
"this is an exacerbation of [Walley's] previous injury." On January
22 1997, Dr. West again examined Walley and released him to return to work
with a light-duty restriction. Walley returned to Bender's shipyard
and provided Wagner with his light-duty work release. However, Walley
testified that Wagner and Jere Davis, a safety and risk manager for Bender,
discussed the release and told him that Bender had no light-duty work available.
Bender was self-insured under the LHWCA, and its light-duty work policy
for partially disabled employees was in addition to its obligations with
respect to compensation and medical benefits under the LHWCA. Under
the light-duty work policy, Bender paid an injured employee the full amount
of his or her normal weekly wage when the employee engaged in light-duty
work. Employees receiving only temporary disability benefits under
the LHWCA received payments equal to only a portion of their normal weekly
wage. Although T.J. Adams, through Liberty Mutual, initially paid
for Walley's medical expenses resulting from his December 1996 injury,
T.J. Adams refused to pay Walley's temporary disability benefits and eventually
stopped paying his medical expenses. In March 1997, Walley retained
an attorney and filed a complaint against Bender with the United States
Department of Labor. Pursuant to its rights under the LHWCA, Bender
initially contested Walley's claim. However, after a June 1997 meeting
between the Department of Labor, Bender, and Walley, Bender accepted the
Department of Labor's finding that Bender was responsible for Walley's
medical expenses and compensation benefits under the LHWCA. Bender
began paying Walley's medical expenses and, within a few weeks, also began
paying Walley temporary disability benefits. Bender thereupon also
offered Walley light-duty work in accordance with its light-duty work policy.
Walley had no income between the date of his December 1996 back injury
and June 1997, when Bender accepted responsibility for paying LHWCA benefits
to Walley. Dr. West released Walley to return to full-duty work effective
September 1, 1997. Although Bender paid Walley's medical expenses
and also his LHWCA compensation benefits accruing after the June 1997 meeting
with the Department of Labor, it was not until July 1998 that Bender
paid Walley the temporary disability benefits due for the period from his
December 1996 injury until the June 1997 meeting. Bender subsequently
paid penalties assessed by the Department of Labor against Bender for its
failure to make timely compensation payments in accordance with the LHWCA.
Walley was unable to pay his living expenses for several months after Dr.
West released him for light-duty work in January 1997. As noted,
during the period, Bender did not pay Walley compensation benefits under
the LHWCA and did not provide him with light-duty work. As a result,
Walley borrowed money from family and friends to pay his living expenses.
He also received assistance from community resources, and he eventually
applied for and received food stamps. Walley averted creditors' efforts
to repossess his truck and to foreclose on his home by borrowing money
from his family, including a $20,000 loan from his parents. Because
he had no source of income, Walley was unable to pay a court-ordered monthly
child-support obligation for the benefit of his son. Walley stated
that his former wife attempted to have him held in contempt for his failure
to pay child support and that she refused to let him exercise his visitation
rights with their son until he had paid all of his child-support obligation.
After receiving that payment, Walley paid his past-due child-support obligation;
he had been unable to visit with his son for approximately 18 months.
There was evidence introduced at trial indicating that Walley was so affected
by his circumstances that, in May 1997, a neighbor had Walley hospitalized
because he had not been eating and she was concerned about his being depressed.
In October 1997, Walley sued Bender in the Mobile Circuit Court alleging,
in pertinent part, that Walley was entitled to an offer of light-duty work
after he was released for such work in January 1997, but that Bender falsely
represented to Walley that no light-duty work was available. Walley
alleged that as a result of Bender's alleged fraud, he suffered monetary
losses and mental anguish; he requested both compensatory damages and punitive
damages. Bender filed a motion for a summary judgment arguing, among
other things, that Walley's fraud claim was barred by the exclusivity provision
of the LHWCA and also that, although some courts have recognized an intentional-tort
exception to the LHWCA's exclusivity provision if the employer has specifically
intended to injure the employee, Walley had failed to allege and offer
evidence that Bender specifically intended to injure him. The trial
court denied Bender's motion. The jury returned a verdict in favor
of Walley and against Bender for $40,000 in compensatory damages, and the
court entered a judgment on that verdict. The Court of Civil Appeals
affirmed. HOLDING: The Supreme Court reversed.
The Court concluded that the availability of a light-duty-work program,
while not mandated by the LHWCA, is an economic benefit an employer can
offer its employees in lieu of its obligation to pay temporary total disability
benefits. The Court reasoned that although the LHWCA does not require
that such a benefit be provided, claims regarding the mishandling of an
economic benefit such as light-duty work, made available to an employee
as the employer's alternative means of complying with the LHWCA, would
arise under the LHWCA. The Court further concluded that, despite
being labeled an "intentional fraud claim," Walley's claim is actually
a claim alleging that Bender, intentionally or in bad faith, refused to
award a benefit to him and, in so doing, intentionally inflicted emotional
distress. Thus, the Court held that Walley's claim against Bender
for failure to confer a benefit offered only as a means of the employer's
satisfying its obligations under the LHWCA is preempted and precluded.)
*Download or view
PDF version of opinion*
-
Providian Nat'l
Bank v. Screws,
No. 1020668 (Ala.
Oct. 3, 2003)
(arbitration; validity
of the contract containing the arbitration provision; arbitration provision
added to credit-card agreements by amendment; John Screws, Sheila Adams,
Terry Person, Charles Richardson, and Gloria Shade (hereinafter referred
to collectively as "the plaintiffs") sued Providian Financial Corporation,
Providian National Bank, Providian Bank, and Providian Bancorp Services
(hereinafter referred to collectively as "Providian") in the Barbour County
Circuit Court. The plaintiffs are current or former holders of a
credit card issued by Providian National Bank. The complaint alleges that
Providian violated its credit-card agreements with the plaintiffs and engaged
in "unconscionable, unfair and fraudulent" business practices by charging
higher than agreed to interest rates, charging for services and products
not requested by cardholders, and improperly assessing late fees.
Providian National Bank notified holders of its credit card, including
the plaintiffs, of a change in the terms of the credit-card agreement,
inserting into the agreement an arbitration provision. Providian
notified its cardholders of this change in the terms of their credit-card
agreements by enclosing a notice in the monthly billing statement.
Acceptance of the arbitration provision by the cardholder was not mandatory.
The notice enclosed within the monthly billing statement began by stating:
"This notice is to advise you that the following Arbitration Provision
will be added to your Account Agreement (the 'Agreement'). The Arbitration
Provision will become effective forty-five (45) calendar days after the
Statement Date on the enclosed billing statement ... unless we receive
prior to then a letter from you stating that you do not want the Arbitration
Provision to become part of the Agreement.... If we receive such a letter
on time, the Arbitration Provision will not become part of the Agreement,
and the status of your Account will be unaffected by your rejection of
the Arbitration Provision." None of the plaintiffs rejected the arbitration
provision. Approximately 15 months later, in August 2002, the plaintiffs
filed this action. Providian filed a motion to compel arbitration
of all claims asserted by plaintiffs Screws, Richardson, and Shade.
The trial court denied the motion. HOLDING: The Supreme
Court reversed. The Court held that the plaintiffs' failure to reject
the arbitration provision within 45 days of receiving notice that it was
being added to their credit-card agreements amounted to acquiescence to
include the arbitration provision in their credit-card agreements.
The Court also held that the arbitration provision is not unconscionable.)
*Download or view
PDF version of opinion*
-
Ex parte Tiffin,
No. 1020898 (Ala.
Oct. 3, 2003)
(disqualification
of attorneys; shareholder-derivative claims; individual claims by minority
shareholders; standing; The minority shareholders of Tiffin Motor
Homes, Inc. ("TMH"), namely, J.M. Page, Darrell Harp, Grady Price, Ann
Vincent, David D. Deaton, and Kathryn B. Deaton (hereinafter collectively
referred to as the "minority shareholders") filed a 14-count complaint
against TMH and the majority shareholders in TMH, namely Robert A. Tiffin,
Jr., David Tiffin, Judy Tiffin, Timothy R. Tiffin, Van L. Tiffin, and Alex
B. Tiffin (hereinafter collectively referred to as "the Tiffins").
The first nine counts of the complaint were shareholder-derivative claims,
asserted on behalf of TMH, pursuant to Ala. R. Civ. P. 23.1, against the
Tiffins in their official capacities. The essence of those claims
was that the Tiffins had breached various duties to the corporation by
"causing the corporation to pay excessive prices for goods and services
to entities connected to the Tiffin family, by usurping business opportunities,
and by diverting incomes and profits to other related companies" ("the
derivative claims"). The remaining claims were against the Tiffins
in their individual capacities. In those claims, the minority shareholders
alleged that they had been "individually damaged by the [Tiffins'] actions."
More specifically, they averred that they had been "deprived of their just
share of the corporate gains"; that the Tiffins had "siphoned off and diverted
profits and dividends from [TMH]"; and that the Tiffins had "engaged in
a systematic scheme or design to 'squeeze out' the minority shareholders
of [TMH]" ("the minority-shareholder claims"). Sirote & Permutt,
P.C. ("Sirote"), undertook to represent the Tiffins, individually, in the
action, while the law firm of Bedford, Rogers & Bowling, P.C., represented
TMH in the action. On June 13, 2002, the trial court entered a partial
summary judgment for the Tiffins disposing of the derivative claims; that
judgment was made final pursuant to Rule 54(b), Ala. R. Civ. P., and is
no longer reviewable by appeal. On July 22, 2002, almost a year after
the complaint was filed and more than a month after the entry of the partial
summary judgment, the minority shareholders moved to disqualify Sirote
from representing the Tiffins. The motion alleged that "[a]t all
times relevant ..., [Sirote had] served as general counsel for [TMH]."
The motion also alleged that "in its capacity as counsel for TMH, [Sirote
had] provided legal advice and performed legal services with respect to
issues and transactions ... directly at issue." It further alleged
that Sirote's "continued representation" of the Tiffins constituted an
"irreconcilable conflict of interest" with TMH, as prohibited by Rule 1.7,
Ala. R. Prof. Conduct, and Rule 1.9, Ala. R. Prof. Conduct. The Tiffins
responded to the minority shareholders' motion to disqualify Sirote, arguing
that because Sirote was representing only them, individually, in the litigation,
the summary judgment on the derivative claims removed any purported conflict
of interest. The trial court granted the minority shareholders' motion,
and entered an order disqualifying Sirote from representing the Tiffins.
Subsequently, the Tiffins filed this mandamus petition, challenging that
order. HOLDING: The Supreme Court granted the writ of mandamus.
The Court noted that, as a general rule, courts do not disqualify
an attorney on the grounds of conflict of interest unless the current or
former client moves for disqualification, that the minority shareholders
had not shown a reason why the general rule should not apply in this case.
The Court concluded that the minority shareholders lack standing to seek
disqualification of Sirote.)
*Download or view
PDF version of opinion*
-
State of Alabama
v. Norris,
No. 1020953 (Ala.
Oct. 3, 2003)
(quo warranto; right
to hold office by felon whose civil and political rights have been restored;
The State of Alabama filed a quo warranto action to remove Huburt Norris
from the office of sheriff in Fayette County ("sheriff"). The trial
court entered summary judgment for Norris. The sole issue presented
by this appeal is whether, after a sheriff has been convicted of a felony
and removed from office for such conviction by operation of Ala. Code §36-9-2,
and thereafter has been pardoned with restoration of "all civil and political
rights which were forfeited as a result of the aforesaid conviction(s),"
the same Code section bars him from ever again holding the office of sheriff
even pursuant to a new election, sought and won after the pardon, to a
new term or part thereof. HOLDING: The Supreme Court
affirmed. The Court held that §36-9-2 does not bar the subsequent
holding of the office pursuant to the subsequent election.)
*Download or view
PDF version of opinion*
-
Polaris Sales, Inc.
v. Heritage Imports, Inc.,
No. 1021166 (Ala.
Oct. 3, 2003)
(arbitration; forum-selection
and choice-of-law clauses; unconscionability; Heritage and Polaris entered
into an agreement pursuant to which Heritage was appointed as a dealer
to sell certain Polaris products from its store in Fairhope and Polaris
agreed to sell those Polaris products to Heritage for resale to retail
customers ("the dealer agreement"). In the dealer agreement, Heritage and
Polaris contracted to arbitrate the following: "All disputes, controversies,
and claims arising out of or in connection with the ... interpretation
... of this Agreement, or of any provision of this Agreement (including
without limitation this arbitration provision and the arbitrability of
any issue), or arising out of or in connection with any claimed duty, right,
or remedy (whether arising under this Agreement or any statute, regulation,
ordinance, or other rule of law or otherwise) relating to any of the foregoing
...." This action began as an effort to collect money Heritage owed
Polaris Acceptance ("Acceptance"), arising out of Heritage's failure to
repay Acceptance for money Acceptance had advanced Heritage to purchase
inventory from Polaris. Heritage expanded the action by adding Polaris
as a third-party defendant and asserting a cross-claim against Polaris
and a counterclaim against Acceptance alleging intentional interference
with a contract. Heritage's cross-claim alleges that Heritage and
a third party entered into a contract pursuant to which the third party
agreed to purchase Heritage's recreational-vehicle dealership, its inventory,
and its franchise rights. This contract allegedly included a clause
stating that the transaction was contingent upon Polaris's approval.
Heritage claims that Polaris intentionally interfered with this contract
by inducing the third party to dishonor its contract with Heritage and
to contract directly with Polaris. Polaris moved the trial court
to compel arbitration of Heritage's cross-claim, based on the arbitration
provision in the dealer agreement. The trial court granted Polaris's
motion to compel arbitration and transferred the action to the administrative
docket pending the completion of arbitration. Approximately four
months later, Polaris moved the lower court to dismiss Heritage's cross-claim
against it on the ground that Heritage failed to prosecute its claim because
it had failed to initiate arbitration proceedings. In response to
Polaris's motion to dismiss, Heritage moved the court to dissolve the stay
and to reinstate the case on the active docket. The court, in response
to Heritage's motion, vacated its earlier order compelling arbitration.
Polaris appealed. HOLDING: The Supreme Court reversed.
The Court held that the requirement in the dealer agreement that the arbitration
proceeding take place in Minnesota and under Minnesota law is not unconscionable.
The Court further held that the plain language of the agreement unquestionably
shows that in this case Heritage and Polaris agreed to arbitrate the issue
of arbitrability and, therefore, any questions of arbitrability relating
to Heritage's claim are for an arbitrator to decide.)
*Download or view
PDF version of opinion*
-
Ex parte Leasecomm
Corp.,
No. 1021212 (Ala.
Oct. 3, 2003)
(outbound forum-selection
clause; fraudulent inducement; On June 8, 1999, Jeffrey R. Sisk, the owner
of Southern Belle Quick Stop convenience store, executed a "Non-Cancellable
Equipment Lease Agreement," pursuant to which he was to lease certain credit-card
processing equipment from Leasecomm Corporation, a Massachusetts corporation
registered to do business in Alabama. The lease agreement
contained the following paragraph just above Sisk's first signature on
the front page, typed in boldface and underlined: "The Parties hereby
agree that this Agreement is made in, governed by, to be performed in,
and shall be construed in accordance with the laws of the Commonwealth
of Massachusetts. They further consent and submit to the exclusive
jurisdiction of the Courts of the Commonwealth of Massachusetts and expressly
agree to such exclusive forum for the bringing of any suit, action or other
proceeding arising out of their obligations hereunder, and expressly waive
any objection to venue in any such Courts and waive any right to a trial
by jury so that trial shall be by and only to the Court. It is further
agreed and understood that the corporate headquarters of Leasecomm Corporation
is located within the venue of The District Court Department of the Trial
Court within Middlesex County." On January 3, 2002, after the credit-card
processing equipment had malfunctioned and Leasecomm had refused to repair
the equipment, Sisk sued Leasecomm in the Etowah Circuit Court, alleging
fraud in the inducement, continuing fraud, misrepresentation, and breach
of contract. Leasecomm moved to dismiss the complaint or, in the
alternative, to enforce the forum-selection clause in the agreement and
transfer the case to an appropriate court in Massachusetts.
After a hearing, the trial court denied Leasecomm's motion without making
any factual findings. HOLDING: The Supreme Court granted
the writ of mandamus. The Court concluded that Leasecomm has a clear
legal right to the enforcement of the outbound forum-selection clause because
Sisk did not clearly establish that Sisk was fraudulently induced to enter
into the agreement containing the clause.)
*Download or view
PDF version of opinion*
-
Ex parte Dillard
Dep't Stores, Inc.,
No. 1021239 (Ala.
Oct. 3, 2003)
(discovery; On November
19, 2000, Carrie Hardrick and Tina Irwin, while shopping at a Dillard department
store in Dothan, were detained by an off-duty Dothan police officer employed
by Dillard as a security officer because the officer thought they were
shoplifting. No merchandise was found on their persons, and they
were immediately released. Thereafter, Hardrick and Irwin sued Dillard
and the City of Dothan Police Department, alleging false imprisonment,
intentional infliction of emotional distress, and assault. The Dothan
Police Department was subsequently dismissed as a party, leaving Dillard
as the sole defendant. On August 21, 2002, Hardrick and Irwin requested
that Dillard, pursuant to Rule 34, Ala. R. Civ. P, produce documents in
connection with a deposition. Dillard did not object within 30 days.
The deposition was continued by agreement of the parties. However,
on September 11, 2002, Hardrick and Irwin refiled an identical request
for production. Dillard timely filed answers and objections to the
September 11 request. Hardrick and Irwin then filed a motion to compel
the production of the requested documents, which the trial court granted
on October 21, 2002, without holding a hearing. At Dillard's request,
the trial court immediately set aside its order. Dillard informed
the trial court that Hardrick and Irwin were seeking documents regarding
(1) all actions filed against Dillard; (2) all claims that did not result
in actions being filed; (3) all complaints and charges made by customers
and noncustomers regarding mistreatment by employees of Dillard; (4) all
customer complaints regarding the mistreatment of employees of Dillard
by other employees; and (5) all records regarding current and former employees
who had been accused of injuring, accusing, or detaining customers or other
employees. On March 24, 2003, after a hearing at which Dillard argued
its objections to the motion to compel, the trial court reinstated the
order compelling discovery. HOLDING: The Supreme Court
granted the petition for writ of mandamus. The Court declined Hardrick
and Irwin's request that we look solely to Dillard's failure to respond
to the first request and ignore the timely response to the second request,
stating that Rule 34 does not specifically provide that a failure to respond
within the time provided will result in a waiver of any objections.
The Court noted that Hardrick and Irwin made no attempt to defend the trial
court's discovery order on its merits, choosing only to resist on the basis
of procedural default. The Court further noted that Dillard showed
that there are more than 100 Dillard department stores throughout the United
States from which Hardrick and Irwin are requesting documents and
that the documents they are requesting are irrelevant to this case.
The Court concluded that the burden imposed on Dillard by the discovery
order is far out of proportion to any benefit Hardrick and Irwin would
obtain from the information requested and that, therefore, the trial court
exceeded its discretion in overruling Dillard's objections. The Court
left for the trial court the question whether discovery should be limited
to Dillard stores in Alabama or to the Dothan store.)
*Download or view
PDF version of opinion*
-
Ex parte McNabb,
No. 1021528 (Ala.
Oct. 3, 2003)
(criminal; appellate
procedure; mandamus; request for payment for transcript; Ruben Corey McNabb
was arrested and tried for robbery. His trial resulted in a deadlocked
jury and a mistrial. McNabb's attorney filed a motion for extraordinary
expenses to pay for a transcript of the trial. McNabb's attorney
stated that the transcript was needed for rebuttal and cross-examination
in McNabb's second trial. The cost of the transcript would have amounted
to $800. The trial court denied the motion. McNabb petitioned
the Court of Criminal Appeals for a writ of mandamus ordering the trial
court to approve payment of a trial transcript. The Court of Criminal
Appeals did not address the merits of the petition. Instead, the
Court of Criminal Appeals transferred the petition to the Supreme Court
to decide whether the Court of Criminal Appeals has jurisdiction to issue
writs of mandamus addressing the payment of extraordinary trial expenses.
HOLDING: The Supreme Court returned the petition to
the Court of Criminal Appeals because the transfer was improper. The Court
held that McNabb's petition does not present an issue that should have
been initially presented to the Supreme Court. The Court held that
because the Court of Criminal Appeals has jurisdiction to hear a petition
for the writ of mandamus "in relation to matters in which said court has
appellate jurisdiction" (§ 6.03), and because the right of a defendant
to a fair trial if the requested transcript is not available is an issue
as to which that court has appellate jurisdiction, the Court of Criminal
Appeals has jurisdiction to deal with the issue presented in McNabb's petition
filed before it.)
*Download or view
PDF version of opinion*
Disclaimer and note regarding opinion
formats: The Supreme Court of Alabama opinions
are now being released by the Court electronically in HTML (.htm) format
as well as in WordPerfect® 5.1 format (with a .rel extension).
We are converting the WordPerfect® files into Portable Document Format
(PDF) and posting the HTML and PDF files. The PDF files can be viewed
using Adobe® Acrobat® Reader™. If you don't have Adobe®
Acrobat® Reader™, you can download it free at www.adobe.com/products/acrobat/readstep2.html.
The link to the PDF version of the opinion will be at the end of the summary
as "*Download or view PDF version of opinion*." While these files
contain the text of the slip opinions released electronically by the Court,
please note that these may differ from the hard copy slip opinions in several
respects. Some, but not necessarily all, of these differences are
that in some of the electronic file formats the footnote numbers may be
in brackets, the text of the footnotes may be at the end of each opinion,
the pagination may not necessarily be the same, section and other symbols
may not appear correctly, and these opinions may not reflect some italicized,
bolded, underlined, or otherwise emphasized text that appears in the opinions
issued on paper. These opinions are released to the public by the
Court and are provided here as a convenience to visitors of our web site.
These opinions do not constitute legal advice. By making these opinions
available over the Internet, we by no means imply, nor should anyone infer,
that we have any connection with any governmental agency or court.
Please read the notice that appears at the top of each opinion. We
recommend obtaining from the Court a paper copy of any slip opinion before
citing to it in any document submitted to any governmental entity for legal
purposes. If you have any questions or comments about our posting
of these opinions, please contact the web administrator: webadmin@wallacejordan.com
Back to top
|